BODY CORPORATE 417948 AND OTHERS NAMED AT SCHEDULE 1 OF THE NOTICE OF APPEAL v WATTS & HUGHES CONSTRUCTION [2019] NZCA 113

BODY CORPORATE 417948 AND OTHERS NAMED AT SCHEDULE 1 OF THE NOTICE OF APPEAL v WATTS & HUGHES CONSTRUCTION [2019] NZCA 113

Leave to appeal was granted because the question of the correct application of r 7.6 to complex building remediation cases is arguable, the applicants put forward new evidence not before the High Court, the allocated fixture was more than a year away so delay from hearing the appeal would be limited, and the issue...

Source-derived case information.

Citation
[2019] NZCA 113
Parties
Applicant: Body Corporate 417948 and Others Named at Schedule 1 of the Notice of Appeal; First Respondent: Watts & Hughes Construction Limited; Second Respondent: Tauranga City Council; Third Respondent: Avery Team Architects Limited; Fourth Respondent: MPM Projects (2003) Limited; Fifth Respondent: GMR Holmac Limited; Sixth Respondent: Tile Trends Limited; Seventh Respondent: Armstrong Plumbing (BOP) Limited; Eighth Respondent: Holmes Structures Limited (In Liquidation); Ninth Respondent: Omaha Investments No. 1 Limited; Tenth Respondent: Robert James Foster; Eleventh Respondent: Bay of Plenty Asphalt Limited
Court
Court of Appeal
Jurisdiction
New Zealand
Judgment Date
16 April 2019
Procedural Posture
Application for Leave to Appeal / Leave Granted by Court of Appeal (application on the Papers)
Outcome
Leave to appeal granted
Legal Topics
Leave to Appeal, High Court Rules R 7.6, Case Management, Trial Timetabling, Weathertightness Remediation
Civil Procedure Building and Construction Appellate Law Leave to Appeal High Court Rules R 7.6 Case Management Trial Timetabling Weathertightness Remediation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Body Corporate 417948 and Others Named at Schedule 1 of the Notice of Appeal

Applicant

Watts & Hughes Construction Limited

First Respondent

Tauranga City Council

Second Respondent

Avery Team Architects Limited

Third Respondent

MPM Projects (2003) Limited

Fourth Respondent

GMR Holmac Limited

Fifth Respondent

Tile Trends Limited

Sixth Respondent

Armstrong Plumbing (BOP) Limited

Seventh Respondent

Holmes Structures Limited (In Liquidation)

Eighth Respondent

Omaha Investments No. 1 Limited

Ninth Respondent

Robert James Foster

Tenth Respondent

Bay of Plenty Asphalt Limited

Eleventh Respondent

Procedural Posture

Application for Leave to Appeal / Leave Granted by Court of Appeal (application on the Papers)

  1. 1 Whether the requirements of r 7.6 of the High Court Rules 2016 are satisfied on the facts of this case
  2. 2 Whether the High Court judge erred in fixing a trial date before repairs and crystallisation of losses
  3. 3 Whether delay to permit completion of repairs and amendment of pleadings is justified

Ratio Decidendi

Leave to appeal was granted because the question of the correct application of r 7.6 to complex building remediation cases is arguable, the applicants put forward new evidence not before the High Court, the allocated fixture was more than a year away so delay from hearing the appeal would be limited, and the issue is of sufficient importance to justify leave.

Court Disposition

Leave to appeal granted

Orders

  • Leave to appeal granted
  • Approved question: whether the requirements of r 7.6 of the High Court Rules 2016 are satisfied on the facts of this case