TEWARA SDN BHD LEE CHOON SENG & SONS SDN BHD
On the evidence the Plaintiff failed to prove entitlement to claimed progress payments and most of the retention sums because claims were provisional and required final remeasurement/certification and Plaintiff failed to call the project managers; Defendant proved defects, failure to hand over and incurred...
Source-derived case information.
- Citation
- JA-12BNCvC-7-04/2022 (Mahkamah Tinggi)
- Parties
- Appellant / Plaintiff: Tewara Sdn Bhd; Respondent / Defendant: Lee Choon Seng & Sons Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 13 April 2023
- Case Number
- JA-12BNCvC-7-04/2022 (Mahkamah Tinggi)
- Procedural Posture
- Civil Appeal From Session Court (contract/construction Dispute) / High Court Re Hearing of Appeal
- Outcome
- Partly allowed: Plaintiff's appeal allowed only to the extent of ordering return of a reduced retention sum; otherwise appeal dismissed and Defendant's counterclaim upheld.
- Legal Topics
- Retention Sum, Defective Works and Rectification, Liquidated and Ascertained Damages, Counterclaim, Adverse Inference Under S114 Evidence Act, Certificate of Practical Completion (cpc)
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Tewara Sdn Bhd
Appellant / Plaintiff
Lee Choon Seng & Sons Sdn Bhd
Respondent / Defendant
Procedural Posture
Civil Appeal From Session Court (contract/construction Dispute) / High Court Re Hearing of Appeal
Legal Issues
- 1 Whether trial judge erred in drawing adverse inference under s114(g) for failure to call material witnesses
- 2 Whether the Plaintiff proved on balance of probabilities entitlement to progress payments and release of retention sums
- 3 Whether the Defendant proved counterclaims for rectification costs, additional operating costs and liquidated damages
Ratio Decidendi
On the evidence the Plaintiff failed to prove entitlement to claimed progress payments and most of the retention sums because claims were provisional and required final remeasurement/certification and Plaintiff failed to call the project managers; Defendant proved defects, failure to hand over and incurred rectification and delay costs; however documents established a reduced computable retention sum of RM136,926.15 which must be returned to Plaintiff; SCJ's invocation of s114(g) against Plaintiff was erroneous but that error did not alter outcome on the counterclaim.
Court Disposition
Partly allowed: Plaintiff's appeal allowed only to the extent of ordering return of a reduced retention sum; otherwise appeal dismissed and Defendant's counterclaim upheld.
Orders
- Defendant to return retention sum of RM136,926.15 to Plaintiff with costs of RM5,000.00, subject to cost of allocator, to be paid by Defendant to Plaintiff
- Plaintiff's appeal against the Defendant's counterclaim dismissed; Plaintiff to pay costs of RM5,000.00, subject to cost of allocator, to be paid by Plaintiff to Defendant
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment