PEMPETISYEN BINA GOODYEAR BERHAD (In Liquidation) IMEJ TENGGARA SDN. BHD

PEMPETISYEN BINA GOODYEAR BERHAD (In Liquidation) IMEJ TENGGARA SDN. BHD

The court held that clause 45 unambiguously covers the parties' disputes arising from the Design and Build Contract, including post‑completion defects and payment claims, and that the existence of a bona fide dispute over a substantial unpaid contract sum meant the winding‑up petition should be stayed pending...

Source-derived case information.

Citation
JA-28NCC-56-04/2023 (Mahkamah Tinggi)
Parties
Petitioner: Bina Goodyear Berhad (in liquidation) (Company No. 18645-H); Respondent: Imej Tenggara Sdn Bhd (Company No. 763226-V)
Court
High Court
Jurisdiction
Malaysia
Judgment Date
3 September 2024
Case Number
JA-28NCC-56-04/2023 (Mahkamah Tinggi)
Procedural Posture
Companies (winding Up) Petition / Judgment on Referral to Arbitration Application (stay Granted)
Outcome
Enclosure 6 allowed; winding‑up Petition JA-28NCC-56-04/2023 stayed pending arbitration
Legal Topics
Winding Up Petition, Stay Pending Arbitration, Defects Liability, Statutory Demand, Contractual Payment Disputes
Company Law Insolvency Law Arbitration Construction/contract Law Winding Up Petition Stay Pending Arbitration Defects Liability Statutory Demand +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Bina Goodyear Berhad (in liquidation) (Company No. 18645-H)

Petitioner

Imej Tenggara Sdn Bhd (Company No. 763226-V)

Respondent

Procedural Posture

Companies (winding Up) Petition / Judgment on Referral to Arbitration Application (stay Granted)

  1. 1 Whether clause 45 arbitration clause in the Design and Build Contract covers the parties' disputes including post‑completion defects and payment claims
  2. 2 Whether there exists a bona fide dispute sufficient to defeat or stay a winding‑up petition
  3. 3 Whether the Petitioner is 'unable to pay its debts' under s466 Companies Act 2016 at this stage

Ratio Decidendi

The court held that clause 45 unambiguously covers the parties' disputes arising from the Design and Build Contract, including post‑completion defects and payment claims, and that the existence of a bona fide dispute over a substantial unpaid contract sum meant the winding‑up petition should be stayed pending determination by arbitration; accordingly enclosure 6 was allowed and enclosure 1 was stayed until arbitration is concluded.

Court Disposition

Enclosure 6 allowed; winding‑up Petition JA-28NCC-56-04/2023 stayed pending arbitration

Orders

  • Enclosure 6 (referral to arbitration application) is allowed.
  • A stay is granted on Enclosure 1 (winding‑up Petition JA-28NCC-56-04/2023) pending referral to and determination by arbitration in accordance with clause 45 of the Design and Build Contract.