EAKONMECH SDN BHD MAPLE STEEL SDN BHD
On the evidence the Adjudicator acted within the scope of the payment claim and the CIPAA: the L4/L5 smoke spill works were raised in the Payment Claim as variation/remeasurement works and supported by as-built drawings, the Adjudicator was entitled under s25(m) to adjust IPC No.11 including retention, and the parties were given directions and opportunities to submit so there was no denial of natural justice. Eakonmech failed to discharge the burden to set aside the adjudication decision under s15(b)/(d); the enforcement application under s28 is therefore allowed.
- Citation
- WA-24C-217-11/2022 (Mahkamah Tinggi)
- Parties
- Plaintiff (o.s. No. WA 24 C 217 11/2022); Defendant (o.s. No. WA 24 C 38 03/2023): Eakonmech Sdn Bhd; Defendant (o.s. No. WA 24 C 217 11/2022); Plaintiff (o.s. No. WA 24 C 38 03/2023): Maple Steel Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 25 July 2023
- Case Number
- WA-24C-217-11/2022 (Mahkamah Tinggi)
- Procedural Posture
- Originating Summons (setting Aside and Enforcement of Adjudication Decision) / Hearing and Final Judgment on Setting Aside Application and Enforcement Application; Setting Aside Dismissed and Enforcement Allowed
- Outcome
- Setting Aside Application dismissed; Enforcement Application allowed
- Legal Topics
- CIPAA Enforcement, Setting Aside Adjudication Decision, Jurisdiction of Adjudicator, Natural Justice, Variation Works, Retention Sums, Liquidated Damages, Costs
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Eakonmech Sdn Bhd
Plaintiff (o.s. No. WA 24 C 217 11/2022); Defendant (o.s. No. WA 24 C 38 03/2023)
Maple Steel Sdn Bhd
Defendant (o.s. No. WA 24 C 217 11/2022); Plaintiff (o.s. No. WA 24 C 38 03/2023)
Procedural Posture
Originating Summons (setting Aside and Enforcement of Adjudication Decision) / Hearing and Final Judgment on Setting Aside Application and Enforcement Application; Setting Aside Dismissed and Enforcement Allowed
Legal Issues
- 1 Whether the adjudicator acted in excess of jurisdiction by deciding Smoke Spill System works at Levels 4 and 5 alleged to be outside the contract
- 2 Whether the adjudicator exceeded jurisdiction in determining adjusted subcontract value and retention sum
- 3 Whether there was denial of natural justice through rewriting contract terms, imposing additional conditions for LAD, or depriving right to be heard on back-charges
Ratio Decidendi
On the evidence the Adjudicator acted within the scope of the payment claim and the CIPAA: the L4/L5 smoke spill works were raised in the Payment Claim as variation/remeasurement works and supported by as-built drawings, the Adjudicator was entitled under s25(m) to adjust IPC No.11 including retention, and the parties were given directions and opportunities to submit so there was no denial of natural justice. Eakonmech failed to discharge the burden to set aside the adjudication decision under s15(b)/(d); the enforcement application under s28 is therefore allowed.
Court Disposition
Setting Aside Application dismissed; Enforcement Application allowed
Orders
- Setting Aside Application dismissed with costs of RM7000.00 (subject to allocator)
- Enforcement Application allowed with costs of RM3000.00 (subject to allocator)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment