PK JUITA SDN BHD 1. ) AF CENTRIC SOLUTIONS SDN. BHD. 2. ) ALBERT CHIA KET SHIN 3. ) Jiang, Zhou
The court found the quotations, work orders and invoices collectively formed a written contract which Defendant 1 accepted (stamped and signed), Defendant 1 made partial payments and failed to raise timely or substantive objections; therefore Defendant 1 had no meritorious defence and summary judgment under Order 14 was appropriate.
- Citation
- JA-A52NCC-19-01/2024 (Mahkamah Sesyen)
- Parties
- Plaintiff: PKJUITA SDN BHD; Defendant 1: AF CENTRIC SOLUTIONS SDN. BHD.; Defendant 2: ALBERT CHIA KET SHIN; Defendant 3: JIANG, ZHOU
- Court
- Sessions Court
- Jurisdiction
- Malaysia
- Judgment Date
- 2 January 2025
- Case Number
- JA-A52NCC-19-01/2024 (Mahkamah Sesyen)
- Procedural Posture
- Civil Claim (summary Judgment Application) / Interlocutory Judgment (order 14 Summary Judgment)
- Outcome
- Application allowed (summary judgment entered against Defendant 1)
- Legal Topics
- Summary Judgment, Account Stated, Estoppel, Invoices and Delivery, Costs, Interest
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
PKJUITA SDN BHD
Plaintiff
AF CENTRIC SOLUTIONS SDN. BHD.
Defendant 1
ALBERT CHIA KET SHIN
Defendant 2
JIANG, ZHOU
Defendant 3
Procedural Posture
Civil Claim (summary Judgment Application) / Interlocutory Judgment (order 14 Summary Judgment)
Legal Issues
- 1 Whether there was a binding contract between plaintiff and Defendant 1 based on invoices, quotations and work orders
- 2 Whether Defendant 1 has a bona fide and triable defence to the claim
- 3 Whether the summary judgment procedure under Order 14 KKM 2012 is appropriate despite alleged delay in filing the application
Ratio Decidendi
The court found the quotations, work orders and invoices collectively formed a written contract which Defendant 1 accepted (stamped and signed), Defendant 1 made partial payments and failed to raise timely or substantive objections; therefore Defendant 1 had no meritorious defence and summary judgment under Order 14 was appropriate.
Court Disposition
Application allowed (summary judgment entered against Defendant 1)
Orders
- Summary judgment entered against Defendant 1 for RM101,989.01
- Interest at 5% per annum on the judgment sum from date of filing until full settlement
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment