IMPIAN MURNI RESOURCES SDN BHD KHENG BEE CONSTRUCTION SDN BHD
The court held that Clauses 2.1 and 2.2 allowed the work programme to be revised due to site conditions and concurrent subcontractor activity; Plaintiff was therefore not in delay and the six-month completion period was effectively extended. Defendant failed to prove the proper quantum and entitlement to set-off for...
Source-derived case information.
- Citation
- DA-22NCvC-37-06/2019 (Mahkamah Tinggi)
- Parties
- Plaintiff: Plaintif; Defendant: Defendan
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 23 July 2023
- Case Number
- DA-22NCvC-37-06/2019 (Mahkamah Tinggi)
- Procedural Posture
- Construction Contract Dispute / Judgment
- Outcome
- Plaintiff's interim payment claim allowed; Defendant's counterclaim dismissed
- Legal Topics
- Extension of Time, Site Conditions, Interim Payment, Set Off, Breach of Contract, Costs, Interest
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Plaintif
Plaintiff
Defendan
Defendant
Procedural Posture
Construction Contract Dispute / Judgment
Legal Issues
- 1 Whether the Plaintiff was in delay in completing the works
- 2 Whether site conditions and concurrent subcontractors (including flooding) entitled Plaintiff to extension under contractual clauses
- 3 Whether Defendant validly set-off amounts for building materials supplied on site against Plaintiff's interim payment claim
Ratio Decidendi
The court held that Clauses 2.1 and 2.2 allowed the work programme to be revised due to site conditions and concurrent subcontractor activity; Plaintiff was therefore not in delay and the six-month completion period was effectively extended. Defendant failed to prove the proper quantum and entitlement to set-off for materials on site and ignored the effect of flooding and the stop-work instruction. Accordingly Plaintiff’s interim payment claim of RM1,288,643.35 is allowed and Defendant’s counterclaim is dismissed.
Court Disposition
Plaintiff's interim payment claim allowed; Defendant's counterclaim dismissed
Orders
- Defendant to pay Plaintiff RM1,288,643.35 (Prayer 15(a))
- Interest at 5% per annum on the judgment sum from date of judgment until full payment
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment