ACM REMOVALS LTD v SOUTHERN DEMOLITION AND SALVAGE LTD [2019] NZHC 124

ACM REMOVALS LTD v SOUTHERN DEMOLITION AND SALVAGE LTD [2019] NZHC 124

The 12 November quotation supplemented but did not exclude the contractor's standard terms; the contract required removal of asbestos identified in the Optimum Report (including lift shafts to the basement and asbestos on tops of I-beams and pillars identified as 'areas of concern'); ACM Removals failed to perform a...

Source-derived case information.

Citation
[2019] NZHC 124
Parties
Plaintiff: ACM Removals Limited; Defendant: Southern Demolition and Salvage Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
12 February 2019
Procedural Posture
Breach of Contract Asbestos Removal (construction) / High Court Judgment After Trial
Outcome
Plaintiff's claims dismissed (contract claim, quantum meruit and liquidated damages); defendant entitled to withhold final payments; costs reserved
Legal Topics
Contract Interpretation, Quantum Meruit, Variations, Liquidated Damages, Penalty Doctrine, Asbestos Removal Obligations
Contract Law Construction Law Environmental/asbestos Regulation Contract Interpretation Quantum Meruit Variations Liquidated Damages Penalty Doctrine +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 5 Authorities cited 8 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

ACM Removals Limited

Plaintiff

Southern Demolition and Salvage Limited

Defendant

Procedural Posture

Breach of Contract Asbestos Removal (construction) / High Court Judgment After Trial

  1. 1 Whether the contract comprised the 9 November and 12 November quotations or the 12 November quotation alone and whether standard terms applied
  2. 2 Whether the contractual scope included the basement, lift shafts and tops of I-beams and specified pillars identified by the Optimum Report
  3. 3 Whether ACM Removals completed its contractual obligations

Ratio Decidendi

The 12 November quotation supplemented but did not exclude the contractor's standard terms; the contract required removal of asbestos identified in the Optimum Report (including lift shafts to the basement and asbestos on tops of I-beams and pillars identified as 'areas of concern'); ACM Removals failed to perform a substantive contractual obligation by not removing asbestos from the tops of the I-beams and therefore Southern Demolition was entitled to withhold final payments and to terminate; the contested variation claims lacked the required written agreement and quantum meruit does not assist because the disputed work fell within the contract; the liquidated damages claim fails and the...

Court Disposition

Plaintiff's claims dismissed (contract claim, quantum meruit and liquidated damages); defendant entitled to withhold final payments; costs reserved

Orders

  • Plaintiff's claim for breach of contract dismissed
  • Plaintiff's quantum meruit claim dismissed