YEOH WEOI LEONG & 248 OTHERS 1. ) HAJI AZMI BIN TAMAT (Disaman sebagai bekas Pengarah Negeri Jabatan Bomba dan Penyelamat Pulau Pinang) 2. ) PENGARAH NEGERI JABATAN BOMBA DAN PENYELAMAT PULAU PINANG 3. ) KETUA PENGARAH JABATAN BOMBA DAN PEN
The claim was dismissed because it was time-barred by section 2(a) of the Public Authorities Protection Act 1948 and, on the merits, the Plaintiffs failed to prove that the Two Release Letters were illegally issued, that Defendants breached statutory duties or acted with malice amounting to misfeasance in public office; inspections and certifications were carried out in accordance with approved plans and applicable law; consequential reliefs and damages were not proven.
- Citation
- PA-21NCC-1-09/2022 (Mahkamah Tinggi)
- Parties
- Plaintiffs: Various named plaintiffs (170 purchasers/owners of units in BM City Complex); Defendants: Haji Azmi bin Tamat; Pengarah Negeri Jabatan Bomba dan Penyelamat Pulau Pinang; Ketua Pengarah Jabatan Bomba dan Penyelamat Malaysia; Kerajaan Malaysia
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 16 August 2023
- Case Number
- PA-21NCC-1-09/2022 (Mahkamah Tinggi)
- Procedural Posture
- Civil Suit for Breach of Statutory Duty and Misfeasance in Public Office / Judgment After Full Trial
- Outcome
- Plaintiffs' claim dismissed
- Legal Topics
- Breach of Statutory Duty, Misfeasance in Public Office, Limitation Under Public Authorities Protection Act, Certification/certificate of Completion and Compliance (ccc), Fire Safety Regulation and Inspections
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Various named plaintiffs (170 purchasers/owners of units in BM City Complex)
Plaintiffs
Haji Azmi bin Tamat; Pengarah Negeri Jabatan Bomba dan Penyelamat Pulau Pinang; Ketua Pengarah Jabatan Bomba dan Penyelamat Malaysia; Kerajaan Malaysia
Defendants
Procedural Posture
Civil Suit for Breach of Statutory Duty and Misfeasance in Public Office / Judgment After Full Trial
Legal Issues
- 1 Whether the action was time-barred under section 2(a) of the Public Authorities Protection Act 1948
- 2 Whether the Two Release Letters (Form G8 and G9) were issued irregularly or illegally
- 3 Whether Defendants breached statutory duties under Street, Drainage and Building Act 1974 and UBBL
Ratio Decidendi
The claim was dismissed because it was time-barred by section 2(a) of the Public Authorities Protection Act 1948 and, on the merits, the Plaintiffs failed to prove that the Two Release Letters were illegally issued, that Defendants breached statutory duties or acted with malice amounting to misfeasance in public office; inspections and certifications were carried out in accordance with approved plans and applicable law; consequential reliefs and damages were not proven.
Court Disposition
Plaintiffs' claim dismissed
Orders
- Claims dismissed in full
- Plaintiffs to pay costs of RM10000 to the Defendants
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment