G.C.S FURNISHING SDN BHD MAH SING PROPERTIES SDN BHD
The High Court held the Magistrate erred by failing to give proper judicial appreciation to contemporaneous documents and testimony. On the balance of probabilities the respondent failed to prove a valid force majeure event or entitlement to EOT because the extension letters lacked the requisite independent opinion by the proper certifier and TNB letters did not corroborate nationwide shortages or administrative procedural causes. The delay was attributable to the respondent's own failures; therefore the appellant was entitled to LAD and the Magistrate's decision was set aside.
- Citation
- JA-11BNCvC-7-06/2023 (Mahkamah Tinggi)
- Parties
- Appellant/plaintiff: G.C.S. Furnishing Sdn Bhd; Respondent/defendant: Mah Sing Properties Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 2 December 2024
- Case Number
- JA-11BNCvC-7-06/2023 (Mahkamah Tinggi)
- Procedural Posture
- Civil Appeal From Magistrate / High Court (appeal From Magistrate)
- Outcome
- Appeal allowed; Magistrate's judgment dated 08.06.2023 set aside; Plaintiff's claim allowed.
- Legal Topics
- Liquidated Ascertained Damages, Force Majeure, Extension of Time (eot), Vacant Possession, Judicial Appreciation of Evidence, Hearsay and Adverse Inference
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
G.C.S. Furnishing Sdn Bhd
Appellant/plaintiff
Mah Sing Properties Sdn Bhd
Respondent/defendant
Procedural Posture
Civil Appeal From Magistrate / High Court (appeal From Magistrate)
Legal Issues
- 1 Whether the developer (respondent) validly relied on clause 20 (force majeure) to avoid liability for LAD
- 2 Whether extension of time letters and engineer/architect opinions satisfied the contractual requirement for an opinion under clause 20.1
- 3 Whether the Magistrate failed to undertake sufficient judicial appreciation of contemporaneous documentary evidence
Ratio Decidendi
The High Court held the Magistrate erred by failing to give proper judicial appreciation to contemporaneous documents and testimony. On the balance of probabilities the respondent failed to prove a valid force majeure event or entitlement to EOT because the extension letters lacked the requisite independent opinion by the proper certifier and TNB letters did not corroborate nationwide shortages or administrative procedural causes. The delay was attributable to the respondent's own failures; therefore the appellant was entitled to LAD and the Magistrate's decision was set aside.
Court Disposition
Appeal allowed; Magistrate's judgment dated 08.06.2023 set aside; Plaintiff's claim allowed.
Orders
- Set aside the decision of the Magistrate dated 08.06.2023
- Allow the Plaintiff's claim as per Writ and Statement of Claim
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment