XXXX Fairview International School Nusajaya Sdn Bhd
The LOA fixed a six-month completion to 28 Feb 2015 and contained an express LAD of RM10,000/day which, under the LOA's precedence clause, overrides the GCS cap; the defendant did not validly apply for extension of time under the PAM procedure and unlawfully suspended and failed to complete the works, so LAD ran from 1 Mar 2015 to JKKP certification on 2 Jun 2015 (94 days) equating to RM940,000; plaintiff was entitled to recover third-party rectification costs because defendant failed to deliver works fit for purpose and no valid payment certificates supported defendant's counterclaim, hence counterclaim dismissed.
- Citation
- W-02(NCvC)(W)-18-01/2022 (Mahkamah Rayuan)
- Parties
- Appellant/defendant: MS Elevators Engineering Sdn Bhd; Respondent/plaintiff: Fairview International School Nusajaya Sdn Bhd
- Court
- NCvC
- Jurisdiction
- Malaysia
- Judgment Date
- 21 July 2025
- Case Number
- W-02(NCvC)(W)-18-01/2022 (Mahkamah Rayuan)
- Procedural Posture
- Civil Appeal / Judgment by Court of Appeal Affirming High Court Decision
- Outcome
- Appeal dismissed; High Court decision affirmed
- Legal Topics
- Liquidated Ascertained Damages, Extension of Time, Breach of Contract, Rectification Costs, Suspension of Works, Payment Certification, Nominal Damages
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
MS Elevators Engineering Sdn Bhd
Appellant/defendant
Fairview International School Nusajaya Sdn Bhd
Respondent/plaintiff
Procedural Posture
Civil Appeal / Judgment by Court of Appeal Affirming High Court Decision
Legal Issues
- 1 whether the defendant breached the Letter of Award (LOA) by failing to complete works by the completion date
- 2 whether plaintiff entitled to LAD and whether LAD limited to 5% cap or RM10,000/day
- 3 whether defendant validly obtained JKKP certification date for purposes of computing LAD
Ratio Decidendi
The LOA fixed a six-month completion to 28 Feb 2015 and contained an express LAD of RM10,000/day which, under the LOA's precedence clause, overrides the GCS cap; the defendant did not validly apply for extension of time under the PAM procedure and unlawfully suspended and failed to complete the works, so LAD ran from 1 Mar 2015 to JKKP certification on 2 Jun 2015 (94 days) equating to RM940,000; plaintiff was entitled to recover third-party rectification costs because defendant failed to deliver works fit for purpose and no valid payment certificates supported defendant's counterclaim, hence counterclaim dismissed.
Court Disposition
Appeal dismissed; High Court decision affirmed
Orders
- Appellant to pay respondent liquidated ascertained damages of MYR 940000.00
- Respondent awarded rectification costs of MYR 70294.80 for third-party repairs
Full Case Text
Judgment text and source record