Chan Kheng Hoe and Rachel Lim Han Ying [Messrs. Chong + Keng Hoe] K. Kirubakaran [Messrs. Selva Mookiah & Associates]
The guarantees were founded on and expressly premised upon the Deferred Payment Scheme in the LOA and Supplemental Agreement; because a Deferred Payment Scheme of the kind in issue amounts to a conditional payment provision void under s35 CIPAA 2012 and therefore the consideration for the guarantees is forbidden by law (Contracts Act ss24(a),25), the guarantees and any related indemnities are void and unenforceable; the plaintiff is estopped from taking a position inconsistent with its stance in the adjudication, and accordingly no legal obligation arises from the guarantees; costs awarded to the defendants.
- Citation
- WA-22C-60-08/2021 (Mahkamah Tinggi)
- Parties
- Plaintiff: SCEC GROUP (MALAYSIA) SDN BHD; 1st Defendant: PASTPRESENTFUTURE SDN BHD; 2nd Defendant: WONG SIEW WOON; 3rd Defendant: LEE POH WAH; 4th Defendant: CHAN BAOJIE
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 16 November 2022
- Case Number
- WA-22C-60-08/2021 (Mahkamah Tinggi)
- Procedural Posture
- Civil Suit (construction Contract Dispute) / Judgment on Order 14 a Application (interlocutory Determination on Validity and Enforceability of Guarantees)
- Outcome
- Order for declarations and dismissals as per judgment: guarantees declared void and unenforceable; related prayers dismissed where applicable; costs to defendants.
- Legal Topics
- Deferred Payment Scheme, Void Contracts, Guarantees and Indemnities, CIPAA S35, Estoppel Against Inconsistent Positions
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
SCEC GROUP (MALAYSIA) SDN BHD
Plaintiff
PASTPRESENTFUTURE SDN BHD
1st Defendant
WONG SIEW WOON
2nd Defendant
LEE POH WAH
3rd Defendant
CHAN BAOJIE
4th Defendant
Procedural Posture
Civil Suit (construction Contract Dispute) / Judgment on Order 14 a Application (interlocutory Determination on Validity and Enforceability of Guarantees)
Legal Issues
- 1 Whether the corporate and individual guarantees are valid and enforceable
- 2 Whether the guarantees are null and void because they are founded on a Deferred Payment Scheme that is a conditional payment provision void under s35 CIPAA 2012
- 3 Whether the plaintiff is estopped from asserting a position inconsistent with its stance in the adjudication proceedings
Ratio Decidendi
The guarantees were founded on and expressly premised upon the Deferred Payment Scheme in the LOA and Supplemental Agreement; because a Deferred Payment Scheme of the kind in issue amounts to a conditional payment provision void under s35 CIPAA 2012 and therefore the consideration for the guarantees is forbidden by law (Contracts Act ss24(a),25), the guarantees and any related indemnities are void and unenforceable; the plaintiff is estopped from taking a position inconsistent with its stance in the adjudication, and accordingly no legal obligation arises from the guarantees; costs awarded to the defendants.
Court Disposition
Order for declarations and dismissals as per judgment: guarantees declared void and unenforceable; related prayers dismissed where applicable; costs to defendants.
Orders
- Prayer 1(a) dismissed – the Guarantees are not valid and enforceable
- Prayer 1(b) granted – the Guarantees are null and void due to the Deferred Payment Scheme being void and the Plaintiff's position in the adjudication
Full Case Text
Judgment text and source record