WA-22NCC-347-06/2019 (Mahkamah Tinggi)

WA-22NCC-347-06/2019 (Mahkamah Tinggi)

Court found a binding contract existed governed by the tender documents and KFN002/2018; FIAM terms did not apply and the alleged 21 December 2017 agreement and its timetable were not authentic or communicated to the plaintiff; delivery period extended to 30 September 2018 under the akuan, defendant accepted...

Source-derived case information.

Citation
WA-22NCC-347-06/2019 (Mahkamah Tinggi)
Parties
Plaintiff: Baja Niaga Sdn Bhd; Defendant: Felcra Niaga Sdn Bhd
Court
High Court
Jurisdiction
Malaysia
Judgment Date
1 April 2022
Case Number
WA-22NCC-347-06/2019 (Mahkamah Tinggi)
Procedural Posture
Civil Suit Commercial Contract Dispute / High Court Final Judgment (trial Concluded)
Outcome
Judgment for Plaintiff on principal claim; Defendant's counterclaim dismissed
Legal Topics
Formation of Contract, Course of Dealing, Delivery Obligations, Time of the Essence, Late Delivery Penalty, Late Payment Interest, Authenticity of Documents, Acceptance and Acquiescence
Contract Law Commercial Law Evidence Law Procurement Law Sale of Goods Formation of Contract Course of Dealing Delivery Obligations +5 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 9 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Baja Niaga Sdn Bhd

Plaintiff

Felcra Niaga Sdn Bhd

Defendant

Procedural Posture

Civil Suit Commercial Contract Dispute / High Court Final Judgment (trial Concluded)

  1. 1 Whether there was a binding contract and which documents/terms governed it
  2. 2 Whether the Plaintiff delivered the goods within the applicable deadlines
  3. 3 Whether the Defendant is entitled to claim late delivery penalties and quantum

Ratio Decidendi

Court found a binding contract existed governed by the tender documents and KFN002/2018; FIAM terms did not apply and the alleged 21 December 2017 agreement and its timetable were not authentic or communicated to the plaintiff; delivery period extended to 30 September 2018 under the akuan, defendant accepted deliveries without protest so time became at large and defendant acquiesced to any delays; defendant therefore not entitled to late delivery penalty and plaintiff entitled to principal claim of RM4,138,780.60 but not to FIAM late payment interest or SOGA interest.

Court Disposition

Judgment for Plaintiff on principal claim; Defendant's counterclaim dismissed

Orders

  • Judgment entered for the Plaintiff for the principal sum of RM4,138,780.60
  • Defendant's counterclaim for late delivery penalty dismissed