Bolt Industries Sdn Bhd Itramas Re Services Sdn Bhd
Court found Defendant proved entitlement to deduct RM42,930 for the 53 damaged PV modules (admitted by Plaintiff) but failed to prove entitlement to deduct RM54,351.12 as liquidated damages and RM18,800 as third‑party completion costs; delay was attributable to Defendant so LAD was not payable; Defendant had not shown actual payment to third party or that Plaintiff had been paid for those missing works; hence Plaintiff entitled to recover RM73,151.12 (RM54,351.12 + RM18,800.00) with 5% interest from 20.7.2019; costs to be borne by parties themselves.
- Citation
- BA-12BC-3-02/2024 (Mahkamah Tinggi)
- Parties
- Appellant/plaintiff: Bolt Industries Sdn Bhd; Respondent/defendant: Itramas Re Services Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 25 June 2024
- Case Number
- BA-12BC-3-02/2024 (Mahkamah Tinggi)
- Procedural Posture
- Civil Appeal / High Court Rehearing on Appeal (order 55 ROC 2012; S.29 Courts of Judicature Act 1964)
- Outcome
- Appeal allowed in part in favour of Plaintiff; Defendant ordered to pay Plaintiff RM73,151.12 with interest; costs to be borne by parties themselves
- Legal Topics
- Liquidated Damages, Backcharges, Subcontract, Final Account, Demobilisation, Delay, CIPAA Payment Claim
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Bolt Industries Sdn Bhd
Appellant/plaintiff
Itramas Re Services Sdn Bhd
Respondent/defendant
Procedural Posture
Civil Appeal / High Court Rehearing on Appeal (order 55 ROC 2012; S.29 Courts of Judicature Act 1964)
Legal Issues
- 1 Whether Defendant entitled to deduct RM116,081.12 from Final Account comprising RM42,930.00 (damaged PV modules), RM54,351.12 (LAD) and RM18,800.00 (third party completion costs)
- 2 Whether Plaintiff entitled to claim RM34,450.00 for additional work outside LOA
Ratio Decidendi
Court found Defendant proved entitlement to deduct RM42,930 for the 53 damaged PV modules (admitted by Plaintiff) but failed to prove entitlement to deduct RM54,351.12 as liquidated damages and RM18,800 as third‑party completion costs; delay was attributable to Defendant so LAD was not payable; Defendant had not shown actual payment to third party or that Plaintiff had been paid for those missing works; hence Plaintiff entitled to recover RM73,151.12 (RM54,351.12 + RM18,800.00) with 5% interest from 20.7.2019; costs to be borne by parties themselves.
Court Disposition
Appeal allowed in part in favour of Plaintiff; Defendant ordered to pay Plaintiff RM73,151.12 with interest; costs to be borne by parties themselves
Orders
- Defendant to pay Plaintiff RM73,151.12 as damages
- Interest at 5% per annum on RM73,151.12 from 20.7.2019 until full settlement
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment