China Communications Construction Company (M) Sdn Bhd Jiangsu Zhongnan Construction Group (Malaysia) Sdn Bhd
The court found the Adjudicator did not act in excess of jurisdiction and did not breach natural justice; the adjudicator considered the DPA, estoppel and relevant evidence and asked himself the right questions; no special circumstances were shown to warrant a stay pending setting aside and arbitration; accordingly the s16 stay application (OS 219) was dismissed with costs.
- Citation
- WA-24C-219-12/2021 (Mahkamah Tinggi)
- Parties
- Plaintiff/applicant: China Communications Construction (M) Sdn Bhd; Defendant/respondent: Jiangsu Zhongnan Construction Group (Malaysia) Sdn Bhd
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 29 March 2024
- Case Number
- WA-24C-219-12/2021 (Mahkamah Tinggi)
- Procedural Posture
- Originating Summons Under Construction Industry Payment and Adjudication Act 2012 (cipaa) S16 Stay Application / High Court Judgment on Stay Application (decision Stage)
- Outcome
- Originating Summons No. WA-24C-219-12/2021 (application for stay) dismissed
- Legal Topics
- Stay of Adjudication, Jurisdiction of Adjudicator, Natural Justice (bias/right to Be Heard), Enforcement Under CIPAA S28, Set Off, Performance Bond, Estoppel, CIPAA S15/s16/s25/s27/s28, Contracts Act S42
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
China Communications Construction (M) Sdn Bhd
Plaintiff/applicant
Jiangsu Zhongnan Construction Group (Malaysia) Sdn Bhd
Defendant/respondent
Procedural Posture
Originating Summons Under Construction Industry Payment and Adjudication Act 2012 (cipaa) S16 Stay Application / High Court Judgment on Stay Application (decision Stage)
Legal Issues
- 1 Whether the adjudicator acted in excess of jurisdiction under s27 CIPAA
- 2 Whether there was breach of natural justice in the adjudication process
- 3 Whether special circumstances exist to justify a stay of the Adjudication Decision under s16 CIPAA pending setting aside application and arbitration
Ratio Decidendi
The court found the Adjudicator did not act in excess of jurisdiction and did not breach natural justice; the adjudicator considered the DPA, estoppel and relevant evidence and asked himself the right questions; no special circumstances were shown to warrant a stay pending setting aside and arbitration; accordingly the s16 stay application (OS 219) was dismissed with costs.
Court Disposition
Originating Summons No. WA-24C-219-12/2021 (application for stay) dismissed
Orders
- Originating Summons No. WA-24C-219-12/2021 dismissed
- Costs awarded to the Defendant/Respondent Jiangsu Zhongnan Construction Group (Malaysia) Sdn Bhd
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment