BAY OF PLENTY ELECTRICITY LTD V VECTOR GAS LTD CA CA444/07

BAY OF PLENTY ELECTRICITY LTD V VECTOR GAS LTD CA CA444/07

The Court held GC 9.1.6 is triggered by a reduction in NGC's legal entitlement to Maui gas following a redetermination (not limited to a purely physical incapacity) and is not a force majeure or exemption clause; accordingly NGC validly terminated the BoPE agreement. The Court further held the interim supply letters...

Source-derived case information.

Citation
openlaw-1c1fc8e6_1158_4c29_bc56_828d97f9c683.pdf
Parties
Appellant: Bay of Plenty Electricity Limited; Respondent: Vector Gas Limited
Court
Court of Appeal
Jurisdiction
New Zealand
Judgment Date
1 September 2008
Procedural Posture
Civil Appeal / Court of Appeal Judgment
Outcome
Appeal allowed in part: Court of Appeal confirmed validity of NGC's termination notice; set aside High Court judgment on the counterclaim and substituted declaratory and repayment orders; allocated costs.
Legal Topics
Termination Clause Interpretation, Force Majeure, Contract Interpretation, Interim Supply Agreement, Redetermination of Reserves, Priority of Service, Counterclaim for Price Difference
Contract Law Energy Law Commercial Law Termination Clause Interpretation Force Majeure Contract Interpretation Interim Supply Agreement Redetermination of Reserves +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Bay of Plenty Electricity Limited

Appellant

Vector Gas Limited

Respondent

Procedural Posture

Civil Appeal / Court of Appeal Judgment

  1. 1 Whether NGC validly terminated the 1995 BoPE Agreement under GC 9.1.6 following a redetermination of Maui gas reserves
  2. 2 Whether the interim supply agreement obliged BoPE to pay $6.50 per GJ inclusive or exclusive of transmission and metering costs
  3. 3 Whether the Strawman agreements meant the reduction in supply resulted from voluntary contractual adjustments rather than the redetermination

Ratio Decidendi

The Court held GC 9.1.6 is triggered by a reduction in NGC's legal entitlement to Maui gas following a redetermination (not limited to a purely physical incapacity) and is not a force majeure or exemption clause; accordingly NGC validly terminated the BoPE agreement. The Court further held the interim supply letters plainly required BoPE, if unsuccessful, to pay on demand the difference between the BoPE agreement price (as escalated, i.e. bundled delivered price) and $6.50 per GJ (including transmission and metering), plus contractual interest, and set aside the High Court decision upholding NGC's counterclaim to the contrary.

Court Disposition

Appeal allowed in part: Court of Appeal confirmed validity of NGC's termination notice; set aside High Court judgment on the counterclaim and substituted declaratory and repayment orders; allocated costs.

Orders

  • Confirmation that NGC validly terminated the BoPE agreement by notice dated 2 August 2004
  • Declaration that under the interim agreement BoPE undertook to pay NGC on demand for each GJ supplied the difference between the price set out in the BoPE agreement (as escalated) and $6.50 per GJ (including all transmission and metering costs), plus interest at the interest rate set out in the BoPE agreement