CAPITOL AVENUE DEVELOPMENT SDN BHD GAMWON PROPERTIES SDN BHD
The Architect's Certificate issued to the main contractor did not effect an extension under clause 14.1.1 of the SPA because the SESB delay was not established as a force majeure event beyond the Developer's control and the certificate arose under the contractor's construction contract; therefore the Developer remained liable for liquidated ascertained damages and the High Court's award was affirmed; the stay of execution was wrongly granted for lack of special circumstances and those stay orders were set aside.
- Citation
- S-02(NCVC)(A)-432-02/2018 (Mahkamah Rayuan)
- Parties
- Appellant/defendant: Capitol Avenue Development Sdn Bhd; Respondent/plaintiff: Gamwon Properties Sdn Bhd; Respondent/plaintiff: YL Pavillion Sdn Bhd; Respondent/plaintiff: Upper Domain Sdn Bhd
- Court
- NCVC
- Jurisdiction
- Malaysia
- Judgment Date
- 20 March 2019
- Case Number
- S-02(NCVC)(A)-432-02/2018 (Mahkamah Rayuan)
- Procedural Posture
- Civil Appeal / Court of Appeal Judgment on Appeals From High Court on Construction of Contract and Stay Applications
- Outcome
- Appeals S-02(NCvC)(A)-432-02/2018, S-02(NCvC)(A)-436-02/2018 and S-02(NCvC)(A)-437-02/2018 dismissed and High Court judgment affirmed; appeals S-02(IM)(NCvC)-1481-02/2018, S-02(IM)(NCvC)-1482-02/2018 and S-02(IM)(NCvC)-1483-02/2018 allowed to set aside stay orders.
- Legal Topics
- Liquidated Damages, Extension of Time, Force Majeure, Architect's Certificate, Stay of Execution, Interpretation of Contract
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Capitol Avenue Development Sdn Bhd
Appellant/defendant
Gamwon Properties Sdn Bhd
Respondent/plaintiff
YL Pavillion Sdn Bhd
Respondent/plaintiff
Upper Domain Sdn Bhd
Respondent/plaintiff
Procedural Posture
Civil Appeal / Court of Appeal Judgment on Appeals From High Court on Construction of Contract and Stay Applications
Legal Issues
- 1 Whether the Architect's Certificate of Extension of Time operates to extend the SPA completion date under clause 14.1.1
- 2 Whether delay in electricity supply by SESB constitutes force majeure or a cause beyond the developer's control
- 3 Whether Originating Summons was the proper mode of commencement
Ratio Decidendi
The Architect's Certificate issued to the main contractor did not effect an extension under clause 14.1.1 of the SPA because the SESB delay was not established as a force majeure event beyond the Developer's control and the certificate arose under the contractor's construction contract; therefore the Developer remained liable for liquidated ascertained damages and the High Court's award was affirmed; the stay of execution was wrongly granted for lack of special circumstances and those stay orders were set aside.
Court Disposition
Appeals S-02(NCvC)(A)-432-02/2018, S-02(NCvC)(A)-436-02/2018 and S-02(NCvC)(A)-437-02/2018 dismissed and High Court judgment affirmed; appeals S-02(IM)(NCvC)-1481-02/2018, S-02(IM)(NCvC)-1482-02/2018 and S-02(IM)(NCvC)-1483-02/2018 allowed to set aside stay orders.
Orders
- Dismissed appeals S-02(NCvC)(A)-432-02/2018, S-02(NCvC)(A)-436-02/2018 and S-02(NCvC)(A)-437-02/2018 and affirmed High Court awards
- Ordered costs of RM20000.00 to the respective Respondents subject to payment of the allocator fee
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment