DELICATE BUILDERS SDN. BHD. INTIGA SDN. BHD.
On re-hearing the court found Delicate primarily liable for delay due to inadequate manpower and failure to plead asserted excuses; Intiga entitled to back-charges arising from delay. The NYC claim was allowed only to the extent of East Elevation labour (reducing the judgment sum from RM172,719.62 to RM103,769.22). Scaffolding and overtime back-charges were held recoverable on balance of probabilities; Delicate’s counterclaim (RM360,691.17) dismissed for lack of documentary substantiation and pleaded particulars.
- Citation
- WA-12BC-11-09/2023 (Mahkamah Tinggi)
- Parties
- Appellant / Defendant (sessions Court): Delicate Builders Sdn. Bhd.; Respondent / Plaintiff (sessions Court): Intiga Sdn. Bhd.
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 22 April 2025
- Case Number
- WA-12BC-11-09/2023 (Mahkamah Tinggi)
- Procedural Posture
- Civil Appeal (high Court) / Judgment on Appeal (re Hearing)
- Outcome
- Appeal allowed in part. Sessions Court judgment varied: amount recoverable by respondent against appellant reduced to RM103,769.22 with interest; appellant's counterclaim dismissed; no order as to costs.
- Legal Topics
- Delay and Liability, Back Charges, Extension of Time, Payment Claims, Counterclaim, Scaffolding Costs, Overtime Claims, Appellate Review Standards
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Delicate Builders Sdn. Bhd.
Appellant / Defendant (sessions Court)
Intiga Sdn. Bhd.
Respondent / Plaintiff (sessions Court)
Procedural Posture
Civil Appeal (high Court) / Judgment on Appeal (re Hearing)
Legal Issues
- 1 Whether the delay to completion was caused by the defendant
- 2 Whether plaintiff entitled to back-charge RM131,440 for NYC appointment
- 3 Whether plaintiff entitled to back-charge RM204,526.98 for scaffolding
Ratio Decidendi
On re-hearing the court found Delicate primarily liable for delay due to inadequate manpower and failure to plead asserted excuses; Intiga entitled to back-charges arising from delay. The NYC claim was allowed only to the extent of East Elevation labour (reducing the judgment sum from RM172,719.62 to RM103,769.22). Scaffolding and overtime back-charges were held recoverable on balance of probabilities; Delicate’s counterclaim (RM360,691.17) dismissed for lack of documentary substantiation and pleaded particulars.
Court Disposition
Appeal allowed in part. Sessions Court judgment varied: amount recoverable by respondent against appellant reduced to RM103,769.22 with interest; appellant's counterclaim dismissed; no order as to costs.
Orders
- Allow appeal in part and vary Sessions Court award: respondent awarded RM103,769.22 against appellant
- Interest at 5% per annum on RM103,769.22 from date of filing of Writ of Summons until full settlement
Full Case Text
Judgment text and source record