BETANAZ PROPERTIES SDN BHD AEON CO. (M) BHD PIHAK KETIGA Ahmad Zaki Resources Berhad PIHAK TERKILAN MUFG BANK (MALAYSIA) BERHAD
On the evidence Betanaz and AZRB fulfilled their respective obligations: AZRB achieved practical completion of the bridge section and government CPC was issued within the EOT and Betanaz delivered vacant possession; AEON failed to secure its CPs and elected not to perform, thereby repudiating the TA; the unsigned lease annexure lacked execution and binding effect; Betanaz’s alternative claim for wasted expenditure was justified and proven; AEON’s counterclaim and bank guarantee action were without merit and dismissed.
- Citation
- WA-22NCvC-121-03/2021 (Mahkamah Tinggi)
- Parties
- Plaintiff (original); Defendant (counterclaim): Betanaz Properties Sdn Bhd; Defendant (original); Plaintiff (counterclaim): AEON Co. (M) Bhd; Defendant (counterclaim): Ahmad Zaki Resources Berhad
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 16 December 2024
- Case Number
- WA-22NCvC-121-03/2021 (Mahkamah Tinggi)
- Procedural Posture
- Civil (contract; Specific Relief; Construction; Banking Guarantee) / Final Judgment (trial Concluded)
- Outcome
- Final judgment for Betanaz on alternative claim (wasted expenditure); AEON's counterclaim dismissed; Bank Guarantee proceeding dismissed; costs awarded against AEON
- Legal Topics
- Termination of Contract, Condition Precedent, Repudiation, Wasted Expenditure (reliance Losses), On Demand Banker's Guarantee, Injunctions, Enforceability of Unsigned Draft Contract, Estoppel and Non Waiver Clauses, Certification: CPC Vs CCC, Costs
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Betanaz Properties Sdn Bhd
Plaintiff (original); Defendant (counterclaim)
AEON Co. (M) Bhd
Defendant (original); Plaintiff (counterclaim)
Ahmad Zaki Resources Berhad
Defendant (counterclaim)
Procedural Posture
Civil (contract; Specific Relief; Construction; Banking Guarantee) / Final Judgment (trial Concluded)
Legal Issues
- 1 Whether tenancy agreement and commercial agreement were void for non-fulfilment of conditions precedent
- 2 Whether AZRB completed bridge obligations under the CA and whether completion satisfied obligations
- 3 Whether AEON lawfully terminated the TA and CA or repudiated them
Ratio Decidendi
On the evidence Betanaz and AZRB fulfilled their respective obligations: AZRB achieved practical completion of the bridge section and government CPC was issued within the EOT and Betanaz delivered vacant possession; AEON failed to secure its CPs and elected not to perform, thereby repudiating the TA; the unsigned lease annexure lacked execution and binding effect; Betanaz’s alternative claim for wasted expenditure was justified and proven; AEON’s counterclaim and bank guarantee action were without merit and dismissed.
Court Disposition
Final judgment for Betanaz on alternative claim (wasted expenditure); AEON's counterclaim dismissed; Bank Guarantee proceeding dismissed; costs awarded against AEON
Orders
- Judgment against AEON for wasted expenditure of RM18,678,255.27 with 5% per annum interest until full realisation
- AEON to pay Betanaz global costs of RM200,000.00 within 45 days
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment