1. ) SAMADO SDN BHD 2. ) KERAJAAN MALAYSIA 1. ) KERAJAAN MALAYSIA 2. ) SAMADO SDN BHD
The High Court found the Government failed to establish a denial of natural justice or that the adjudicator acted beyond jurisdiction; the adjudicator had given parties opportunity to be heard, considered the evidence, lawfully revised the practical completion date under s25(m) within the scope of the payment claim, and lawfully exercised discretion on costs; therefore the adjudication decision stands and is enforceable as a High Court judgment.
- Citation
- WA-24C-99-06/2019 & WA-24C-121-07/2019 (Mahkamah Tinggi)
- Parties
- Plaintiff (os WA 24 C 99 06/2019); Defendant (os WA 24 C 121 07/2019): Samado Sdn Bhd (Company No.: 117555-V); Defendant (os WA 24 C 99 06/2019); Plaintiff (os WA 24 C 121 07/2019): Kerajaan Malaysia (Government of Malaysia)
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 10 October 2019
- Case Number
- WA-24C-99-06/2019 & WA-24C-121-07/2019 (Mahkamah Tinggi)
- Procedural Posture
- CIPAA Enforcement and Setting Aside Applications / High Court Grounds of Judgment; Appeal by Government of Malaysia Filed
- Outcome
- Enforcement application by Samado allowed; Government of Malaysia's application to set aside dismissed; adjudication decision enforced as High Court judgment.
- Legal Topics
- Enforcement of Adjudication Decision, Setting Aside Adjudication Decision, Natural Justice, Excess of Jurisdiction, Liquidated and Ascertained Damages, Practical Completion, Costs of Adjudication
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Samado Sdn Bhd (Company No.: 117555-V)
Plaintiff (os WA 24 C 99 06/2019); Defendant (os WA 24 C 121 07/2019)
Kerajaan Malaysia (Government of Malaysia)
Defendant (os WA 24 C 99 06/2019); Plaintiff (os WA 24 C 121 07/2019)
Procedural Posture
CIPAA Enforcement and Setting Aside Applications / High Court Grounds of Judgment; Appeal by Government of Malaysia Filed
Legal Issues
- 1 Whether there was a denial of natural justice under section 15(b) CIPAA
- 2 Whether the adjudicator acted in excess of jurisdiction under section 15(d) CIPAA
- 3 Whether the works had reached practical completion and the correct date for CPC
Ratio Decidendi
The High Court found the Government failed to establish a denial of natural justice or that the adjudicator acted beyond jurisdiction; the adjudicator had given parties opportunity to be heard, considered the evidence, lawfully revised the practical completion date under s25(m) within the scope of the payment claim, and lawfully exercised discretion on costs; therefore the adjudication decision stands and is enforceable as a High Court judgment.
Court Disposition
Enforcement application by Samado allowed; Government of Malaysia's application to set aside dismissed; adjudication decision enforced as High Court judgment.
Orders
- Enforce Adjudication Decision dated 12.3.2019 as judgment: Government of Malaysia to pay Adjudicated Sum RM605,766.82 with simple interest at 4% per annum from 29 May 2015 until payment.
- OS No. WA-24C-99-06/2019 (SSB enforcement) allowed; costs awarded to SSB RM3,000.00 (subject to allocator).
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment