GRAND DYNAMIC BUILDERS SDN. BHD. DAMAI CITY SDN. BHD.
The court held the adjudication decision was valid despite being delivered after 45 working days because DCSB caused lawful suspension of proceedings via restraining orders and judicial management filings under Companies Act ss 368 and 410 which tolled the adjudication timeline and prevented continuation without court leave; the adjudicator acted within statutory powers (including rejecting a rejoinder) and properly dealt with issues including Interim Certificate No.24, hence there were no special circumstances or clear errors to set aside or stay the adjudication decision.
- Citation
- WA-24C-143-09/2024 (Mahkamah Tinggi)
- Parties
- Plaintiff (os139) / Defendant (os143): Damai City Sdn Bhd; Plaintiff (os143) / Defendant (os139): Grand Dynamic Builders Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 21 April 2025
- Case Number
- WA-24C-143-09/2024 (Mahkamah Tinggi)
- Procedural Posture
- Originating Summons Challenging and Enforcing CIPAA Adjudication Decision / Judgment on Originating Summonses (setting Aside, Stay and Enforcement)
- Outcome
- Dismissed: Enclosure 1 and Enclosure 11 in Originating Summons No. WA-24C-139-09/2024; Adjudication Decision dated 20.8.2024 upheld and enforcement/order in terms granted in Originating Summons No. WA-24C-143-09/2024.
- Legal Topics
- CIPAA Adjudication Timelines and Enforcement, Restraining Orders and Judicial Management Moratoriums, Interim Payment Certificates, Natural Justice and Procedure (rejoinder), Res Judicata, Stay Pending Arbitration
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Damai City Sdn Bhd
Plaintiff (os139) / Defendant (os143)
Grand Dynamic Builders Sdn Bhd
Plaintiff (os143) / Defendant (os139)
Procedural Posture
Originating Summons Challenging and Enforcing CIPAA Adjudication Decision / Judgment on Originating Summonses (setting Aside, Stay and Enforcement)
Legal Issues
- 1 Whether the adjudication decision delivered beyond 45 working days was void under section 12(3) CIPAA
- 2 Whether restraining orders and judicial management applications under Companies Act 2016 (ss 368 and 410) suspended or tolled CIPAA timelines
- 3 Whether Interim Certificate No.24 was payable/matured
Ratio Decidendi
The court held the adjudication decision was valid despite being delivered after 45 working days because DCSB caused lawful suspension of proceedings via restraining orders and judicial management filings under Companies Act ss 368 and 410 which tolled the adjudication timeline and prevented continuation without court leave; the adjudicator acted within statutory powers (including rejecting a rejoinder) and properly dealt with issues including Interim Certificate No.24, hence there were no special circumstances or clear errors to set aside or stay the adjudication decision.
Court Disposition
Dismissed: Enclosure 1 and Enclosure 11 in Originating Summons No. WA-24C-139-09/2024; Adjudication Decision dated 20.8.2024 upheld and enforcement/order in terms granted in Originating Summons No. WA-24C-143-09/2024.
Orders
- Dismiss Enclosure 1 in OS No. WA-24C-139-09/2024 with costs.
- Dismiss Enclosure 11 in OS No. WA-24C-139-09/2024 with costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment