Minet Lesotho (Pty) Ltd v Ministry of Defence & National Security (C of A (CIV) 15 of 20) [2020] LSCA 27 (30 October 2020)

Minet Lesotho (Pty) Ltd v Ministry of Defence & National Security (C of A (CIV) 15 of 20) [2020] LSCA 27 (30 October 2020)

The signing of the contract during the suspension imposed by the procurement oversight body was grossly irregular and unlawful, violating mandatory procurement regulations. The entire tender process, including the award and contract, is invalid and must be set aside.

Source-derived case information.

Citation
[2020] LSCA 27
Parties
Appellant: Minet Lesotho (Pty) Ltd; Appellant: Lesotho National General Insurance Company Ltd; Respondent: Minister of Defence and National Security; Respondent: Principal Secretary, Ministry of Defence and National Security; Respondent: Procurement Policy and Advice Department, Ministry of Finance; Respondent: Alliance Insurance Company (Pty) Ltd; Respondent: Attorney General
Court
Court of Appeal
Jurisdiction
Lesotho
Case Number
C of A (CIV) 15 of 20
Procedural Posture
Civil Appeal / Judgment on Appeal
Outcome
appeal upheld
Legal Topics
Tender Process, Judicial Review, Public Contracts, Procurement Irregularity
Source Language
en
Public Procurement Administrative Law Tender Process Judicial Review Public Contracts Procurement Irregularity

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Minet Lesotho (Pty) Ltd

Appellant

Lesotho National General Insurance Company Ltd

Appellant

Minister of Defence and National Security

Respondent

Principal Secretary, Ministry of Defence and National Security

Respondent

Procurement Policy and Advice Department, Ministry of Finance

Respondent

Alliance Insurance Company (Pty) Ltd

Respondent

Attorney General

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal

  1. 1 Whether the signing of the contract during a suspended tender process was lawful
  2. 2 Whether the tender process and award were valid given procedural irregularities
  3. 3 Appropriate remedy for unlawful procurement actions

Ratio Decidendi

The signing of the contract during the suspension imposed by the procurement oversight body was grossly irregular and unlawful, violating mandatory procurement regulations. The entire tender process, including the award and contract, is invalid and must be set aside.

Court Disposition

appeal upheld

Orders

  • The appeal is upheld, with costs.
  • The order of the High Court is set aside.