Teh Hooi Peng (No. K/P: 880630-01-5310) Southkey City Sdn. Bhd. (No. Syarikat: 581190-A)
The Federal Court in Ang Ming Lee establishes that reg 11(3) of the Housing Development Regulations is ultra vires s.24 of the Housing Development Act, therefore any purported waiver or extension granted by the Controller/Ministry under that provision is invalid ab initio; consequently the Schedule H prescribed 36 months completion period governs the SPA and the appellant is entitled to pursue liquidated damages for delay; the Magistrate erred in finding triable issues and the appeal is allowed.
- Citation
- JA-11ANCvC-15-09/2020 (Mahkamah Tinggi)
- Parties
- Appellant / Plaintiff: Teh Hooi Peng; Respondent / Defendant: Southkey City Sdn. Bhd.
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 24 June 2021
- Case Number
- JA-11ANCvC-15-09/2020 (Mahkamah Tinggi)
- Procedural Posture
- Civil Appeal Against Refusal of Summary Judgment / Judgment on Appeal
- Outcome
- Appeal allowed; decision of the learned Magistrate dated 24.8.2020 set aside
- Legal Topics
- Statutory Contract, Schedule H of Housing Development Regulations, Ultra Vires, Liquidated Ascertained Damages, Summary Judgment, Delegation of Regulatory Power
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Teh Hooi Peng
Appellant / Plaintiff
Southkey City Sdn. Bhd.
Respondent / Defendant
Procedural Posture
Civil Appeal Against Refusal of Summary Judgment / Judgment on Appeal
Legal Issues
- 1 Whether the Controller/Ministry had power under reg 11(3) to waive or modify Schedule H contract terms
- 2 Whether the Ministry's extension of completion period was valid or ultra vires
- 3 Whether the SPA is governed by the 36 months completion period in Schedule H notwithstanding parties' clause specifying 42 months
Ratio Decidendi
The Federal Court in Ang Ming Lee establishes that reg 11(3) of the Housing Development Regulations is ultra vires s.24 of the Housing Development Act, therefore any purported waiver or extension granted by the Controller/Ministry under that provision is invalid ab initio; consequently the Schedule H prescribed 36 months completion period governs the SPA and the appellant is entitled to pursue liquidated damages for delay; the Magistrate erred in finding triable issues and the appeal is allowed.
Court Disposition
Appeal allowed; decision of the learned Magistrate dated 24.8.2020 set aside
Orders
- Appeal allowed
- Order of the learned Magistrate dated 24.8.2020 set aside
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment