KAY CORPORATION SDN BHD KAYANGAN KEMAS SDN BHD
Clause 2 of the LOA incorporated the Main Contract and bound KC; most of KC's variation claims failed because they lacked Employer/Consultant/Main Contractor approval and/or were time-barred under Clauses 50.1/50.3; KK's backcharges were largely unsupported by requisition/acknowledgement evidence and thus disallowed except for MCCT costs borne by KC and shared labour costs apportioned equally; retention and uncertified sums are payable subject to set-off against justified backcharges; KC's counterclaim dismissed in material part.
- Citation
- BA-22C-33-09/2021 (Mahkamah Tinggi)
- Parties
- Plaintiff (suit 50) / Defendant (suits 32 & 33): Kayangan Kemas Sdn. Bhd.; Defendant (suit 50) / Plaintiff (suits 32 & 33): Kay Corporation Sdn. Bhd.
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 12 January 2024
- Case Number
- BA-22C-33-09/2021 (Mahkamah Tinggi)
- Procedural Posture
- Civil Construction Contract Dispute / Judgment (trial Court Decision)
- Outcome
- Partial judgment: KC's counterclaim largely dismissed; KK entitled to limited recovery in Suit 50; KC awarded sums in Suits 32 and 33; retention/release subject to contractual conditions and set-off; no order as to costs.
- Legal Topics
- Variation Claims, Backcharges, Retention Sum, Pre Judgment Interest, Time Bar (contractual Notice), Lump Sum Contract, Set Off
- Source Language
- Malay/English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Kayangan Kemas Sdn. Bhd.
Plaintiff (suit 50) / Defendant (suits 32 & 33)
Kay Corporation Sdn. Bhd.
Defendant (suit 50) / Plaintiff (suits 32 & 33)
Procedural Posture
Civil Construction Contract Dispute / Judgment (trial Court Decision)
Legal Issues
- 1 Whether the Main Contract forms part of the Letter of Award dated 04.01.2016
- 2 Whether KC is entitled to claim for variation works
- 3 Whether the imposition of backcharges by KK is justifiable
Ratio Decidendi
Clause 2 of the LOA incorporated the Main Contract and bound KC; most of KC's variation claims failed because they lacked Employer/Consultant/Main Contractor approval and/or were time-barred under Clauses 50.1/50.3; KK's backcharges were largely unsupported by requisition/acknowledgement evidence and thus disallowed except for MCCT costs borne by KC and shared labour costs apportioned equally; retention and uncertified sums are payable subject to set-off against justified backcharges; KC's counterclaim dismissed in material part.
Court Disposition
Partial judgment: KC's counterclaim largely dismissed; KK entitled to limited recovery in Suit 50; KC awarded sums in Suits 32 and 33; retention/release subject to contractual conditions and set-off; no order as to costs.
Orders
- Suit 50: Kay Corporation Sdn. Bhd. to pay Kayangan Kemas Sdn. Bhd. RM146,420.46 (Judgment Sum)
- Suit 50: Interest at 5% per annum on RM146,420.46 from date of filing until full payment
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment