PP Chin Hin Sdn Bhd Jiangsu Provincial Construction (M) Sdn Bhd
Because the respondent failed to comply with the statutory demand and filed no affidavit in opposition, the consent judgment and affidavit verifying the petition established the debt and, absent evidence of solvency, the respondent was presumed unable to pay; accordingly the winding up petition was granted and the court appointed the proposed liquidator.
- Citation
- WA-28NCC-1254-11/2019 (Mahkamah Tinggi)
- Parties
- Petitioner: PP Chin Hin Sdn Bhd; Respondent: Jiangsu Provincial Construction (M) Sdn Bhd; Supporting Creditor: YLL Hydarulic Services Sdn Bhd; Supporting Creditor: Heng Fatt Engineering Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 19 February 2020
- Case Number
- WA-28NCC-1254-11/2019 (Mahkamah Tinggi)
- Procedural Posture
- Winding Up Petition Under Companies Act 2016 / Hearing and Judgment (winding Up Order Granted)
- Outcome
- Winding up order granted against Jiangsu Provincial Construction (M) Sdn Bhd
- Legal Topics
- Statutory Demand, Winding Up, Consent Judgment, Appointment of Liquidator
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
PP Chin Hin Sdn Bhd
Petitioner
Jiangsu Provincial Construction (M) Sdn Bhd
Respondent
YLL Hydarulic Services Sdn Bhd
Supporting Creditor
Heng Fatt Engineering Sdn Bhd
Supporting Creditor
Procedural Posture
Winding Up Petition Under Companies Act 2016 / Hearing and Judgment (winding Up Order Granted)
Legal Issues
- 1 Whether statutory demand was complied with
- 2 Whether respondent is insolvent and presumed unable to pay debts
- 3 Whether consent judgment constitutes sufficient evidence of debt in absence of opposing affidavit
Ratio Decidendi
Because the respondent failed to comply with the statutory demand and filed no affidavit in opposition, the consent judgment and affidavit verifying the petition established the debt and, absent evidence of solvency, the respondent was presumed unable to pay; accordingly the winding up petition was granted and the court appointed the proposed liquidator.
Court Disposition
Winding up order granted against Jiangsu Provincial Construction (M) Sdn Bhd
Orders
- Winding up order in terms of the petition granted against the Respondent
- Chong Chuan Long of the firm CL Chong appointed as Liquidator in terms of supporting creditor's Form of Summons (Enclosure 12)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment