BINACHUAN SDN. BHD. AKS SEPAKAT SDN. BHD.
Court admitted ID3 as P3 relying on s.90A(6) and hearsay exception s.32(1)(b) together with s.73A and SP1's contemporaneous knowledge; contemporaneous invoices and account summaries established that Defendant made progressive payments but did not pay in full; conversion calculations were consistently expressed and accepted in cubic metres during the relevant period; Defendant failed to prove full payment or the counterclaim and raised issues late; accordingly Plaintiff's claim of RM94,668.78 succeeded and Defendant's appeal and counterclaim were dismissed.
- Citation
- JA-A72NCC-433-05/2020 (Mahkamah Majistret)
- Parties
- Plaintiff: BINACHUAN SDN. BHD.; Defendant: AKS SEPAKAT SDN. BHD.
- Court
- Magistrates' Court
- Jurisdiction
- Malaysia
- Judgment Date
- 7 April 2022
- Case Number
- JA-A72NCC-433-05/2020 (Mahkamah Majistret)
- Procedural Posture
- Civil Contract Claim for Supply of Goods (debt Recovery) / Judgment at Full Trial (appeal by Defendant Dismissed)
- Outcome
- Appeal dismissed; judgment entered for Plaintiff and Defendant's counterclaim dismissed
- Legal Topics
- Admissibility of Computer Generated Documents, Breach of Contract, Conversion Factor Dispute (metric Ton to Cubic Metre), Debt Recovery, Counterclaim for Consequential Loss, Assessment of Damages, Interest and Costs
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
BINACHUAN SDN. BHD.
Plaintiff
AKS SEPAKAT SDN. BHD.
Defendant
Procedural Posture
Civil Contract Claim for Supply of Goods (debt Recovery) / Judgment at Full Trial (appeal by Defendant Dismissed)
Legal Issues
- 1 Admissibility of ID3 (computer‑generated statement) without s.90A certificate
- 2 Whether Defendant had paid in full
- 3 Quantum of outstanding debt
Ratio Decidendi
Court admitted ID3 as P3 relying on s.90A(6) and hearsay exception s.32(1)(b) together with s.73A and SP1's contemporaneous knowledge; contemporaneous invoices and account summaries established that Defendant made progressive payments but did not pay in full; conversion calculations were consistently expressed and accepted in cubic metres during the relevant period; Defendant failed to prove full payment or the counterclaim and raised issues late; accordingly Plaintiff's claim of RM94,668.78 succeeded and Defendant's appeal and counterclaim were dismissed.
Court Disposition
Appeal dismissed; judgment entered for Plaintiff and Defendant's counterclaim dismissed
Orders
- Defendant to pay Plaintiff RM94,668.78
- Interest at 5% per annum on the claim from date of filing of the writ to date of judgment
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment