Intercargo Shipping & Forwarding Sdn Bhd Taiko Odyssey Sdn Bhd
Contemporaneous invoices, time cards, statements and acknowledged communications established the plaintiff's entitlement to summary judgment for unpaid rentals of RM1,245,956.62; only the defendant's counterclaim arising from the collapse of five prestressed girder beams raised triable issues, justifying a stay of...
Source-derived case information.
- Citation
- BA-22NCvC-150-04/2021 (Mahkamah Tinggi)
- Parties
- Plaintiff: INTERCARGO SHIPPING & FORWARDING SDN. BHD.; Defendant: TAIKO ODYSSEY SDN. BHD.
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 9 December 2021
- Case Number
- BA-22NCvC-150-04/2021 (Mahkamah Tinggi)
- Procedural Posture
- Civil Suit Summary Judgment Application (interlocutory) / Summary Judgment Granted With Partial Stay; Counterclaim Trial Directions Issued; Appeal Filed to Court of Appeal
- Outcome
- Summary judgment entered for plaintiff for unpaid rentals; partial stay of execution ordered pending trial of defendant's counterclaim; directions issued for counterclaim trial; costs awarded to plaintiff.
- Legal Topics
- Summary Judgment, Stay of Execution, Counterclaim, Set Off/contra, Interest, Contemporaneous Documentary Evidence, Trial Directions (o.14 R.6, O.34)
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
INTERCARGO SHIPPING & FORWARDING SDN. BHD.
Plaintiff
TAIKO ODYSSEY SDN. BHD.
Defendant
Procedural Posture
Civil Suit Summary Judgment Application (interlocutory) / Summary Judgment Granted With Partial Stay; Counterclaim Trial Directions Issued; Appeal Filed to Court of Appeal
Legal Issues
- 1 Whether there exists any triable defence to the plaintiff's claim for unpaid crane rentals
- 2 Whether the defendant's counterclaim arising from collapse of five prestressed girder beams raises triable issues
- 3 Whether the defendant validly effected set-off/contra by proposed sale of machinery
Ratio Decidendi
Contemporaneous invoices, time cards, statements and acknowledged communications established the plaintiff's entitlement to summary judgment for unpaid rentals of RM1,245,956.62; only the defendant's counterclaim arising from the collapse of five prestressed girder beams raised triable issues, justifying a stay of execution for RM363,892.16 pending trial of that counterclaim; the defendant's unilateral proposal to contra machinery did not defeat recovery of at least RM882,064.46; the 3% per month interest was not recoverable and 5% per annum interest was awarded from 08.01.2021 until full realisation.
Court Disposition
Summary judgment entered for plaintiff for unpaid rentals; partial stay of execution ordered pending trial of defendant's counterclaim; directions issued for counterclaim trial; costs awarded to plaintiff.
Orders
- Summary judgment for RM1,245,956.62 awarded to the Plaintiff against the Defendant with interest at 5% per annum from 08.01.2021 until full realisation
- Stay of execution in respect of RM363,892.16 pending trial of the counterclaim relating to the collapse of five prestressed girder beams
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment