Menteri Besar Selangor (Pemerbadanan) Pentadbir Tanah Daerah Gombak PENCELAH MALAYSIA RAIL LINK SDN BHD
Court increased the land value from RM95.00/sqm to RM105.00/sqm and awarded additional compensation of RM90,010.00 (land value) and RM315,459.90 (pecah pisah) with late payment interest at 5% per annum from date of Form K until full settlement. Court dismissed applicants' further claims for additional compensation for injurious affection and incidental costs because applicants failed to prove diminution or disruption to the remainder land to the requisite standard.
- Citation
- BA-15-275-10/2024 (Mahkamah Tinggi)
- Parties
- Pemohon: Menteri Besar Selangor (Perbadanan); Pemohon: Malaysia Rail Link Sdn Bhd; Respondent: Pentadbir Tanah Daerah Gombak
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 8 January 2026
- Case Number
- BA-15-275-10/2024 (Mahkamah Tinggi)
- Procedural Posture
- Rujukan Tanah / Ruling on Objections to Compensation and Valuation (high Court Decision)
- Outcome
- Part of applicants' objections allowed: valuation increased and additional compensation awarded; claims for further injurious affection and incidental costs dismissed.
- Legal Topics
- Injurious Affection, Valuation of Land, Appealability of Compensation Awards, Severance/pecah Pisah
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Menteri Besar Selangor (Perbadanan)
Pemohon
Malaysia Rail Link Sdn Bhd
Pemohon
Pentadbir Tanah Daerah Gombak
Respondent
Procedural Posture
Rujukan Tanah / Ruling on Objections to Compensation and Valuation (high Court Decision)
Legal Issues
- 1 Whether the per square metre value should be increased from RM95.00 to RM105.00
- 2 Whether claimant proved entitlement to additional compensation for injurious affection
- 3 Whether claimant proved entitlement to incidental costs
Ratio Decidendi
Court increased the land value from RM95.00/sqm to RM105.00/sqm and awarded additional compensation of RM90,010.00 (land value) and RM315,459.90 (pecah pisah) with late payment interest at 5% per annum from date of Form K until full settlement. Court dismissed applicants' further claims for additional compensation for injurious affection and incidental costs because applicants failed to prove diminution or disruption to the remainder land to the requisite standard.
Court Disposition
Part of applicants' objections allowed: valuation increased and additional compensation awarded; claims for further injurious affection and incidental costs dismissed.
Orders
- Increase land value from RM95.00 per sqm to RM105.00 per sqm
- Respondent to pay additional land value compensation of RM90,010.00
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment