WTK ENGINEERING SDN. BHD. SERIEMAS DEVELOPMENT SDN. BHD.
The court construed 'due or payable' in s 30(5) CIPAA disjunctively: 'due' means an accrued debt owing under the contract and 'payable' means an amount fallen due for immediate payment such that there is an immediately enforceable obligation. Under the PAM Contract the second moiety of retention was not 'due' (owed)...
Source-derived case information.
- Citation
- WA-24C-189-09/2020 (Mahkamah Tinggi)
- Parties
- Applicant: WTK Engineering Sdn. Bhd.; Respondent: Seriemas Development Sdn. Bhd.
- Court
- High Court
- Jurisdiction
- Malaysia
- Judgment Date
- 18 January 2021
- Case Number
- WA-24C-189-09/2020 (Mahkamah Tinggi)
- Procedural Posture
- Originating Summons (enforcement Under S 30 Cipaa) / Judgment (high Court Decision Dismissing Application)
- Outcome
- Application dismissed
- Legal Topics
- S 30 CIPAA Direct Payment, Meaning of 'due or Payable', Retention Monies, Enforcement of Adjudication Decision, Contractual Condition Precedent (cmgd and Architect's Certificate)
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
WTK Engineering Sdn. Bhd.
Applicant
Seriemas Development Sdn. Bhd.
Respondent
Procedural Posture
Originating Summons (enforcement Under S 30 Cipaa) / Judgment (high Court Decision Dismissing Application)
Legal Issues
- 1 What is the meaning of the phrase 'due or payable' in s 30(5) CIPAA?
- 2 Was the second moiety of the retention sum due or payable by the principal (Seriemas) to the contractor (PA Builders) at the time Seriemas received the direct payment request on 3.6.2020?
- 3 Whether s 30 CIPAA could be invoked to require direct payment by the principal where contractual conditions for payment (CMGD and Architect's certificate) had not been satisfied?
Ratio Decidendi
The court construed 'due or payable' in s 30(5) CIPAA disjunctively: 'due' means an accrued debt owing under the contract and 'payable' means an amount fallen due for immediate payment such that there is an immediately enforceable obligation. Under the PAM Contract the second moiety of retention was not 'due' (owed) until issuance of the Certificate of Making Good Defects (CMGD) and was not 'payable' (immediately enforceable) until the Architect issued the residue certificate within 14 days of the CMGD and the payment period elapsed; because neither the CMGD nor the Architect's certificate was issued as at 3.6.2020, the statutory precondition in s 30(5) CIPAA was not satisfied and the...
Court Disposition
Application dismissed
Orders
- Application dismissed
- Costs in favour of Respondent Seriemas Development Sdn. Bhd. RM4000.00, subject to allocator
Full Case Text
Judgment text and source record