BUMI JELAPANG CORPORATION SDN. BHD. Kerajaan Negeri Kedah

BUMI JELAPANG CORPORATION SDN. BHD. Kerajaan Negeri Kedah

Court found an implied contract existed from the parties’ conduct and documents; termination by Defendant was wrongful because delays were substantially caused by Defendant (late possession, delayed variations, refusal of EOT and premature opening to public); Plaintiff completed 78% but received only 29.37% of...

Source-derived case information.

Citation
KA-21C-1-11/2018 (Mahkamah Tinggi)
Parties
Plaintiff: BUMI JELAPANG CORPORATION SDN BHD; Defendant: THE GOVERNMENT OF THE STATE OF KEDAH DARUL AMAN
Court
High Court
Jurisdiction
Malaysia
Judgment Date
21 October 2024
Case Number
KA-21C-1-11/2018 (Mahkamah Tinggi)
Procedural Posture
Civil Contract / Judgment
Outcome
Judgment for Plaintiff
Legal Topics
Wrongful Termination, Quantum Meruit, Estoppel, Extension of Time, Counterclaim
Contract Law Construction Law Equity (estoppel) Remedies and Damages Wrongful Termination Quantum Meruit Estoppel Extension of Time +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 14 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

BUMI JELAPANG CORPORATION SDN BHD

Plaintiff

THE GOVERNMENT OF THE STATE OF KEDAH DARUL AMAN

Defendant

Procedural Posture

Civil Contract / Judgment

  1. 1 Whether a valid and binding contract (express or implied) existed between the parties
  2. 2 Whether the termination of the contract by the Defendant was lawful
  3. 3 Whether the delays were attributable to the Plaintiff or to the Defendant

Ratio Decidendi

Court found an implied contract existed from the parties’ conduct and documents; termination by Defendant was wrongful because delays were substantially caused by Defendant (late possession, delayed variations, refusal of EOT and premature opening to public); Plaintiff completed 78% but received only 29.37% of contract sum and is therefore entitled under quantum meruit and estoppel to RM8,581,654.18; Defendant’s counterclaim was unproven and dismissed; interest and costs awarded.

Court Disposition

Judgment for Plaintiff

Orders

  • Defendant to pay Plaintiff RM8,581,654.18
  • Interest at 5% per annum from date of filing of the writ until full realisation