PUNCAK GALI HARMONI SDN BHD EMRAIL SDN BHD

PUNCAK GALI HARMONI SDN BHD EMRAIL SDN BHD

Plaintiff established a serious issue to be tried but failed on discretionary grounds: damages are essentially adequate for the commercial losses alleged, the injunction sought was broad and would impose substantial operational restraints on a public railway rehabilitation project, the balance of convenience favoured refusal, public interest reinforced that conclusion, and no narrower neutral order could be fashioned; therefore the interim injunction (Enclosure 3) is dismissed.

Citation
BA-24NCC(ARB)-7-09/2025 (Mahkamah Tinggi)
Parties
PLAINTIFF: PUNCAK GALI HARMONI SDN BHD; DEFENDANT: EMRAIL SDN BHD
Court
ARB
Jurisdiction
Malaysia
Judgment Date
22 April 2026
Case Number
BA-24NCC(ARB)-7-09/2025 (Mahkamah Tinggi)
Procedural Posture
Originating Summons (inter Partes Application for Interim Injunction) / Inter Partes Hearing Remitted by Court of Appeal; Judgment on Interlocutory Application
Outcome
Enclosure 3 dismissed; interim protection ceased upon disposal of this inter partes hearing; Originating Summons remains extant; costs in the cause awarded to Defendant
Legal Topics
Interim Injunction, Specific Performance, Status Quo Preservation, Adequacy of Damages, Balance of Convenience, Public Interest in Infrastructure, Conditional Contracts
Source Language
Malay/English

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 6 Authorities cited 15 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

PUNCAK GALI HARMONI SDN BHD

PLAINTIFF

EMRAIL SDN BHD

DEFENDANT

Procedural Posture

Originating Summons (inter Partes Application for Interim Injunction) / Inter Partes Hearing Remitted by Court of Appeal; Judgment on Interlocutory Application

  1. 1 Whether there is a bona fide serious issue to be tried
  2. 2 Whether damages are an adequate remedy
  3. 3 Whether there remains a status quo or substratum apt for preservation by injunction

Ratio Decidendi

Plaintiff established a serious issue to be tried but failed on discretionary grounds: damages are essentially adequate for the commercial losses alleged, the injunction sought was broad and would impose substantial operational restraints on a public railway rehabilitation project, the balance of convenience favoured refusal, public interest reinforced that conclusion, and no narrower neutral order could be fashioned; therefore the interim injunction (Enclosure 3) is dismissed.

Court Disposition

Enclosure 3 dismissed; interim protection ceased upon disposal of this inter partes hearing; Originating Summons remains extant; costs in the cause awarded to Defendant

Orders

  • Enclosure 3 is dismissed.
  • The interim protection that continued pursuant to the Court of Appeal's order dated 10.04.2026 shall cease upon the disposal of this inter partes hearing, subject to any further order of the Court of Appeal or other court of competent jurisdiction.