CRCC MALAYSIA BERHAD 1. ) M101 ENTITY SDN BHD 2. ) M101 HOLDINGS SDN BHD 3. ) YAP TING HAU, DATO' 4. ) DATIN CHAN HENG SI
On the evidence the plaintiff proved breach of contract by the 1st Defendant through failure to pay certified interim sums; the expiry of the performance bond did not justify withholding payment where defendant had not promptly raised the issue and sought to rely on it only after defaulting on payments; the purported Line of Credit arrangement was not contractually concluded and could not defeat the plaintiff's claim; the plaintiff's suspension was contractually justified and the defendant's termination was wrongful—consequently judgment was entered for the plaintiff against the 1st Defendant for RM38,277,862.45 with interest and costs, while claims against the 2nd, 3rd and 4th Defendants...
- Citation
- WA-22C-70-07/2020 (Mahkamah Tinggi)
- Parties
- Plaintiff: CRCC Malaysia Berhad; 1st Defendant: M101 Entity Sdn Bhd; 2nd Defendant: M101 Holdings Sdn Bhd; 3rd Defendant: Dato' Yap Ting Hau; 4th Defendant: Datin Chan Heng Si
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 15 May 2024
- Case Number
- WA-22C-70-07/2020 (Mahkamah Tinggi)
- Procedural Posture
- Civil Construction Contract Dispute (breach of Contract, Variations, Performance Bond, Directors' Allegations) / High Court Judgment on Liability and Quantum (trial)
- Outcome
- Judgment for Plaintiff CRCC Malaysia Berhad against 1st Defendant M101 Entity Sdn Bhd for RM38,277,862.45 plus interest; Plaintiff's claims against 2nd, 3rd and 4th Defendants dismissed.
- Legal Topics
- Performance Bond, Suspension and Termination of Contract, Variation Orders and Quantum, Contractual Interest, Director Duties and Piercing Corporate Veil, Misrepresentation and Estoppel, Adjudication/cipaa Issues
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
CRCC Malaysia Berhad
Plaintiff
M101 Entity Sdn Bhd
1st Defendant
M101 Holdings Sdn Bhd
2nd Defendant
Dato' Yap Ting Hau
3rd Defendant
Datin Chan Heng Si
4th Defendant
Procedural Posture
Civil Construction Contract Dispute (breach of Contract, Variations, Performance Bond, Directors' Allegations) / High Court Judgment on Liability and Quantum (trial)
Legal Issues
- 1 Whether plaintiff entitled to payment for works done and variations
- 2 Whether defendant validly withheld payment for expired performance bond
- 3 Whether plaintiff validly suspended works and whether defendant lawfully terminated contract
Ratio Decidendi
On the evidence the plaintiff proved breach of contract by the 1st Defendant through failure to pay certified interim sums; the expiry of the performance bond did not justify withholding payment where defendant had not promptly raised the issue and sought to rely on it only after defaulting on payments; the purported Line of Credit arrangement was not contractually concluded and could not defeat the plaintiff's claim; the plaintiff's suspension was contractually justified and the defendant's termination was wrongful—consequently judgment was entered for the plaintiff against the 1st Defendant for RM38,277,862.45 with interest and costs, while claims against the 2nd, 3rd and 4th Defendants...
Court Disposition
Judgment for Plaintiff CRCC Malaysia Berhad against 1st Defendant M101 Entity Sdn Bhd for RM38,277,862.45 plus interest; Plaintiff's claims against 2nd, 3rd and 4th Defendants dismissed.
Orders
- 1. Judgment entered for the Plaintiff against the 1st Defendant in the sum of RM38,277,862.45 (being RM37,694,650.97 for works done; RM2,780,560.20 for variation works; RM832,527.76 for customised material; less set-off of RM5,514,760.20 already paid).
- 2. 1st Defendant to pay contractual interest at 5% per annum on the total judgment sum of RM38,277,862.45 from 24.7.2020 until full settlement.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment