BODY CORPORATE S73368 v ROSALIND KAY OTWAY (NOW ROSALIND KAY WRIGHT) AND OLPHERT SANDFORD TRUSTEE SERVICE COMPANY LIMITED [2018] NZCA 612
Decks were within unit boundaries but defects arose from original design and construction of the building stormwater/weathertightness system so s127 did not apply; the remediation repaired an indivisible building element (the overall stormwater/weathertightness system) benefiting all units so s138(4) could not be...
Source-derived case information.
- Citation
- (2018) 20 NZCPR 477
- Parties
- Appellant: Body Corporate S73368; First Respondent: Rosalind Kay Otway (now Rosalind Kay Wright); First Respondent: Olphert Sandford Trustee Service Company Limited; Second Respondent: Philip Herbert Dorr; Second Respondent: Sharon Lesley Dorr; Second Respondent: Donald Raymond Pilbrow
- Court
- Court of Appeal
- Jurisdiction
- New Zealand
- Judgment Date
- 19 December 2018
- Procedural Posture
- Appeal (court of Appeal) / Determination on Appeal and Costs (final Judgment)
- Outcome
- Appeal dismissed; High Court substantive and costs decisions upheld in substance
- Legal Topics
- Unit Titles Act 2010 Ss 126, 127, 138(4), Recovery of Repair Costs, Building Elements and Infrastructure, Weathertightness Remediation, Calderbank Offers and Costs Consequences
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Body Corporate S73368
Appellant
Rosalind Kay Otway (now Rosalind Kay Wright)
First Respondent
Olphert Sandford Trustee Service Company Limited
First Respondent
Philip Herbert Dorr
Second Respondent
Sharon Lesley Dorr
Second Respondent
Donald Raymond Pilbrow
Second Respondent
Procedural Posture
Appeal (court of Appeal) / Determination on Appeal and Costs (final Judgment)
Legal Issues
- 1 Are the decks within the unit boundaries and therefore unit property?
- 2 Can the body corporate recover repair costs under s127 (fault) where defects arise from construction/design)?
- 3 What is the relationship between s126 (substantial benefit apportionment) and s138(4) (recovery from owner of unit containing building element)?
Ratio Decidendi
Decks were within unit boundaries but defects arose from original design and construction of the building stormwater/weathertightness system so s127 did not apply; the remediation repaired an indivisible building element (the overall stormwater/weathertightness system) benefiting all units so s138(4) could not be used as a standalone mechanism to shift the bulk of costs onto individual unit owners and must be read down where ss126/127 apply; limited joinery works benefiting particular units were recoverable under s126; the respondents' Calderbank offer of 7 August 2017 was sufficiently clear and more beneficial than the judgment so costs consequences followed; appeal dismissed.
Court Disposition
Appeal dismissed; High Court substantive and costs decisions upheld in substance
Orders
- Appeals dismissed
- High Court substantive judgment and awards affirmed (including limited recovery for joinery works under s126)
Full Case Text
Judgment text and source record
1 paragraphs
BODY CORPORATE S73368 v ROSALIND KAY OTWAY (NOW ROSALIND KAY WRIGHT) ANDOLPHERT SANDFORD TRUSTEE SERVICE COMPANY LIMITED [2018] NZCA 612 [19 December 2018]IN THE COURT OF APPEAL OF NEW ZEALANDI TE KŌTI PĪRA O AOTEAROACA71/2018[2018] NZCA 612BETWEEN BODY CORPORATE S73368AppellantAND ROSALIND KAY OTWAY (NOWROSALIND KAY WRIGHT) ANDOLPHERT SANDFORD TRUSTEESERVICE COMPANY LIMITEDFirst RespondentsPHILIP HERBERT DORR,SHARON LESLEY DORR ANDDONALD RAYMOND PILBROWSecond RespondentsCA319/2018BETWEEN BODY CORPORATE S73368AppellantAND ROSALIND KAY OTWAY (NOWROSALIND KAY WRIGHT) ANDOLPHERT SANDFORD TRUSTEESERVICE COMPANY LIMITEDFirst RespondentsPHILIP HERBERT DORR,SHARON LESLEY DORR ANDDONALD RAYMOND PILBROWSecond RespondentsHearing: 27 August 2018Court: Miller, Mallon and Gendall JJCounsel: S C Price and I J Stephenson for AppellantG Brittain QC and J Delaney for RespondentsJudgment: 19 December 2018 at 2.00 pmJUDGMENT OF THE COURTA The appeals are dismissed.B The appellant must pay the respondents one set of costs for a standardappeal on a band A basis and usual disbursements.____________________________________________________________________REASONS OF THE COURT(Given by Gendall J)Introduction[1] Maintenance and repair issues in unit title developments and the question ofwho pays for required repairs have caused some difficulty recently, particularly in thecontext of leaky buildings.1[2] This appeal concerns a dispute regarding the responsibility of the respondentapartment owners to pay for substantial repairs undertaken by the appellantBody Corporate on a leaking unit title apartment block at Mount Maunganui.The Body Corporate appeals the substantive decision on this dispute given byWoolford J in the High Court of 20 December 2017,2 and his costs decision of17 May 2018.3Background[3] The respondents own two apartments on the first floor of the 12 storey mixedresidential and commercial unit title development known as Oceanside Tower Two,located across the road from the beach at Mount Maunganui. The first floor has largedecks which sit above ground-floor shops and the public footpath. The decks are1 This has been recognised by a range of commentators in this area including Lisa Fry-Irvine andTim Jones "Challenges for Bodies Corporate" (New Zealand Law Society webinar, 2015) at 1;and Elizabeth Toomey and others "Revised Legal Frameworks for Ownership and Use ofMulti-dwelling Units" (BRANZ External Research Report, University of Canterbury, 2017)at 191–192 and 230–235.2 Body Corporate S73368 v Otway [2017] NZHC 3265 [HC substantive judgment].3 Body Corporate S73368 v Otway [2018] NZHC 1095 [HC costs judgment].formed by a concrete slab sitting on structural steel beams. Previously, the concreteslab was covered by a butyl rubber membrane with ceramic tiles laid on top.These decks had been leaking since at least 2009, due in large measure to thepremature failure of the waterproof membrane.[4] The Body Corporate requested the respondents, as the owners of the decks, torepair them but they refused. This refusal continued for some years and the deckscontinued to leak into the ground-floor commercial shop units.[5] In 2014, the Body Corporate began to carry out repairs to the decks and thebuilding pursuant to the Unit Titles Act 2010 (the UTA 2010). The work wascompleted and a code compliance certificate issued on 17 November 2014. The repaircosts totalled $841,838.56. This cost was met initially by levies imposed bythe Body Corporate on all unit owners in the development. The Body Corporate brokethese repair costs into three categories:(a) balcony works (excluding joinery and drainage Works) —$591,459.64;(b) joinery works — $183,739.46; and(c) drainage works — $66,639.46.[6] The Body Corporate elected to treat the drainage works as infrastructure forthe building as a whole so it did not pursue that cost from the respondents.The Body Corporate, however, sought $290,830.43 from each of the respondents forthe balcony works and the joinery works.4[7] In 2015, the Body Corporate carried out other work relating to these repairs.This involved removing soffit linings, repairing structural steel under the decks,replacing the soffits and painting them (the podium and soffit works). This work was4 The third unit on the first floor contributed to the cost of these works and was not a defendant inthis proceeding.completed at a total cost of $115,129.09. The Body Corporate sought from each ofthe respondents $24,488.05 for this work.[8] The basis on which the Body Corporate sought recovery of the repair costsunder the UTA 2010 was:(a) The s 127 claim — given that the Body Corporate said that the deckswere the respondents' unit property, they were obliged (from at least2009 to 2012) to repair and maintain their decks pursuant to r 1(e) ofthe then Body Corporate Rules.5 The respondents did not do so inbreach of that obligation which resulted in the Body Corporate havingto undertake the work. This work was completed on the basisthe Body Corporate was entitled to recover from the respondents theresulting repair costs pursuant to s 127 as a fault provision.(b) The s 138(4) claim — again, on the basis that the decks werethe respondents' unit property, the Body Corporate said it was entitledto recover from them the costs of repairing these decks (beingbuilding elements that served or related to more than one unit) pursuantto s 138(4) of the UTA 2010.(c) The s 126 claim — this claim was advanced alternatively in the eventthat recovery under the fault section, ss 127 and/or 138(4), proved notto be available. If this was found to be the case, the Body Corporatesought part recovery of the repair costs under s 126 on the basis that the5 Since the passage of the Unit Titles Act 2010 [UTA 2010] this obligation has also been broadlyoutlined in s 80(1)(g), which provides:(1) An owner of a principal unit—(g) must repair and maintain the unit and keep it in good order to ensurethat no damage or harm, whether physical, economic, or otherwise,is, or has the potential to be, caused to the common property, anybuilding element, any infrastructure, or any other unit in thebuilding:repairs to the respondents' decks were said to benefit their first-floorunits (and the ground-floor units) substantially more than the otherunits in the apartment block.The Unit Titles Act 2010[9] Provisions in the UTA 2010 of relevance here are:126 Recovery of money expended for repairs and other work(1) This section applies where the body corporate does any repair, work,or act that it is required or authorised to do, by or under this Act, or byor under any other Act, but the repair, work, or act—(a) is substantially for the benefit of 1 unit only; or(b) is substantially for the benefit of some of the units only; or(c) benefits 1 or more of the units substantially more than itbenefits the others or other of them.(2) Any expense incurred by the body corporate in doing the repair, work,or act is recoverable by it as a debt in any court of competentjurisdiction (less any amount already paid) in accordance with thefollowing:(a) so far as the repair, work, or act benefits any unit by a distinctand ascertainable amount, the owner at the time when theexpense was incurred and the owner at the time when theaction is instituted are jointly and severally liable for the debt;or(b) so far as the amount of the debt is not met in accordance withthe provisions of paragraph (a), it must be apportioned amongthe units that derive a substantial benefit from the repair,work, or act rateably according to the utility interest of thoseunits, and in the case of each of those units, the owner at thetime when the expense was incurred and the owner at the timewhen the action is instituted are jointly and severally liablefor the amount apportioned to that unit.(3) Despite subsection (2)(b), if the court considers that it would beinequitable to apportion the amount of the debt in proportion to theutility interest of the unit owners referred to in that paragraph, it mayapportion that amount in relation to those units in the shares as itthinks fit, having regard to the relative benefits to those units.127 Recovery of money expended where person at fault(1) This section applies if the body corporate does any repair, work, or actthat it is required or authorised to do, by or under this Act, or by orunder any other Act, and the repair, work, or act was renderednecessary by reason of any wilful or negligent act or omission on thepart of, or any breach of the Act, the body corporate operational rules,or any regulations by, any unit owner or his or her tenant, lessee,licensee, or invitee.(2) Any expense incurred by the body corporate in doing the repair, work,or act, together with any reasonable costs incurred in collecting theexpense, is recoverable as a debt due to the body corporate (less anyamount already paid) by the person who was the unit owner at thetime the expense became payable or by the person who is the unitowner at the time proceedings are instituted.138 Body corporate duties of repair and maintenance(1) The body corporate must repair and maintain—(a) the common property; and(d) any building elements and infrastructure that relate to or servemore than 1 unit.(4) Any costs incurred by the body corporate that relate to repairs to ormaintenance of building elements and infrastructure contained in aprincipal unit are recoverable by the body corporate from the ownerof that unit as a debt due to the body corporate (less any amountalready paid) by the person who was the unit owner at the time theexpense was incurred or by the person who is the unit owner at thetime the proceedings are instituted.The High Court substantive decision[10] We turn first to the Judge's substantive decision of 20 December 2017.Before the Body Corporate's claims under the UTA 2010 could be determined,the Judge had to resolve the preliminary issue as to where the floor boundaries ofthe respondents' units were located. Initially, the respondents had claimed their legalfloor boundaries were some two to 15 centimetres above the concrete floor slabs intheir apartments and decks. Thus, they denied they owned the decks and said that,given the decks were not their unit property, they were not responsible for the repairsrequired. The Body Corporate refuted this and argued that the concrete floor slabs ofthe decks in particular came within the respondents' units.[11] The Judge rejected the respondents' denial and held the respondents' deckswere their respective unit property. He found the location of the legal boundariesbetween unit floors in the tower block of the apartments was the top of the respectiveconcrete floor slabs. This included the top of the concrete floor slab constituting thedeck of each of the respondents' units. In other words, the decks were part of eachrespondent's own unit property and that included all material above the top of theconcrete floor slab, being the waterproof membrane and the ceramic surface tiles.6[12] The Judge's conclusion on this point is not the subject of this appeal.Our judgment proceeds on his unchallenged findings as to the boundaries of the units.[13] We turn now to the Body Corporate's claims to recover the repair costs fromthe respondents under ss 126, 127 and 138(4) of the UTA 2010.[14] Addressing first the s 127 claim, the Judge held that the Body Corporate couldnot recover any of the repair costs under this section. He found that the respondentshad "not committed any wilful or negligent act in breach of the [UTA 2010] orthe body corporate operational rules".7 He was of the view that:8the defects must have been caused during the construction process throughincorrect product specification, poor or incorrect installation, or incompleteinstallation.And:9the damage caused by the defective membrane was not the result of a failureon the part of the first-floor apartment owners to keep their units in sufficientlygood order, repair and condition, but a failure during the construction process.In determining that the membrane failed prematurely due to errors in the design andconstruction process, he found too that the overall storm water system for the buildingno longer met the requirements of the current Building Code.106 HC substantive judgment, above n 2, at [13]–[14].7 At [36].8 At [21].9 At [23].10 At [29].[15] Next, addressing s 126, the Judge noted that this provision enablesthe Body Corporate to recover repair costs from a unit owner if the repair work hasbenefitted that unit "by a distinct and ascertainable amount".11 Otherwise, the costsmust be apportioned among the units that derive a substantial benefit from the repairwork according to the utility interest of those units.[16] The Judge accepted that the membrane on the decks was an important part ofthe storm water system for the entire apartment building. The replacement of thismembrane necessitated the balcony works, the joinery works and the drainage worksto ensure the requirements of the current Building Code were met.12[17] He found that the repair works did not benefit the first-floor units more thanother units by a distinct and ascertainable amount because:13(a) the weathertightness of the entire building is interlinked and indivisibleso the repairs affected all units;(b) although the first-floor units own from the top of the concrete slab,the membrane and the tiles, the concrete floor slab itself is owned bythe ground-floor units or by the Body Corporate as common property;(c) the allocation by the Body Corporate of repair costs has been somewhatarbitrary;(d) each of the unit owners bought into the building as a whole, not justtheir individual units;(e) the sharing of common property repair costs on a unit entitlement basisnecessarily contemplates there may be an element ofdisproportionality;11 At [26].12 At [29].13 At [30].(f) if any part of a building is not weathertight, then that adversely affectsthe saleability and value of all units, regardless of whether theythemselves are in fact leaky; and(g) the first-floor units, in any event, will pay proportionally more thanalmost all other unit owners based on their unit entitlements which takeinto account the floor area of their extensive decks.[18] The Judge made one exception. This was with regard to the new joineryinstalled in the first-floor apartments. He found these repairs were for the distinct andascertainable benefit of those units.14 He ordered payment of $44,344.75 from eachrespondent under s 126(2)(a) or s 126(3). This was lower than the sum sought bythe Body Corporate ($68,993.29) because the Judge considered some costs for thiswork, such as scaffolding, could not be directly connected with the installation ofthe joinery.15[19] Finally, turning to consider s 138(4), the Judge was of the view that this wasnot limited to circumstances where s 126 does not apply. Rather, he said they arealternative modes of recovery. He found that there was some limited jurisdiction alsounder s 138(4) here, but only to order the respondents to pay for the specific newwindow joinery installed in their units.16Appeal against the substantive decision[20] The Body Corporate raises two main questions on its appeal against the Judge'ssubstantive decision. The High Court having found that the respondents own theirdecks, the issues are:(a) Was the Body Corporate entitled to recover the costs of repairing thedecks under s 127 of the UTA 2010 on the basis that the BodyCorporate's carrying out of the deck repairs resulted from14 At [31]–[32].15 At [33] and [41]. Any issues of possible betterment related to the new joinery in the respondents'apartments it seems were not raised, as Woolford J made no mention of this in his judgment.16 At [40].the respondents' sustained breach of r 1(e) of the Body CorporateRules? Linked to this question is the issue as to whether the membranewas the major contributor to the water leaks and consequential damageto the ground floors, thus necessitating the remedial work.(b) Was the Body Corporate entitled to recover the costs of repairing thedecks under s 138(4) of the UTA 2010 on the basis the repairs were tothe respondents' unit property? This question also involves aconsideration of whether or not s 138(4) of the UTA 2010 is limited tocircumstances where s 126 of the UTA 2010 does not apply.[21] The Body Corporate also addresses some argument to the issue of itsentitlement under s 126 with regard to the podium and soffit works.Recovery under s 127[22] At trial, the Body Corporate submitted that the respondents owned their decksand refused to repair the defects in them. This caused water damage to continue in thedownstairs units for many years, until, in 2012, it became clear thatthe Body Corporate, in light of the provisions in the new UTA 2010, was authorisedto fix the failing waterproof membrane which it said was causing the problems.The Judge did not allow recovery under s 127 because he found the defects werecaused during the construction process.17 Therefore, it was not a result ofthe respondents' failure to keep their units in sufficiently good order, repair andcondition.18[23] The Body Corporate now maintains now that the Judge erred in determiningrecovery under s 127 on this basis. It argues that the respondents were required torepair the decks in terms of r 1(e) of the operative Body Corporate Rules but refusedto. At the material time r 1(e) required that a unit proprietor shall:Repair and maintain his Unit and keep it in sufficiently good order, repair andcondition to ensure that no damage or harm shall ensue to the commonproperty or any other Unit in the building to which the Unit forms part.17 At [21] and [36].18 At [23] and [36].The Body Corporate submits that, as the Judge determined that the respondents didown their decks, repairs were required to stop the leaking which was causing damageto the downstairs units and other common property, so the grounds for recovery unders 127 were met. It was the respondents' failure to carry out the repairs that resulted inthe Body Corporate having to incur the costs of completing them.[24] The wording of s 127 indicates that liability arises when the repair is madenecessary because the unit owner has either: committed any wilful or negligent act oromission; or breached the UTA 2010, body corporate rules or any regulations.[25] The Body Corporate's case is that the respondents breached r 1(e) of itsoperative rules by failing to repair and keep in good order their unit property, beingthe decks. This failure made it necessary for the Body Corporate to undertake therepairs. Thus, under s 127(2), it is entitled to recover from the respondents the amountspent on the repairs.[26] In response, the respondents submit that the Body Corporate's claim unders 127 fails on the facts as the evidence confirms that the repairs were necessarybecause of widespread defects in the original design and construction of the building.They argue that the repair work substantially benefitted all of the units by making thedevelopment as a whole, including the roof of the ground-floor units, watertight andensuring that the storm water drainage system for the entire apartment tower compliedwith the Building Code.[27] On these aspects, we accept that the repairs carried out in 2014 and 2015, whichincluded work to the respondents' decks, were part of an indivisible remediationproject to fix what were design and construction defects in the storm water disposalsystem for the building as a whole. The evidence here confirmed that this storm waterdrainage system, which included the necessary run-off from the tower block tothe respondents' decks, was both under-designed and defective in its originalconstruction. In reality, the repairs and remediation work undertaken effectivelyprovided an entirely new storm water disposal system as for the building, such that itcould now meet the requirements of the current Building Code. Much was made hereof the defects in the waterproof membrane and the contribution of this to deck leaksto the ground-floor shops. We accept that the membrane was an important part of theoverall drainage plane and integral to the storm water disposal system, but it wasthrough its premature failure that these issues were caused. As the Judge noted, thereis also no evidence of any post-installation damage to the membrane.19 We find, too,that the evidence indicates the membrane problems were only one of a number ofdefects in the original design and construction of the building's storm water disposalsystem which necessitated the work undertaken by the Body Corporate.[28] For completeness, we note that the Judge concluded:20In the present case, I am of the view that the first-floor apartment owners havenot committed any wilful or negligent act in breach of the Act orthe body corporate operational rules. The waterproof membrane on the decksfailed prematurely and therefore did not meet the requirements ofthe Building Code. [29] With respect, we record that the Judge has confused the requirements ofs 127(1) of the UTA 2010 here. As we noted at [24] above, the Body Corporate'srepair or work must be rendered necessary by reason of either "any wilful or negligentact or omission on the part ofany unit owner" or "any breach of the UTA 2010,the Body Corporate Operational Rules, or any regulations by any unit owner".Notwithstanding this, we accept the confusion here is only minor and has little realimpact on the Judge's overall conclusion that the respondents were not at fault in termsof s 127 of the UTA 2010. We agree with this conclusion. The Body Corporatetherefore cannot recover repair costs under this fault provision from the respondents.[30] We agree with the Judge therefore that the Body Corporate is unable to recoverfrom the respondents any of the repair costs under s 127 of the UTA 2010.Recovery under s 138(4)[31] Section 138(1) of the UTA 2010 obliges the Body Corporate to repair andmaintain "the common property",21 and also "any building elements and infrastructurethat relate to or serve more than 1 unit".22 The deck areas in question here meet the19 At [21].20 At [36].21 UTA 2010, s 138(1)(a).22 Section 138(1)(d).definition of a "building element" and it is common ground that the deck areas servemore than one unit.23 Therefore, it is clear that, absent some obligation on unit ownersto do so, the Body Corporate in this case was under an obligation to repair and maintainthe decks as "building elements".[32] Section 138(4) of the UTA 2010, however, is problematical. An immediatedifficulty arising is whether the Body Corporate can require one or more individualunit owners to pay for these "building elements" repair costs, or whetherthe Body Corporate as a whole should meet these costs. This argument also involvesthe question whether, absent substantial benefit to a particular unit owner or fault onthe part of that unit owner, the Body Corporate has to meet those costs itself.[33] This brings into play s 126 of the UTA 2010. This section provides for thesharing of repair costs disproportionately on the basis that the repairs benefitted certainunits substantially more than other units.[34] In his substantive decision, the Judge found:(a) with respect to the s 138(4) claim, the respondents were to pay only anamount in respect of window joinery replacement specific to their units,representing a small part of the total costs of the deck and storm watersystem repairs;24 and(b) with respect to the s 126 claim, no order for recovery of repairs wasmade, other than for the window joinery works noted above, on thebasis that the Judge did not consider the respondents to have received"distinct and ascertainable benefit" from the deck repairs.25[35] It is apparent that the relationship between s 138(4) and s 126 of the UTA 2010created some potential difficulty here. This difficulty was the focus of a large part ofthe argument before us on this appeal. It is a significant issue in this and other cases,2623 Section 5(1), definition of "building elements".24 HC substantive judgment, above n 2, at [40].25 At [32].26 In Body Corporate 324525 v Stent [2017] NZHC 2857, which involved a not dissimilar leakybuilding unit title development at Paihia, Associate Judge Bell at [211] noted:and has also been recognised by commentators in this area.27 We now turn to addressthe relationship between these provisions.The relationship between ss 138(4) and s 126[36] The legislative history of s 138(4) of the UTA 2010 is well set out in the recentHigh Court judgment of van Bohemen J in Body Corporate 199380 v Cook.28We adopt that account. Relevantly the Unit Titles Act 1972 (the UTA 1972) did notexpressly provide that a body corporate might repair individually-owned unit propertywhen the repairs related to the integrity of or damage to common property. This issuearose fairly often as a consequence of the leaky building crisis.[37] In Berachan Investments Ltd v Body Corporate 164205 this Court held that abody corporate could, under the UTA 1972, undertake obligations to repair unitproperty if those obligations were incidental to its duties to maintain and repaircommon property.29 However, a body corporate could only undertake responsibilitiesto repair unit property under the UTA 1972 in two ways: pursuant to a rule under s 37of that Act (and only if the "incidental" test from Berachan was satisfied), or undera scheme for repairs to the building approved by the Court pursuant to s 48 ofthat Act.30 The approval of schemes that allowed for the body corporate to undertakerepairs to common property was discussed by this Court in Tisch v Body CorporateNo 318596.31 Notably, the Court there emphasised that, though it was possible todepart from the scheme of the UTA 1972 and the body corporate rules (and sopotentially allow for repairs to unit property), any departure should be no more than"To carry out works [the Body Corporate is required to do] the body corporate will use its fundsderived from levies paid by all owners. It may then look to owners under ss 126, 127 and 138(4).Whether it does so is for it to decide. It may, but cannot be required to, make claims under thesesections. Such claims are not straightforward." (Emphasis added.)27 See for example Thomas Gibbons "Maintenance" (paper presented to New Zealand Law SocietyUnit Titles Intensive Conference, April 2013) at 68:"Ultimately, there is potential for a conflict between s 138(4) and s 126(2). Should costsrecovery depend on whose property the building element rests within, or on who will benefitfrom the repair. Perhaps in this instance, the specific should prevail over the general, though ageneral reliance on s 126 seems more appropriate in many cases."28 Body Corporate 199380 v Cook [2018] NZHC 1244.29 Berachan Investments Ltd v Body Corporate 164205 [2012] NZCA 256, [2012] 3 NZLR 72at [46].30 We need not express a view as to whether s 33 of the Unit Titles Act 1972 [UTA 1972] permittedbody corporates to recover costs for repairs done to unit property. Compare Cook, above n 28,at [58]–[59].31 Tisch v Body Corporate No 318596 [2011] NZCA 420, [2011] 3 NZLR 679.was reasonably necessary to achieve fairness between unit holders in thecircumstances.32 It also emphasised that relative benefits between owners was not areason to depart from the scheme of the UTA 1972, and that ordinarily owners shouldbe taken to have purchased their units knowing their individual obligations for theirunit property.33[38] Against this backdrop Parliament enacted the UTA 2010, which changed theobligations on a body corporate with regard to unit property. Whereas underthe UTA 1972 the body corporate was obliged to "keep the common property in a stateof good repair",34 the UTA 2010 requires a body corporate to repair and maintain"the common property" and any "building elements" and "infrastructure" that relateto or serve more than one unit.35 As this Court explained in Wheeldon v BodyCorporate 342525, the UTA 2010 introduced the concept of building elements —those components necessary to the building's structural integrity or exterior aestheticsor to the health and safety of its occupants or users36 — to address the dilemma createdby defects within a unit that might affect another unit or the development as a whole.37To that end, the UTA 2010 circumscribed the property rights of unit owners byrequiring that they permit the body corporate access to repair building elementsaffecting another unit or the common property,38 and by limiting their right to altertheir own units without the body corporate's consent.39 The UTA 2010's processes areintended to prevent holdout problems that arose under the former legislation when unitowners refused to repair their units or permit repairs.40 To the same end, as the Courtwent on to explain, the UTA 2010 limited the unit-owner's obligation to repair andmaintain their own unit;41 it is an obligation to repair and maintain the unit to avoiddamage to building elements rather than to repair and maintain the building elementsthemselves.4232 At [49].33 At [64].34 UTA 1972, s 15(1)(f).35 UTA 2010, s 138(1).36 Section 5(1), definition of "building elements".37 Wheeldon v Body Corporate 342525 [2016] NZCA 247, (2016) 17 NZCPR 353 at [35].38 UTA 2010, s 80(1)(a).39 Sections 80(1)(i) and s 79(e). See also Wheeldon, above n 37, at [37].40 (30 March 2010) 661 NZPD 10217 and 10219.41 UTA 2010, s 80(1)(g).42 Wheeldon, above n 37, at [38].[39] The deck and the balcony and podium and soffit works in this case arebuilding elements. The Body Corporate was obliged to repair them under s 138(1)(d)and entitled to access the units for that purpose under s 80(1)(a). The argument in thepresent case centres on whether the Body Corporate is entitled to recover the repaircosts from the owners under s 138(4).[40] We have quoted s 138(4) at [9] above. It provides that the costs incurred bythe Body Corporate that relate to repairs or maintenance of building elements andinfrastructure "contained in a principal unit" are recoverable from the owner of thatunit.[41] Subsection 138(4) is the product of a departmental report prepared by the thenDepartment of Building and Housing for the relevant select committee during thelegislative process. Submitters to the Committee were concerned as to who would payfor repair costs, and specifically as to how the relationship between what is now ss 126,127 and 138(4) of the UTA 2010 would operate in practice. The Departmentresponded to those concerns:43Some submitters were confused over the link between a unit owner'sresponsibility to repair and maintain their unit and the body corporateresponsibility to repair and maintain all building elements and infrastructurethat affect more than one unit All building elements and infrastructure thatrelate to or serve more than one unit ought to be maintained by the bodycorporate, but costs should be recoverable from the unit owners in instanceswhere those unit owners substantially benefit from the repair or are at faultunder clauses 111 and 112.RecommendationAdd sub-clause to clause 122 to indicate that costs may be recovered from theowner of the principal unit if the body corporate does any repair work tothe building elements or infrastructure that are contained within a unit owner'sprincipal unit.[42] It will be seen that the Department wanted to assign liability for buildingelement repairs to unit owners only where they were at fault or benefited substantiallyfrom the repair. This is merely declaratory of what became sections 126 and 127.The Select Committee report explained that what became s 138 set out43 Department of Building and Housing Departmental Report to the Social Services SelectCommittee on the Unit Titles Bill 2008 (July 2009) at 20–21 (emphasis added).the body corporate's duties of repair and maintenance for "common property,building elements and infrastructure" but had been silent on who must pay for workdone "on elements forming part of an individual unit".44 As we see it, the Committeeenvisaged the new provision s 138(4) as being subsidiary to ss 126 and 127, whichwere to prevail where they applied. Section 138(4) would only apply to repair workdone by the body corporate either on elements within a unit that were not buildingelements or infrastructure or on building elements themselves where ss 126 or 127 didnot apply. As to this latter situation, the Committee recognised the possibility thatrepairs to a building element as defined either may have been caused by fault on thepart of the unit owner or were such that the repairs did not benefit any other unit owner,and therefore the cost should be met by the unit owner alone. We expand on thisbelow.[43] The Body Corporate here endeavoured to maintain that s 138(4) sets up aparallel recovery mechanism for building elements or infrastructure within a unitboundary and says it can employ s 138(4) at its discretion. But this was the sameargument that failed in Cook, where van Bohemen J summarised it as a claim that,despite its many differences from the predecessor legislation, the UTA 2010deliberately assigns responsibility for remedial work to unit owners regardless ofbenefit.45[44] In the judgment under appeal, the Judge suggested that ss 126 and 138(4) areindeed alternative modes of recovery.46 As van Bohemen J noted in Cook, however,the Judge's conclusion, which was confined to the joinery works and made nodifference in the result, was somewhat at odds with his findings about the decks.47[45] In our view, the legislative policy is clear and s 138(4) can be interpreted in amanner consistent with it. We reach this conclusion for reasons relating directly to thelegislative purpose of Parliament in passing the UTA 2010. In addressing the mischiefto which this enactment was directed, the legislature sought to address difficulties thathad arisen when defects within a unit affected other units or the common property.44 Unit Titles Bill 2008 (212–2) (select committee report) at 27–28.45 Cook, above n 28, at [93].46 HC substantive judgment, above n 2, at [40].47 Cook, above n 28, at [86]–[89].It did so by assigning to bodies corporate responsibility for building elements andinfrastructure found within units and limiting owners' rights and obligationsaccordingly.48 The legislation permits a body corporate to act to prevent harm that hasthe potential to harm the common property, or any building element or any other unit.In s 126 the legislature created the necessary corollary, a flexible mechanism torecover from owners the costs of remedial work done by the body corporate: an ownerwho benefits in a substantial way must pay, and in other cases those owners who derivea substantial benefit must pay rateably according to their utility interests. In s 127 itprovided that an owner who is at fault may be required to pay. And in s 138(4) itprovided for the case where work is done on elements "contained in" a unit that mayprove to be building elements or infrastructure or in some cases may not.The legislation recognises that the bases on which costs may be assigned under theseprovisions may be unknown when the work is commissioned. For example, it maynot be known whether an element within a unit is a building element as defined; thatdepends on whether any given damage or defect may affect structural integrity,external aesthetics or health and safety. Whether an element qualifies as such maydepend at least in part on the potential for it to affect other units.[46] As we noted above at [32], on its face, s 138(4) is somewhat problematical.A plain and literal reading of the words of this provision might be seen as allowingstand-alone recovery against only one unit owner in a case such as this which thereforecuts across s 126 and 127 and the overall scheme of the UTA 2010.[47] The learned author of Burrows and Carter: Statute Law in New Zealandaddresses inconsistency between legislative provisions and states:49Apparently inconsistent provisions may appear in the same Act for a numberof reasons. Sometimes in a long Act the framers may fail adequately to spellout the relationship between various sections; sometimes amendment of a Billin the course of the parliamentary process may add a section that does notsquare satisfactorily with provisions in other parts of the Act; sometimes alater amendment to the Act, perhaps years after its original passage, may addprovisions that do not fit comfortably with the rest of it; sometimesconsolidation of several Acts may draw together sections that are not inharmony with each other.48 Clearly this can be inferred from the unit owners' responsibilities in s 80(1) andthe Body Corporate's duties of repairs and maintenance in s 138 of the UTA 2010.49 Ross Carter Burrows and Carter: Statute Law in New Zealand (5th ed, LexisNexis, Wellington,2015) at 463–464 (footnotes omitted).Normally it will be found, on reading the Act as a whole, taking into accountscheme and purpose, that the two provisions can in fact be read consistently,albeit by "reading down" one of them. There are numerous cases when such reconciliation has been necessary.Sometimes the reconciliation requires a strained interpretation to be given toone section; the law has always recognised that the avoidance of an internalinconsistency can justify some liberality with words.[48] With this in mind, a purposive construction of the UTA 2010 is required,construing the meaning of the words in s 138(4) against the legislative purpose ofthe Act to ensure the overall scheme and functionality of the Act is respected.50[49] A statement of purpose may be set out in the text of an Act. In the case of theUTA 2010 this occurs in s 3 which relevantly states:3 PurposeThe purpose of this Act is to provide a legal framework for the ownershipand management of land and associated buildings and facilities on asocially and economically sustainable basis by communities of individualowners and, in particular,—(a) to allow for the subdivision of land and buildings into unittitle developments; and(b) to create bodies corporate, which comprise all unit owners ina development, to operate and manage unit titledevelopments; and(c) to establish a flexible and responsive regime for thegovernance of unit title developments; and(d) to protect the integrity of the development as a whole.(Emphasis added.)[50] The function of a purpose clause such as s 3 is to provide a guiding principlefor interpreting the text of the Act. This statement of the main purpose of the UTA2010 in s 3 emphasises that the position of the community of owners is important.50 It is useful to remember the "golden rule" that generally purpose is to prevail andLord Wensleydale's classic statement of this rule in Grey v Pearson (1857) 6 HL Cas 61 wherehe said at 106: "the grammatical and ordinary sense of the words is to be adhered to, unless thatwould lead to some absurdity, or some repugnance or inconsistency with the rest of theinstrument, in which case the grammatical and ordinary sense of the words may be modified, soas to avoid the absurdity and inconsistency, but no further". (Emphasis added.)Increasingly, as commentators in this area have emphasised, in unit title developments,the whole is to prevail over the one.51[51] In the present case, an important question is how the building elements inquestion are to be defined. Are these building elements simply a repair to the owners'deck, or to the deck membrane, or is it a repair to the overall storm water disposalsystem for the building which necessarily goes to its weathertightness?[52] In our view, it is the latter. A building element is something that is necessaryto the structural integrity or exterior aesthetics of the building or the health and safetyof occupiers and users of the building. The deck membrane here is only a part of theoverall storm water and weathertightness system necessary for the structural integrityof the building and the health and safety of owners and users. The building elementrepaired by the Body Corporate here is the entire storm water system which had goneon to cause weathertightness issues. First, that system cannot be said to be "contained"only in the appellants' units here as we outline at [27] above. And secondly andimportantly, the storm water system repairs, being crucial to the integrity and value ofthe entire development, benefit all owners. For these reasons s 138(4) does not applyhere.[53] And generally, on the view we take of the legislation, we find that anyperceived conflict between s 138(4) and ss 126 and 127 can be resolved asthe Select Committee envisaged, with the latter sections where they apply prevailingover s 138(4) which, if necessary, is to be read down. Hence there is no need for aspecific mechanism to apply and guide a body corporate when choosing among them.This avoids the risk that a body corporate will abuse its powers by requiring one unitowner to bear the cost of remedial work that substantially benefits others, and iteliminates the need for a judicially-developed mechanism to guide decision-making,such as that adopted by van Bohemen J in Cook.5251 Thomas Gibbons "Foreword" (paper presented to New Zealand Law Society Unit Titles —Density and Intensity Intensive Conference, November 2015) at 6.52 Cook, above n 28, at [97]–[100].[54] It follows that there is no ability for the Body Corporate in the circumstancesof the present case to recover costs from the respondents on the basis of s 138(4).We disagree therefore with the Judge's findings first, as we have noted, that ss 138(4)and 126 are alternative modes of recovery, and secondly, that:53There is therefore jurisdiction under s 138(4) to order that the first-floorapartment owners pay for the new joinery installed in their apartments.This error made no difference in the result, since the Judge awardedthe Body Corporate the window joinery sum in reliance on s 126.[55] The matters we have outlined above dispose of the s 138(4) aspects ofthis appeal.Recovery under s 126[56] We turn now to the Body Corporate's appeal arguments relating to s 126 ofthe UTA 2010.[57] The Body Corporate's position on this appeal relating to recovery under s 126was simply that, as liability should be found against the respondents under ss 127 or138(4) for the majority of the repair costs here, s 126 is no longer relevant other thanin relation to the podium and soffit works. The podium and soffit works involved theremoval of soffit linings around the first-floor deck area, repairing and paintingstructural steel under the decks, replacing the soffits and painting them at a total costof $115,129.09. The Body Corporate had sought from each of the respondents$24,488.05 for this work but this claim failed before the Judge.[58] The Judge's focus was on the need for the repairs to benefit the respondents"by a distinct and ascertainable amount" before their costs could be recovered from aparticular unit owner.54 The Judge found this was not so in the present case, bar thejoinery works as already noted.55 We consider that the test he applied, that repair workhad to benefit a unit "by a distinct and ascertainable amount", was incorrect.53 HC substantive judgment, above n 2, at [40].54 At [26].55 At [30].The presence of "distinct and ascertainable benefit" does not trigger the application ofs 126. Rather, s 126 provides for recovery where there is "substantial benefit" to orfor one or more units. The term "distinct and ascertainable benefit" refers to one oftwo bases for apportioning costs recoverable under s 126, that in s 126(2)(a).The alternative basis is set out in s 126(2)(b) and apportions the costs rateably betweenthose units that substantially benefit.[59] In the case of the podium and soffit works, the Judge did not discuss whetherthese works substantially benefitted some units more than others. He noted only thatthey were not necessitated by the replacement of the deck membrane. What is clearfrom the evidence, however, is that some of the podium and soffit works did assist inthe drainage and storm water disposal system. In its submissions on appeal,the Body Corporate suggested that the only owners affected by the podium andsoffit works were the ground-floor and first-floor owners. It noted the evidence beforethe High Court that the podium and soffit works did not affect the structural integrityof the rest of the building. Therefore, the Body Corporate submitted these repairs weresubstantially for the benefit of the ground-floor and first-floor units only and not otherowners in the building. Thus, the cost for these repairs meets the criteria in s 126(1)and is accordingly recoverable from those benefitted owners pursuant to s 126(2)(b).[60] As part of their response, the respondents opposed the categorisation of theoverall repairs to the building as a whole into balcony works and podium andsoffit works. They argue that all the works were necessary to repair the damage to thebalcony, the podium, and the drainage and storm water system, and they formed oneindivisible set of works for the collective benefit of all owners. The respondents pointto the evidence of Mr Earley, the Body Corporate's building consultant, whoacknowledged that he was directed to segment these matters and to use the terms"Deck Weathertightness Works" and "Podium Soffit Works" in his reporting. He saidthat he would not otherwise have used the label "Podium Soffit Works".[61] It is clear from the evidence that the podium and soffit works were required toreplace decaying soffits and to construct new drains and repair and rectify anunpainted, and no doubt rusting, metal beam structure supporting the concrete floorfor the decks. This also comprised the roof for the ground-floor units. The overallaesthetics and functionality of this part of the building, which included common areasover the footpath, was clear. No doubt, completion of the podium and soffit workswould have been needed to obtain Building Code consent for the new storm waterdrainage system required for the building.[62] We accept that the podium and soffit works were truly part of one repaircontract for all the required work to fix the major weathertightness issue inthe building. As such, we are satisfied the podium and soffit works were of substantialbenefit to all of the units in this development, including the tower block. Some of thisalso involved work carried out to the common property. The usual starting point forthis is that common property repair costs should be met on an ownership interest basis.We repeat that this work was part of the necessary repairs and renewal of the stormwater drainage system for the entire building, which had been under-designed andpoorly constructed, and needed upgrading to comply with the Building Code.[63] On this basis, we are of the view that the gateway provision in s 126(1)(c) isnot satisfied so far as the respondents are concerned. Section 126(1)(c) (in using"substantially more" language) deals with disproportionality of benefit that one orseveral unit owners have over others for the repairs that are undertaken. The podiumand soffit works did not benefit the respondents' units substantially more than itbenefitted others, nor were they benefitted by a distinct and ascertainable amount.Nor does it seem there was any real quantification evidence or other evidential basisadvanced by the Body Corporate before the High Court to assess any relativity here.[64] For these reasons, the Body Corporate's appeal relating to s 126 andthe podium and soffit works fails.[65] For completeness, in considering the s 126 issues, although the Body Corporateis not appealing the Judge's decision not to make any award against the respondentsfor balcony works under s 126 (other than for the new window joinery installed inthe first-floor apartments which we noted at [18] above), we consider it appropriatehere to note our agreement with his decision on this aspect. We do so, given theextensive submissions we have received from the respondents on this aspect whichwere not entirely necessary.[66] On this aspect, we are of the view that the Judge was correct to find thatthe balcony works were not substantially for the benefit of the respondents' first-floorunits and did not benefit those units substantially more than the remaining units in thebuilding.56 We say this given that the repairs fixed an important part of the storm watersystem for the entire building. We have already noted that we see the weathertightnessof the entire building, including the podium and soffit works, as being interlinked andindivisible.The High Court costs decisionThe parties' costs claims[67] Before the High Court:(a) The Body Corporate claimed partial success and sought costs of$31,220, comprising scale costs on a 2B basis with a 50 per centreduction. It also sought disbursements of $65,264.39.57(b) The respondents acknowledged the Body Corporate had achieved somesuccess but claimed they were entitled to costs becausethe Body Corporate failed to accept Calderbank settlement offers theyhad made without reasonable justification. They sought increased scalecosts of $83,863.38 (comprising 2B scale costs increased by 33 percent), and $220 filing fees.The Calderbank offers[68] Turning to the Calderbank offers, on 18 December 2015, each ofthe respondents offered to pay $100,000 to settle the claim. However, the offerincluded various obligations on the Body Corporate. The Body Corporate rejectedthis offer on 21 December 2015. It countered with an offer that the respondents acceptliability of $170,000 each. This was not accepted.56 At [30].57 These were reduced to reflect the Body Corporate's partial success.[69] The Judge held that this was not an offer under r 14.11(3) or (4) ofthe High Court Rules 2016 because a Calderbank offer requires an offer be madewithout significant conditional terms.58[70] On 10 July 2017, the Body Corporate sent a letter stating it would accept$650,000 "in full and final settlement of it claim". No mention was made in that letterof whether the settlement would cover the disputed issue of where the floor boundaryfor the units actually lay. That offer was to lapse on 14 July 2017. Counsel forthe Body Corporate asked for an update on 4 August 2017. Under a subject line"without prejudice save as to costs", counsel for the respondents replied by email on7 August 2017 with a counter offer:My clients are prepared to each pay $200,000 including GST in full andfinal settlement of all issues. They will not be bound until a written agreementis signed.[71] On 9 August 2017, counsel for the Body Corporate responded with anothercounteroffer:1. We refer to your clients' offer dated 7 August 2017 of $400,000 in fulland final settlement.2. Your clients' offer roughly matches the cost of the repairs as presentlyclaimed. However, considerable interest and costs have accrued overthe years. Regrettably, those costs place your clients' offer well belowthe Body Corporate's bottom line.3. We are instructed the lowest figure that the Body Corporate willaccept to avoid any further action being taken is $531,000 includingGST in full and final settlement of the claim for recovery of repaircosts, and on the basis that your clients will not oppose the orderssought in relation to unit boundaries. [72] The respondents' reply to this was given on 16 August 2017. It said they wouldsettle on the basis of $450,000, together with their consent to the unit boundaries beingfixed at the concrete slab. This was with the proviso, however, that futureapportionment of costs for repairs to the new membrane were to be allocated in thirdsto the "Tower", the first-floor units and the ground-floor units.58 HC costs judgment, above n 3, at [31]–[32].[73] The Body Corporate replied on 21 August 2017 rejecting this offer.Essentially, the Body Corporate simply repeated its 9 August 2017 counter-offer.The Judge's costs decision[74] As to the Calderbank offer issues, the Judge found that the email from counselfor the respondents on 7 August 2017 did constitute a Calderbank offer as it wasspecific in amount and in "full and final settlement".59 Although brief, he consideredit was implicit that the offer would be on the same terms and conditions asthe Body Corporate's previous offer, except for a different amount.60 He also notedthat the Body Corporate perceived it as an offer to settle.61 The Judge consideredtherefore the respondents were entitled to scale costs on a 2B basis for steps taken after7 August 2017.[75] The Judge acknowledged that in the 7 August 2017 email the respondents saidthey "will not be bound until a written settlement agreement is signed". However, hefound this to be akin to making an offer conditional on the agreement being finalisedin writing. It was not a significant condition and did not indicate an intention tonegotiate further terms.62[76] The Judge found that the total 7 August 2017 offer of $400,000 exceeded theeventual judgment sum and was more beneficial to the Body Corporate thanthe judgment, even taking into account issues of non-monetary success. Therefore, heawarded the respondents 2B scale costs from 7 August 2017 and disbursementsincurred after that date.63[77] As to the increase on those scale costs sought by the respondents, the Judgeconsidered that the Body Corporate's conduct in this case was not unreasonable. Thus,he did not award the increase of 33 per cent they sought.6459 At [34].60 At [35].61 At [36].62 At [38].63 At [40]–[41].64 At [46]–[50].[78] For costs up to 7 August 2017, in light of the Body Corporate's partial success,the Judge awarded it the 2B scale costs sought with a 50 per cent reduction and limitedto steps taken in the proceeding until 7 August 2017. Adjusted disbursements werealso awarded to the Body Corporate, also limited to amounts incurred before7 August 2017.65Appeal against the costs decision[79] The Body Corporate appeals the costs decision on the basis that it saysthe respondents' email of 7 August 2017 was not a Calderbank offer and, therefore,should not have warranted costs being awarded to the respondents.[80] To be effective for costs purposes pursuant to rule 14.10 of the High CourtRules, the emailed offer needs to be:(a) clearly and unambiguously stated;66(b) capable of contractual acceptance; and(c) more beneficial (or close in benefit) to the other party than the judgmentactually obtained.67[81] Here, the Body Corporate submits that the requirement the offer be capable ofacceptance and be more beneficial to the offeree than the outcome achieved at trialwere not met.[82] In response, the respondents argue the 7 August 2017 email was a Calderbankoffer and the Judge correctly applied the principles in rr 14.10 and 14.11.Was the offer capable of acceptance and clearly stated?[83] The Body Corporate contends there was no certainty as to what the offercovered. It argues that a blanket statement that the offer settles "all issues" cannot65 At [58].66 Simpson v Walker HC Auckland CIV-2008-404-7381, 10 February 2011 at [27(a)].67 High Court Rules 2016, rr 14.11(3) and (4).encompass the spectrum of issues in the seven pleaded causes of action, whichincluded declaratory relief and questions of costs. The Body Corporate suggests itcould not act on this offer without leaving most issues in the claim unresolved.Further, the respondents' "offer" specifically included what was said to be a caveatthat the respondents would not be bound until a written agreement was signed.[84] In his costs decision, the Judge found that while the email was brief, it wasimplicitly on the same terms and conditions as the Body Corporate's previous offer,except for a different amount. The Body Corporate submits this was in error as thereis nothing in the email to imply reference back to its earlier settlement proposal.That offer had expired almost a month prior and it also referred specifically to theboundary dispute, which was not referenced in the email.[85] The Judge said, too, that "[p]ractically, it will almost always be the case thatparties subsequently enter into a formal written settlement agreement".68The Body Corporate went on to argue that the dispute here covered serious issues andthe terms of any settlement were not just a formality.[86] The Body Corporate contends that if a party wishes to avail itself of the rulesrelating to a Calderbank offer, it must take due care to put forward an offer capable ofacceptance. Had it accepted the offer, the Body Corporate says there would have beenno certainty as to what was accepted. This was particularly so with regard to thedeclaration as to location of the unit boundaries sought in the proceeding.[87] In response, the respondents suggest that the ultimate issue is always whetherthe recipient of an offer can understand what is offered and what will be settled by theoffer. They argue that the response from the Body Corporate's solicitors on9 August 2017 demonstrates that the Body Corporate was not confused and felt ableto make a counter offer in full and final settlement of "the claim for recovery of repaircosts, and on the basis that your clients will not oppose the orders sought in relationto unit boundaries". They say this reply demonstrates that the Body Corporateappreciated that the respondent's offer was in respect of the monetary claim only, and68 HC costs judgment, above n 3, at [38].the parties were agreed that the Body Corporate would continue with its first andsecond causes of action (regarding the unit boundaries).[88] The respondents further submit that if the offer is not considered to be aCalderbank offer, it could still be taken into account under r 14.7(f)(v).[89] On these aspects and regarding the need for an offer to be clearly stated,the authors of McGechan on Procedure confirm:69The aim is to remove any scope for disagreement as to the terms of the offer. The offer should be clearly and unambiguously stated. If settlementoptions are offered, they should be unequivocally spelt out. The offer shouldstate whether or not it includes costs. [90] Offers of this type must be considered too in the context of othercommunications at the time between the parties. The Calderbank offer cost rules arebased on the concept that the offeree should have reasonably accepted the offer.Therefore, it is of relevance what the parties actually understood to be the case.[91] It appears to us that it was understood between the parties here that thesettlement offers related only to the Body Corporate's monetary claims. It is clearfrom the Body Corporate's communications at the time that the offers included costs.This is also evident from the higher sums offered than those that were discussed inDecember 2015.[92] Therefore, we find that the respondents' 7 August 2017 offer was sufficientlyclear and unambiguous to be taken into account by the Court under r 14.11. It was afirm offer to settle and we reject the Body Corporate's suggestion that it was merely"an invitation to treat".[93] We also consider the offer was capable of being accepted bythe Body Corporate. We agree with the Judge that the reference to a written agreementdid not indicate an intention on the part of the respondents to negotiate further terms.It merely meant that the agreement would be recorded and finalised in writing. As in69 Andrew Beck and others McGechan on Procedure (online looseleaf ed, Thomson Reuters)at [HR14.10.02(1)].Bushline Trustees Ltd v ANZ Bank New Zealand Ltd, it is highly doubtful that the offerwas rejected here because of this requirement.70Was the offer more beneficial than the outcome?[94] The Body Corporate contends that by proceeding to a hearing beforethe High Court, while it did not obtain the monetary awards it sought, it extinguishedthe respondents' persistent denial that they owned the decks, a significant issue.[95] This Court made clear in Weaver v Auckland Council, however, that a broadapproach to the concept of success is required when assessing where costs should fall,and it held that "success on more limited terms is still success".71 The High Court hasnoted too that there is inherent difficulty in comparing declaratory relief with monetaryoutcomes.72[96] The Body Corporate argues that in order for it to have accepted the offer at thetime it would have needed to accept that the decks were not owned by the respondents.As it could not accept that conclusion, it says it pushed on and was successful in thatrespect. It says that it is not proper to award costs to the respondents given thatthe Body Corporate went on to win that fundamental point which it could not let sit.But we disagree.[97] We are satisfied that the Body Corporate did appreciate that the respondents'counter offer of 7 August 2017 was in respect of the monetary claim only and theparties were agreed that the Body Corporate would continue with its first and secondcauses of action which required litigation to clarify the location of the unit boundaries.This was for the benefit of all owners in the development. It was the case irrespectiveof the dispute with the respondents over repair costs. We are satisfied that the costs ofthat exercise should be properly absorbed by the Body Corporate.70 Bushline Trustees Ltd v ANZ Bank New Zealand Ltd [2018] NZHC 454 at [28].71 Weaver v Auckland Council [2017] NZCA 330 at [26].72 Body Corporate 396711 v Sentinel Management Ltd [2012] NZHC 2556 at [20].[98] We conclude, therefore, that the benefit the Body Corporate would havereceived here after accepting the 7 August 2017 offer from the respondents would haveclearly been greater than that which they received from the Judge's judgment.[99] It follows that the Judge did not err in determining the issue of costs betweenthe parties. The Body Corporate's costs appeal therefore fails.Conclusion[100] While we have not agreed with the Judge on certain aspects of his reasoning,particularly the relationship between s 138(4) and 126 of the UTA 2010, we agree first,with his analysis of the expert evidence here and his end conclusion as to the amountthe Body Corporate is entitled to recover in its substantive claim from the respondents,and secondly, as to his proper allocation of costs on this proceeding. It follows thatwe uphold the final decisions that the Judge reached on both the substantive and costsdecisions.Result[101] The appeals are dismissed.[102] The appellant must pay the respondents one set of costs for a standard appealon a band A basis and usual disbursements.Solicitors:MinterEllisonRuddWatts, Auckland for AppellantLyon O'Neale Arnold, Tauranga for Respondents