ASTINAS CONSTRUCTION & DEVELOPMENT SDN BHD GINMIT TRADING SDN BHD

ASTINAS CONSTRUCTION & DEVELOPMENT SDN BHD GINMIT TRADING SDN BHD

Clause 24 of the SPA is clear and must be read as setting the 24-month period from the later of the date of proposed building plan approval by the local authority or the date of the agreement; commencement of works without approval and failure to inform did not create a representation or sufficient basis for...

Source-derived case information.

Citation
JA-12BNCvC-11-06/2022 (Mahkamah Tinggi)
Parties
Appellant: Astinas Construction & Development Sdn Bhd; Respondent: Ginmit Trading Sdn Bhd
Court
High Court
Jurisdiction
Malaysia
Judgment Date
14 May 2023
Case Number
JA-12BNCvC-11-06/2022 (Mahkamah Tinggi)
Procedural Posture
Civil Appeal / Judgment (high Court)
Outcome
Appeal allowed; Sessions Court decision set aside; Plaintiff's claim dismissed with costs.
Legal Topics
Interpretation of Contract Clauses, Liquidated Ascertained Damages, Estoppel, Illegality / Ex Turpi Causa, Building Plan Approval
Contract Law Construction Law Property Law Administrative Law Interpretation of Contract Clauses Liquidated Ascertained Damages Estoppel Illegality / Ex Turpi Causa +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Astinas Construction & Development Sdn Bhd

Appellant

Ginmit Trading Sdn Bhd

Respondent

Procedural Posture

Civil Appeal / Judgment (high Court)

  1. 1 Whether the 24-month period for delivery of vacant possession is calculated from the date of the SPA or from the date of building plan approval by the local authority
  2. 2 Whether the defendant is estopped from relying on the approval date due to commencing works without approval and failing to inform the purchaser
  3. 3 Whether illegality arising from commencing works without approval prevents the defendant from relying on contractual defences or avoids the SPA

Ratio Decidendi

Clause 24 of the SPA is clear and must be read as setting the 24-month period from the later of the date of proposed building plan approval by the local authority or the date of the agreement; commencement of works without approval and failure to inform did not create a representation or sufficient basis for estoppel nor render the contract unenforceable; the Vendor was therefore within the 24-month period (approval 4.10.2013; vacant possession 22.5.2014) and the Sessions Court’s finding awarding LAD was reversed.

Court Disposition

Appeal allowed; Sessions Court decision set aside; Plaintiff's claim dismissed with costs.

Orders

  • Allow appeal
  • Set aside Sessions Court judgment