1. ) TRI METAL MINING SDN. BHD. 2. ) MAHANG QUARRY SDN. BHD. 3. ) CHUNG NYAP YOON SDN. BHD. 1. ) HILMAN KUARI SDN BHD 2. ) JVC EMAS SDN BHD
Defendants materially breached both agreements by failing to obtain and maintain the statutory permits and approvals required by the contracts (no Form 4C for Plot A and no valid EIA for PT 388); under the Supplementary Agreement termination of one agreement caused the other to terminate; therefore plaintiffs validly terminated, plaintiffs proven losses recoverable as assessed, injunctions denied where plaintiffs had removed equipment, and defendants' counterclaim dismissed.
- Citation
- PA-22NCvC-207-09/2019 (Mahkamah Tinggi)
- Parties
- 1st Plaintiff: Tri Metal Mining Sdn Bhd; 2nd Plaintiff: Mahang Quarry Sdn Bhd; 3rd Plaintiff: Chung Nyap Yoon Sdn Bhd; 1st Defendant: Hilman Quarry Sdn Bhd; 2nd Defendant: JVC Emas Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 28 September 2022
- Case Number
- PA-22NCvC-207-09/2019 (Mahkamah Tinggi)
- Procedural Posture
- Civil Breach of Contract / Judgment After Full Trial
- Outcome
- Plaintiffs' termination of TMMSB and MQSB held valid; 1st and 2nd plaintiffs awarded specified sums; 3rd plaintiff's injunctions dismissed; defendants' counterclaim dismissed; costs awarded as ordered.
- Legal Topics
- Termination of Contract, Assessment of Damages, Mandatory and Prohibitory Injunctions, Statutory Permits and Approvals (form 4 C, Eia), Contractual Interpretation
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Tri Metal Mining Sdn Bhd
1st Plaintiff
Mahang Quarry Sdn Bhd
2nd Plaintiff
Chung Nyap Yoon Sdn Bhd
3rd Plaintiff
Hilman Quarry Sdn Bhd
1st Defendant
JVC Emas Sdn Bhd
2nd Defendant
Procedural Posture
Civil Breach of Contract / Judgment After Full Trial
Legal Issues
- 1 Whether the TMMSB Agreement was validly terminated by the 1st plaintiff
- 2 Whether the MQSB Agreement was validly terminated by the 2nd plaintiff (including effect of Supplementary Agreement)
- 3 Whether defendants breached obligations to obtain statutory permits (Form 4C and EIA)
Ratio Decidendi
Defendants materially breached both agreements by failing to obtain and maintain the statutory permits and approvals required by the contracts (no Form 4C for Plot A and no valid EIA for PT 388); under the Supplementary Agreement termination of one agreement caused the other to terminate; therefore plaintiffs validly terminated, plaintiffs proven losses recoverable as assessed, injunctions denied where plaintiffs had removed equipment, and defendants' counterclaim dismissed.
Court Disposition
Plaintiffs' termination of TMMSB and MQSB held valid; 1st and 2nd plaintiffs awarded specified sums; 3rd plaintiff's injunctions dismissed; defendants' counterclaim dismissed; costs awarded as ordered.
Orders
- Defendants ordered to pay RM823,430.15 to 1st plaintiff comprising RM377,294.84 mobilisation costs, RM298,661.72 operating costs, RM125,473.59 idling costs and RM22,000.00 deposits/other payments; interest at 5% per annum from date of filing to date of full settlement; costs RM30,000.00 subject to allocator fee.
- 1st plaintiff's claim for RM212,725.24 for seized stockpile sand dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment