MENTA CONSTRUCTION SDN BHD 1. NAZA ENGINEERING & CONSTRUCTION SDN BHD 2. NAZA TTDI SEGARIS SDN BHD
Defendants admitted the substantive debt and failed to establish a bona fide defence or triable issue; the non-delivery of the contra properties amounted to repudiation permitting Plaintiff to rescind the Settlement Agreement and claim the outstanding sum including late interest; therefore summary judgment is granted for RM2,122,392.46 with interest and costs.
- Citation
- WA-22C-59-07/2020 (Mahkamah Tinggi)
- Parties
- Plaintiff: Menta Construction Sdn Bhd; Defendant: Naza Engineering & Construction Sdn Bhd; Defendant: Naza TTDI Segaris Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 30 April 2021
- Case Number
- WA-22C-59-07/2020 (Mahkamah Tinggi)
- Procedural Posture
- Civil Contract/construction / Application for Summary Judgment (order 14 Ro C 2012)
- Outcome
- Plaintiff's application for summary judgment allowed
- Legal Topics
- Summary Judgment, Repudiation and Rescission, Set Off/contra, Late Payment Interest, Without Prejudice Admissibility
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Menta Construction Sdn Bhd
Plaintiff
Naza Engineering & Construction Sdn Bhd
Defendant
Naza TTDI Segaris Sdn Bhd
Defendant
Procedural Posture
Civil Contract/construction / Application for Summary Judgment (order 14 Ro C 2012)
Legal Issues
- 1 Whether there are triable issues such that summary judgment should be refused
- 2 Whether the Settlement Agreement was repudiated such that Plaintiff could rescind and claim outstanding sums and late interest
- 3 Whether Clause 5 of the Settlement Agreement bars late interest after rescission
Ratio Decidendi
Defendants admitted the substantive debt and failed to establish a bona fide defence or triable issue; the non-delivery of the contra properties amounted to repudiation permitting Plaintiff to rescind the Settlement Agreement and claim the outstanding sum including late interest; therefore summary judgment is granted for RM2,122,392.46 with interest and costs.
Court Disposition
Plaintiff's application for summary judgment allowed
Orders
- Judgment for the Plaintiff in the sum of RM2,122,392.46
- Interest at the rate of 5% per annum on RM2,122,392.46 from 30.4.2021 until full settlement
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment