1. ) ABDUL HAZIQ BIN MATLAN 2. ) ABDULLAH SANI BIN SAAD & MIZALAWATI BINTI MUHARRUDIN 3. ) AZLINDAWATI BINTI PANDAK MAT YUSOP 4. ) BHARATHI A/L KRISHNAKUMAR 5. ) DANIAL FITRI BIN NORIZAM & SITI NOR ATIQAH BINTI AZIZAN 6. ) DEE DE FANDEE BIN

1. ) ABDUL HAZIQ BIN MATLAN 2. ) ABDULLAH SANI BIN SAAD & MIZALAWATI BINTI MUHARRUDIN 3. ) AZLINDAWATI BINTI PANDAK MAT YUSOP 4. ) BHARATHI A/L KRISHNAKUMAR 5. ) DANIAL FITRI BIN NORIZAM & SITI NOR ATIQAH BINTI AZIZAN 6. ) DEE DE FANDEE BIN

Court held that LAD is calculated from the date of the booking fee/payment (date of the bargain) as established in PJD Regency, concludes LAD ends on date of notice of delivery supported by Certificate of Completion and Compliance (18-3-2024), the 153-day EOT granted under s38C Covid-19 Act applies across the...

Source-derived case information.

Citation
BA-22NCvC-235-06/2024 (Mahkamah Tinggi)
Parties
Plaintiff: Abdul Haziq bin Matlan & 76 others; Defendant: Zestran Sdn. Bhd.; Defendant: Delisprings Land Sdn. Bhd.
Court
High Court
Jurisdiction
Malaysia
Judgment Date
6 August 2025
Case Number
BA-22NCvC-235-06/2024 (Mahkamah Tinggi)
Procedural Posture
Civil Representative Action for Liquidated Ascertained Damages / Judgment
Outcome
Plaintiffs' claims allowed in part
Legal Topics
Liquidated Ascertained Damages, Computation of Damages, Booking Fee as Formation of Contract, Extension of Time Under Covid 19 Act, Certificate of Completion and Compliance, Rebate/discount Impact on Damages
Contract Law Housing Law Property Law Consumer Protection Emergency/covid 19 Legislation Liquidated Ascertained Damages Computation of Damages Booking Fee as Formation of Contract +3 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Abdul Haziq bin Matlan & 76 others

Plaintiff

Zestran Sdn. Bhd.

Defendant

Delisprings Land Sdn. Bhd.

Defendant

Procedural Posture

Civil Representative Action for Liquidated Ascertained Damages / Judgment

  1. 1 Whether the start date for LAD is the booking fee payment date or the SPA date
  2. 2 Whether the end date for LAD is the date of notice of vacant possession accompanied by the Certificate of Completion and Compliance
  3. 3 Whether the Ministerial EOT under s38C Covid-19 Act applies to all purchasers in a development or only to individual SPAs entered into before 31-5-2021

Ratio Decidendi

Court held that LAD is calculated from the date of the booking fee/payment (date of the bargain) as established in PJD Regency, concludes LAD ends on date of notice of delivery supported by Certificate of Completion and Compliance (18-3-2024), the 153-day EOT granted under s38C Covid-19 Act applies across the project because the first agreement for the development predates 31-5-2021, LAD must be calculated on the full purchase price (not discounted price), and PW1 was properly authorised to represent the plaintiffs.

Court Disposition

Plaintiffs' claims allowed in part

Orders

  • Declaration that plaintiffs are entitled to liquidated ascertained damages at 10% per annum of the purchase price stated in the SPA
  • Declaration that plaintiffs are entitled to compute and claim LAD from the date of payment of the booking fee/deposit, taking into account the statutory development period of 24 months plus an extension of time of 153 days, and ending on the date of issuance of the Certificate of Completion and Compliance (Form F)...