PANTAS TECHNOLOGIES SDN BHD 1. ) KEMENTERIAN PENDIDIKAN MALAYSIA 2. ) Kerajaan Malaysia
D1 is not a proper legal entity to be sued; Plaintiff is estopped from challenging termination of Contract 1 because it agreed to recoupment via Contract 2 and accepted conditional terms when entering Contract 2; Plaintiff failed to prove on balance of probabilities that RM6,454,861.72 of variation/remeasurement works were performed or valued correctly; the Certificate of Termination Costs dated 16.12.2020 was properly made under the Contract and Defendant 2 is entitled to recover the net termination shortfall (RM4,030,327.79 after set-offs); recoupment of RM961,550.39 from Contract 2 interim payments was lawful under Clause 33; termination of Contract 2 was valid because Plaintiff failed...
- Citation
- WA-21C-9-11/2020 (Mahkamah Tinggi)
- Parties
- Plaintiff: PANTAS TECHNOLOGIES SDN BHD; Defendant First: KEMENTERIAN PENDIDIKAN MALAYSIA; Defendant Second: KERAJAAN MALAYSIA
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 31 May 2023
- Case Number
- WA-21C-9-11/2020 (Mahkamah Tinggi)
- Procedural Posture
- Writ (construction Contract) / Judgment (trial)
- Outcome
- Plaintiff's claims dismissed; claims against Kementerian Pendidikan Malaysia struck out; Defendant 2 counterclaim allowed.
- Legal Topics
- Termination of Contract, Extension of Time (eo T), Variation and Remeasurement Claims, Certificate of Termination Costs, Estoppel, Set Off/recoupment, Limitation Period, Deduction From Payments
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
PANTAS TECHNOLOGIES SDN BHD
Plaintiff
KEMENTERIAN PENDIDIKAN MALAYSIA
Defendant First
KERAJAAN MALAYSIA
Defendant Second
Procedural Posture
Writ (construction Contract) / Judgment (trial)
Legal Issues
- 1 Whether termination of Contract 1 was valid
- 2 Whether Plaintiff entitled to RM6,454,861.72 for variations and remeasurement
- 3 Whether Certificate of Termination Costs dated 16.12.2020 (PKP) is valid and enforceable
Ratio Decidendi
D1 is not a proper legal entity to be sued; Plaintiff is estopped from challenging termination of Contract 1 because it agreed to recoupment via Contract 2 and accepted conditional terms when entering Contract 2; Plaintiff failed to prove on balance of probabilities that RM6,454,861.72 of variation/remeasurement works were performed or valued correctly; the Certificate of Termination Costs dated 16.12.2020 was properly made under the Contract and Defendant 2 is entitled to recover the net termination shortfall (RM4,030,327.79 after set-offs); recoupment of RM961,550.39 from Contract 2 interim payments was lawful under Clause 33; termination of Contract 2 was valid because Plaintiff failed...
Court Disposition
Plaintiff's claims dismissed; claims against Kementerian Pendidikan Malaysia struck out; Defendant 2 counterclaim allowed.
Orders
- Plaintiff's claim dismissed with costs against Defendant First and Defendant Second
- Counterclaim by Defendant Second allowed in the sum of RM4,030,327.79
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment