Kaunapaua Ndilula N.O. v Edison Building Enterprises CC (HC-MD-CIV-ACT-CON- 4883 of 2021) [2022] NAHCMD 516 (29 September 2022)

Kaunapaua Ndilula N.O. v Edison Building Enterprises CC (HC-MD-CIV-ACT-CON- 4883 of 2021) [2022] NAHCMD 516 (29 September 2022)

Leave to amend particulars of claim is granted because objections raised by defendants pertain to excipiability and vagueness, which are not grounds to refuse amendment at this stage; such objections can be addressed by exception after pleadings are finalized.

Source-derived case information.

Citation
[2022] NAHCMD 516
Parties
1st Plaintiff: Kaunapaua Ndilula N. O.; 2nd Plaintiff: Evangelina Nangula Hamunyela N. O.; 3rd Plaintiff: Jacobus de la Rey du Toit N. O.; 4th Plaintiff: Andrew Campbell N. O.; 1st Defendant: Edison Building Enterprises CC; 2nd Defendant: Edison Kapuuo; 3rd Defendant: Mbakutua Rairirira Mbetjiha; 4th Defendant: The Minister of Works, Transport and Communication
Court
High Court Main Division
Jurisdiction
Namibia
Case Number
HC-MD-CIV-ACT-CON- 4883 of 2021
Procedural Posture
Civil (contract) / Application for Leave to Amend Pleadings
Outcome
Leave to amend granted; costs reserved; matter postponed for status hearing.
Legal Topics
Amendment of Pleadings, Objection to Amendment, Summary Judgment, Excipiability, Performance Guarantee
Source Language
en
Civil Procedure Contract Amendment of Pleadings Objection to Amendment Summary Judgment Excipiability Performance Guarantee

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Kaunapaua Ndilula N. O.

1st Plaintiff

Evangelina Nangula Hamunyela N. O.

2nd Plaintiff

Jacobus de la Rey du Toit N. O.

3rd Plaintiff

Andrew Campbell N. O.

4th Plaintiff

Edison Building Enterprises CC

1st Defendant

Edison Kapuuo

2nd Defendant

Mbakutua Rairirira Mbetjiha

3rd Defendant

The Minister of Works, Transport and Communication

4th Defendant

Procedural Posture

Civil (contract) / Application for Leave to Amend Pleadings

  1. 1 Whether plaintiffs should be granted leave to amend particulars of claim
  2. 2 Whether objections to amendment based on excipiability and vagueness are valid at this stage

Ratio Decidendi

Leave to amend particulars of claim is granted because objections raised by defendants pertain to excipiability and vagueness, which are not grounds to refuse amendment at this stage; such objections can be addressed by exception after pleadings are finalized.

Court Disposition

Leave to amend granted; costs reserved; matter postponed for status hearing.

Orders

  • Plaintiffs granted leave to amend particulars of claim as set out in notice dated 1 July 2022, amendment to be effected by 13 October 2022.
  • Costs occasioned by objection to amendment stand over for later decision.