Plaintiffs failed to prove, on a balance of probabilities, the actual value and completion of works required for recovery; evidence established delay and abandonment attributable to Plaintiffs and the 12.7.2017 Minute supported a valid late penalty calculation of RM351,000 which the Defendant proved; other...

Source-derived case information.

Citation
WA-22C-83-08/2020 (Mahkamah Tinggi)
Parties
Plaintiff: Lee Boong Hong @ Ng Boong Hong (Top Form Renovation & Construction); Plaintiff: Wong Chee Leong (Igo 37 Archo Gallery); Defendant: WH Electrical Marketing (M) Sdn Bhd; Third Party: Ng Wei Siang (Franco Alex Associate)
Court
High Court
Jurisdiction
Malaysia
Judgment Date
20 June 2023
Case Number
WA-22C-83-08/2020 (Mahkamah Tinggi)
Procedural Posture
Civil Suit – Construction/contract Dispute / Trial Judgment (full Grounds of Judgment)
Outcome
Plaintiffs' claim dismissed. Defendant's counterclaim allowed in part (RM351,000 late penalty with interest). Defendant's indemnity claim against Third Party dismissed.
Legal Topics
Late Delivery Penalty, Quantum Meruit and S.71 Contracts Act, Third‑party Indemnity, Abuse of Process, Unjust Enrichment, Costs
Contract Law Construction Law Civil Procedure Evidence Law Tort/negligence Late Delivery Penalty Quantum Meruit and S.71 Contracts Act Third‑party Indemnity +3 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Lee Boong Hong @ Ng Boong Hong (Top Form Renovation & Construction)

Plaintiff

Wong Chee Leong (Igo 37 Archo Gallery)

Plaintiff

WH Electrical Marketing (M) Sdn Bhd

Defendant

Ng Wei Siang (Franco Alex Associate)

Third Party

Procedural Posture

Civil Suit – Construction/contract Dispute / Trial Judgment (full Grounds of Judgment)

  1. 1 Whether plaintiffs sued the correct party
  2. 2 Whether claim based solely on Letters of Award and Consultation Contract
  3. 3 Whether there was delay in completion and who was responsible

Ratio Decidendi

Plaintiffs failed to prove, on a balance of probabilities, the actual value and completion of works required for recovery; evidence established delay and abandonment attributable to Plaintiffs and the 12.7.2017 Minute supported a valid late penalty calculation of RM351,000 which the Defendant proved; other counterclaims and Plaintiffs' primary monetary claims failed for lack of proof and procedural/pleading deficiencies.

Court Disposition

Plaintiffs' claim dismissed. Defendant's counterclaim allowed in part (RM351,000 late penalty with interest). Defendant's indemnity claim against Third Party dismissed.

Orders

  • Plaintiffs (jointly and severally) to pay Defendant RM351000.00 as late penalty
  • Interest on RM351000.00 at 5.0 per cent per annum from date of judgment until full settlement