Dreamland Investment CC v Dichtl and Another (HC-MD-LAB-APP-AAA 13 of 2018) [2018] NALCMD 35 (12 December 2018)

Dreamland Investment CC v Dichtl and Another (HC-MD-LAB-APP-AAA 13 of 2018) [2018] NALCMD 35 (12 December 2018)

The appellant was properly notified of the hearing and failed to follow the prescribed procedure for postponement. The arbitrator was correct to refuse postponement and proceed in the appellant's absence. Conciliation could not be conducted without both parties present. There was no finding of waiver by the...

Source-derived case information.

Citation
[2018] NALCMD 35
Parties
Appellant: Dreamland Investment CC; First Respondent: Edmund Fritz Dichtl; Second Respondent: The Labour Commissioner
Court
Labour Court Main Division
Jurisdiction
Namibia
Case Number
HC-MD-LAB-APP-AAA 13 of 2018
Procedural Posture
Labour Appeal / Judgment on Appeal and Cross Appeal
Outcome
Appeal dismissed; arbitration award confirmed; cross-appeal referred back for further compensation consideration.
Legal Topics
Unfair Dismissal, Arbitration Award, Conciliation Procedure, Postponement of Proceedings
Source Language
en
Labour Law Unfair Dismissal Arbitration Award Conciliation Procedure Postponement of Proceedings

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Dreamland Investment CC

Appellant

Edmund Fritz Dichtl

First Respondent

The Labour Commissioner

Second Respondent

Procedural Posture

Labour Appeal / Judgment on Appeal and Cross Appeal

  1. 1 Whether the arbitrator erred in proceeding with arbitration without first attempting conciliation
  2. 2 Whether the arbitrator erred in refusing postponement and proceeding in absence of appellant
  3. 3 Whether the arbitrator erred in allowing evidence of settlement negotiations

Ratio Decidendi

The appellant was properly notified of the hearing and failed to follow the prescribed procedure for postponement. The arbitrator was correct to refuse postponement and proceed in the appellant's absence. Conciliation could not be conducted without both parties present. There was no finding of waiver by the arbitrator. The calculation of further compensation is a factual matter for the arbitrator, not the court.

Court Disposition

Appeal dismissed; arbitration award confirmed; cross-appeal referred back for further compensation consideration.

Orders

  • The arbitration award dated 18 January 2018 is confirmed and the matter is referred back to the same arbitrator to consider whether the respondent is entitled to further compensation as claimed in the cross-appeal, in addition to the compensation already granted.