MERCHANT SYNERGY SDN BHD NUJAIMAH BINTI SAFIE

MERCHANT SYNERGY SDN BHD NUJAIMAH BINTI SAFIE

Appeal allowed because 'vacant possession' under the contract required CCC and utilities ready for connection; Defendant could not lawfully deliver vacant possession due to failure of third party developer to complete infrastructure, and the Defendant was thereby prevented from performing (s68 Contracts Act 1950);...

Source-derived case information.

Citation
BA-11BNCvC-4-01/2021 (Mahkamah Tinggi)
Parties
Appellant: Merchant Synergy Sdn Bhd; Respondent: Nujaimah Binti Safie
Court
High Court
Jurisdiction
Malaysia
Judgment Date
8 June 2021
Case Number
BA-11BNCvC-4-01/2021 (Mahkamah Tinggi)
Procedural Posture
Civil Appeal (contract/construction) / Judgment on Appeal
Outcome
Appeal allowed
Legal Topics
Liquidated and Ascertained Damages, Vacant Possession, Certificate of Completion and Compliance (ccc), Indemnity, Prevention of Performance (section 68 Contracts Act 1950), Building Regulation Offences
Contract Law Construction Law Evidence Law Statutory Compliance Liquidated and Ascertained Damages Vacant Possession Certificate of Completion and Compliance (ccc) Indemnity +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 15 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Merchant Synergy Sdn Bhd

Appellant

Nujaimah Binti Safie

Respondent

Procedural Posture

Civil Appeal (contract/construction) / Judgment on Appeal

  1. 1 Whether the contractor breached the agreement by failing to surrender vacant possession
  2. 2 Whether vacant possession requires CCC and utilities ready for connection
  3. 3 Whether inability to deliver vacant possession was caused by third party developer (Bandar Akademia) and whether indemnity or joinder was required

Ratio Decidendi

Appeal allowed because 'vacant possession' under the contract required CCC and utilities ready for connection; Defendant could not lawfully deliver vacant possession due to failure of third party developer to complete infrastructure, and the Defendant was thereby prevented from performing (s68 Contracts Act 1950); Magistrate erred in holding Defendant liable and in requiring Defendant to join Bandar Akademia; costs awarded RM6,000.

Court Disposition

Appeal allowed

Orders

  • Lower court judgment set aside insofar as it awarded LAD against the Defendant
  • Costs of RM6000 awarded to the Defendant covering the lower court proceedings and this appeal