1. ) NG SOCK FOON 2. ) LIM KIM KEANG 3. ) YEN JEAN SIANG 4. ) LEE SUVEN 5. ) KONG LAI HOONG 6. ) LEE JIA MIN 7. ) ADINO GIAM LIP GHEE 8. ) PREM KUMAR A/L MARIAPPAN 9. ) PRAKASH KUMAR A/L MARIAPPAN 10. ) NAVANITHAN A/L RADZAKRISNAN 11. ) SUM
The court applied binding Federal Court and Court of Appeal authorities to hold that (1) delivery of vacant possession for LAD computation commences from the booking fee/deposit; (2) any extension of the Schedule H 36-month completion period effected via controller approval is ultra vires and the 36-month period governs; (3) the apex court decisions operate retrospectively; and (4) claims against the 93rd and 94th defendants fail because their actions were bona fide and protected by HDA s17 and G.P. Act s29, therefore the plaintiffs succeed and the defendant's counterclaim is dismissed.
- Citation
- BA-22NCvC-179-04/2021 (Mahkamah Tinggi)
- Parties
- Plaintiff (original); Defendant (counterclaim): NG SOOK FOON & others (92 purchasers); Defendant (original); Plaintiff (counterclaim): MARIMO LAND SDN BHD; 93rd Defendant (in Counterclaim): Kementerian Perumahan dan Kerajaan Tempatan; 94th Defendant (in Counterclaim): Pengawal Perumahan
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 4 July 2022
- Case Number
- BA-22NCvC-179-04/2021 (Mahkamah Tinggi)
- Procedural Posture
- Civil Housing Development / Contract Dispute With Counterclaim / Judgment Determining Questions of Law Under Order 14 a Ro C (final Disposition)
- Outcome
- Plaintiffs' claim allowed; Defendant's counterclaim dismissed; counterclaim against 93rd and 94th defendants unsustainable
- Legal Topics
- Sale and Purchase Agreement (schedule H), Liquidated Ascertainable Damages (lad), Ultra Vires Modification of Statutory Form, Retrospectivity of Judicial Decisions, Indemnity and Protection of Public Officers
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
NG SOOK FOON & others (92 purchasers)
Plaintiff (original); Defendant (counterclaim)
MARIMO LAND SDN BHD
Defendant (original); Plaintiff (counterclaim)
Kementerian Perumahan dan Kerajaan Tempatan
93rd Defendant (in Counterclaim)
Pengawal Perumahan
94th Defendant (in Counterclaim)
Procedural Posture
Civil Housing Development / Contract Dispute With Counterclaim / Judgment Determining Questions of Law Under Order 14 a Ro C (final Disposition)
Legal Issues
- 1 Whether delivery of vacant possession commences from booking fee payment or date of SPA
- 2 Whether parties are bound by SPA where completion period was modified from 36 to 48 months via Regulation 11(3)
- 3 Whether purchasers can rely on original Schedule H 36-month completion period to claim LAD
Ratio Decidendi
The court applied binding Federal Court and Court of Appeal authorities to hold that (1) delivery of vacant possession for LAD computation commences from the booking fee/deposit; (2) any extension of the Schedule H 36-month completion period effected via controller approval is ultra vires and the 36-month period governs; (3) the apex court decisions operate retrospectively; and (4) claims against the 93rd and 94th defendants fail because their actions were bona fide and protected by HDA s17 and G.P. Act s29, therefore the plaintiffs succeed and the defendant's counterclaim is dismissed.
Court Disposition
Plaintiffs' claim allowed; Defendant's counterclaim dismissed; counterclaim against 93rd and 94th defendants unsustainable
Orders
- Declaration that delivery of vacant possession for LAD calculation commences from date of booking fee/deposit and that Schedule H 36-month completion period applies
- Federal Court decisions in Ang Ming Lee and PJD Regency apply retrospectively
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment