MADILL & SMEED LIMITED AND ANOR V EBERT CONSTRUCTION LIMITED AND ORS HC AK CIV-2006-404-882
The contractual preconditions in NZS3910 clause 13 (timely referral to the Engineer within one month of the Final Payment Certificate) had not been met so Ebert had no contractual right to compel arbitration; it was not appropriate to imply a term permitting late referral for latent defects because that would...
Source-derived case information.
- Citation
- openlaw-291e9acf_5763_41f6_9e92_3a2688741f78.pdf
- Parties
- First Plaintiff: Madill & Smeed Limited; Second Plaintiff: Halls Refrigerated Transport Limited; First Defendant: Ebert Construction Limited; Second Defendant: Stiles & Hooker Limited; Third Defendant: Cowperthwaite Limited
- Court
- High Court
- Jurisdiction
- New Zealand
- Judgment Date
- 9 August 2006
- Procedural Posture
- Construction Contract Dispute (arbitration and Stay Applications) / Interlocutory Applications (application for Stay and Application for Extension of Time to Commence Arbitration)
- Outcome
- Application for stay of proceedings dismissed; application for extension of time to commence arbitration proceedings dismissed; costs awarded to plaintiffs
- Legal Topics
- Arbitration Clause Compliance, Time Limits for Dispute Referral, Implied Contractual Terms, Stay of Proceedings, Extension of Time Under Arbitration Act Second Schedule (clause 7)
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Madill & Smeed Limited
First Plaintiff
Halls Refrigerated Transport Limited
Second Plaintiff
Ebert Construction Limited
First Defendant
Stiles & Hooker Limited
Second Defendant
Cowperthwaite Limited
Third Defendant
Procedural Posture
Construction Contract Dispute (arbitration and Stay Applications) / Interlocutory Applications (application for Stay and Application for Extension of Time to Commence Arbitration)
Legal Issues
- 1 Whether Ebert complied with NZS3910 clause 13 preconditions (referral to Engineer within one month) and so has a contractual right to refer dispute to arbitration
- 2 Whether a term can be implied into clause 13 to allow referral for latent defects after the one month period
- 3 Whether the Court should extend time under clause 7 of the Second Schedule to the Arbitration Act 1996 on grounds of undue hardship
Ratio Decidendi
The contractual preconditions in NZS3910 clause 13 (timely referral to the Engineer within one month of the Final Payment Certificate) had not been met so Ebert had no contractual right to compel arbitration; it was not appropriate to imply a term permitting late referral for latent defects because that would improperly remake the parties' contract and is neither just nor obvious; Ebert failed to show undue hardship warranting an extension of time under clause 7 of the Second Schedule to the Arbitration Act 1996; accordingly both the application for a stay and the application for extension of time were dismissed.
Court Disposition
Application for stay of proceedings dismissed; application for extension of time to commence arbitration proceedings dismissed; costs awarded to plaintiffs
Orders
- Dismissal of Ebert Construction Limited's application for a stay of the High Court proceedings to enable arbitration
- Dismissal of Ebert Construction Limited's originating application for an order extending the time for commencement of arbitration proceedings under the Arbitration Act 1996 Second Schedule clause 7
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment