Kami Offshore Sdn. Bhd Norr System Hydraulics Pte. Ltd.
The court dismissed the appeal because the plaintiff proved the outstanding debt by invoices, statement of account and admissions; the OPA was ambiguous and did not operate as a back-to-back pay-if-paid clause; non-provision of the warranty bond was excused because commissioning was taken over by THHE and the delay/approval process was attributable to THHE; interest at 2% was enforceable as agreed in invoices; and LAD was not recoverable because the delay was caused by THHE approvals constituting a valid exemption from the compensation clause.
- Citation
- JA-12B-54-11/2019 (Mahkamah Tinggi)
- Parties
- Appellant/defendant: KAMI OFFSHORE SDN BHD; Respondent/plaintiff: NORR SYSTEM HYDRAULICS PTE LTD
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 11 August 2020
- Case Number
- JA-12B-54-11/2019 (Mahkamah Tinggi)
- Procedural Posture
- Civil Appeal / High Court Judgment on Appeal From Sessions Court
- Outcome
- Appeal dismissed; judgment entered for Respondent (Plaintiff)
- Legal Topics
- Payment Dispute, Pay If Paid / Pay When Paid Clauses, Collateral/outstanding Payment Agreement, Liquidated Damages, Interest on Late Payment, Unjust Enrichment, Warranty Bond / Commissioning
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
KAMI OFFSHORE SDN BHD
Appellant/defendant
NORR SYSTEM HYDRAULICS PTE LTD
Respondent/plaintiff
Procedural Posture
Civil Appeal / High Court Judgment on Appeal From Sessions Court
Legal Issues
- 1 Whether the Outstanding Payment Agreement (OPA) created a back-to-back pay-if-paid obligation preventing plaintiff’s claim
- 2 Whether plaintiff entitled to outstanding milestone payments and contractual interest despite lack of warranty bond and incomplete commissioning
- 3 Whether allowing plaintiff’s claim would result in unjust enrichment
Ratio Decidendi
The court dismissed the appeal because the plaintiff proved the outstanding debt by invoices, statement of account and admissions; the OPA was ambiguous and did not operate as a back-to-back pay-if-paid clause; non-provision of the warranty bond was excused because commissioning was taken over by THHE and the delay/approval process was attributable to THHE; interest at 2% was enforceable as agreed in invoices; and LAD was not recoverable because the delay was caused by THHE approvals constituting a valid exemption from the compensation clause.
Court Disposition
Appeal dismissed; judgment entered for Respondent (Plaintiff)
Orders
- Appeal dismissed
- Judgment for the Respondent for USD183,477.88
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment