MAJLIS DAERAH CAMERON HIGHLANDS PUTRA NILAI BUILDERS SDN BHD
The High Court set aside the Adjudication Decision because the adjudicator committed a material breach of natural justice by deciding a new alternative basis for PNB's loss and expense claim that was first raised in the adjudication reply without giving the Council an opportunity to respond, and because the adjudicator acted in excess of his jurisdiction by ordering reimbursement of LAD which falls outside CIPAA's definition of 'payment'; accordingly the enforcement application was dismissed.
- Citation
- WA-24C-138-08/2021 (Mahkamah Tinggi)
- Parties
- Plaintiff in O.s. No. WA 24 C 129 08/2021; Defendant in O.s. No. WA 24 C 138 08/2021: Putra Nilai Builders Sdn Bhd; Plaintiff in O.s. No. WA 24 C 138 08/2021; Defendant in O.s. No. WA 24 C 129 08/2021: Majlis Daerah Cameron Highlands
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 12 November 2021
- Case Number
- WA-24C-138-08/2021 (Mahkamah Tinggi)
- Procedural Posture
- Originating Summons Under CIPAA (setting Aside and Enforcement of Adjudication Decision) / High Court Judgment on Competing Applications to Set Aside and Enforce Adjudication Decision
- Outcome
- Council's setting aside application allowed; Putra Nilai Builders' enforcement application dismissed; Adjudication Decision set aside.
- Legal Topics
- Setting Aside Adjudication Decision, Enforcement of Adjudication Decision, Natural Justice in Adjudication, Adjudicator Jurisdiction Limits, Liquidated Ascertained Damages, Extension of Time, Loss and Expense Claims, Interpretation of CIPAA
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Putra Nilai Builders Sdn Bhd
Plaintiff in O.s. No. WA 24 C 129 08/2021; Defendant in O.s. No. WA 24 C 138 08/2021
Majlis Daerah Cameron Highlands
Plaintiff in O.s. No. WA 24 C 138 08/2021; Defendant in O.s. No. WA 24 C 129 08/2021
Procedural Posture
Originating Summons Under CIPAA (setting Aside and Enforcement of Adjudication Decision) / High Court Judgment on Competing Applications to Set Aside and Enforce Adjudication Decision
Legal Issues
- 1 Whether the adjudicator breached natural justice by deciding a new/alternative claim first raised in the adjudication reply without giving the respondent opportunity to comment
- 2 Whether the adjudicator acted in excess of jurisdiction by deciding an award for loss and expense on a new basis not raised in the payment claim/adjudication claim
- 3 Whether the adjudicator acted in excess of jurisdiction by ordering reimbursement of Liquidated Ascertained Damages (LAD) which fall outside the definition of 'payment' under CIPAA
Ratio Decidendi
The High Court set aside the Adjudication Decision because the adjudicator committed a material breach of natural justice by deciding a new alternative basis for PNB's loss and expense claim that was first raised in the adjudication reply without giving the Council an opportunity to respond, and because the adjudicator acted in excess of his jurisdiction by ordering reimbursement of LAD which falls outside CIPAA's definition of 'payment'; accordingly the enforcement application was dismissed.
Court Disposition
Council's setting aside application allowed; Putra Nilai Builders' enforcement application dismissed; Adjudication Decision set aside.
Orders
- Adjudication Decision dated 25.6.2021 set aside
- PNB to pay costs to the Council of MYR 5,000.00 for each application (subject to allocatur)
Full Case Text
Judgment text and source record