CHIEM v FORDYCE COMPANY LIMITED [2022] NZHC 1978
The plaintiff acted as an on‑site representative but did not assume the role of project manager nor possess special skill; qualified consultants were engaged and led the technical work; accordingly no duty of care, as alleged, was established and, in any event, material breach and causation were not proved, so both...
Source-derived case information.
- Citation
- [2022] NZHC 1978
- Parties
- Plaintiff: Bon Cheak Chiem; Defendant: Fordyce Company Limited
- Court
- High Court
- Jurisdiction
- New Zealand
- Judgment Date
- 11 August 2022
- Procedural Posture
- Civil Negligence and Contractual Dispute / Judgment (trial Concluded)
- Outcome
- Plaintiff's claim dismissed; Defendant's counterclaim dismissed
- Legal Topics
- Duty of Care, Assumption of Responsibility, Project Management Liability, Resource Consent Compliance, Damages, Abatement Notice, Shareholder Dispute
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Bon Cheak Chiem
Plaintiff
Fordyce Company Limited
Defendant
Procedural Posture
Civil Negligence and Contractual Dispute / Judgment (trial Concluded)
Legal Issues
- 1 Whether plaintiff had an enforceable agreement for payment of $800/week
- 2 Whether plaintiff assumed role of project manager thereby owing a duty of care to defendant
- 3 Whether, if a duty existed, plaintiff breached it by permitting or directing deficient earthworks between 24 Oct 2017 and 5 Dec 2017
Ratio Decidendi
The plaintiff acted as an on‑site representative but did not assume the role of project manager nor possess special skill; qualified consultants were engaged and led the technical work; accordingly no duty of care, as alleged, was established and, in any event, material breach and causation were not proved, so both the claim and counterclaim fail.
Court Disposition
Plaintiff's claim dismissed; Defendant's counterclaim dismissed
Orders
- Plaintiff's claim dismissed
- Defendant's counterclaim dismissed
Full Case Text
Judgment text and source record
1 paragraphs
CHIEM v FORDYCE COMPANY LIMITED [2022] NZHC 1978 [11 August 2022]IN THE HIGH COURT OF NEW ZEALANDAUCKLAND REGISTRYI TE KŌTI MATUA O AOTEAROATĀMAKI MAKAURAU ROHECIV-2018-404-754[2022] NZHC 1978BETWEEN BON CHEAK CHIEMPlaintiffAND FORDYCE COMPANY LIMITEDDefendantHearing: 2 – 6, 9, 10 and 11 August 2021Further submissions and documents received 7, 18, and 28 Julyand 3 August 2022Appearances: R J Latton and K B Arthur for PlaintiffD S McGill and D L Bennington for DefendantJudgment: 11 August 2022JUDGMENT OF PETERS JThis judgment was delivered by Justice Peters on 11 August 2022 at 10.30 ampursuant to r 11.5 of the High Court RulesRegistrar/Deputy RegistrarDate: ...................................Solicitors: Graham & Co, AucklandDuncan Cotterill, AucklandCounsel: R J Latton, AucklandK B Arthur, AucklandTable of ContentsPara NoBackground .......................................................................................................... [8]Resource consent [18]Brooklands Ltd and Deane Consultancy Ltd [19]Abatement notice [23]Shareholder meeting 21 February 2017 [26]Mr Blomfield [29]Parakai Subdivision Ltd [30]ENGEO [33]Mr Chiu and Mr Chiem [35]Lifting of abatement notice [39]Airey, Coffey, Shepherd and Mr Richards [41]Events after 5 December 2017 [49]Evidence ............................................................................................................. [50]Claim .................................................................................................................. [53]Counterclaim ..................................................................................................... [59]Duty of care [60]Role of a project manager [62]Assumption of responsibility [63]Discussion [70]Breach [81]Particular (a) [95]Particular (b) [96]Particular (c) [98]Particulars (d), (e) and (f) [99]Particular (g) [100]Particular (h) [101]"Allowed or directed" [103]Conclusion on breach [105]Damages ........................................................................................................... [108]Result ................................................................................................................ [113]Costs ................................................................................................................. [115]Post-script ........................................................................................................ [116][1] This proceeding began life as a claim by the plaintiff, Mr Chiem, to recover asubstantial sum that he alleged was due to him from the defendant ("FCL"). However,the sum Mr Chiem now claims is modest, being $38,771.49 for remuneration hecontends is due for services rendered between 2 November 2016 and 20 November2017.[2] FCL denies liability to Mr Chiem for this or any other sum.[3] The more substantial claim is by FCL against Mr Chiem by way ofcounterclaim. FCL contends that Mr Chiem is liable to it in negligence for damagesof $2,792,733.[4] FCL alleges that between 2 November 2016 and 5 December 2017 Mr Chiemowed it a duty of care to ensure that the development undertaken on what is referredto as the Stage 1 land was carried out in a manner which complied with the applicableresource consent(s), and in a good and workmanlike manner. FCL alleges thatMr Chiem breached his duty, in that earthworks undertaken under his (alleged)direction on the Stage 1 land between 24 October 2017 and 5 December 2017, wereconducted to a poor standard, and with a lack of quality control in respect of "fill"materials placed on the site. The sum claimed by way of damages is said to be that ofremediating the site, plus costs said to be required to ready the site for works, such asinsurance, fencing, health and safety measures, and so on.[5] Mr Chiem denies both liability and quantum.[6] There is an obvious irony to the case, in that Mr Chiem alleges that FCLengaged him to manage the development for $800 per week but denies he assumed therole of project manager, whereas FCL denies it agreed to pay Mr Chiem but asserts heundertook to project manage the development without payment.[7] For reasons set out below, I am not satisfied either the claim or counterclaim isestablished.Background[8] At all material times prior to this dispute, the land in issue was farmland. InAugust 2015, a developer obtained resource consent to develop and subdivide the landfor residential purposes. The total land area involved was approximately 10 ha. It wascontemplated, and indeed this is what transpired, that the development would beconducted in two stages.[9] In early 2016, a local real estate agent approached Mr Chiem to see if he hadany interest in purchasing the land. Mr Chiem was known to the agent as he hadpreviously owned a café in the vicinity. Mr Chiem expressed interest in the proposal.[10] The chronology is not entirely clear on the evidence but, by mid-2016,Mr Chiem had contacted Chi Wai Wong, whom Mr Chiem had known for many years,to see if he had any interest in investing in the project. Mr Wong was interested andintroduced two other investors, Hung-Chi Chiu and Tung Ming Liu. In due course allbecame shareholders in FCL. After discussions, they agreed that they would purchasethe land marked for Stage 1, which comprised approximately 5.5438 ha.[11] By this time, the developer ("FRTL") had entered into agreements for the saleand purchase of both the Stage 1 and Stage 2 land with Fordyce Partnership Ltd("FPL"). FPL was a company wholly owned and controlled by Mr Chiem,incorporated especially for this acquisition. FPL then entered into an agreement tosell the Stage 1 land to Mr Chiu and Mr Wong or nominee. Mr Chiu and Mr Wongsubsequently nominated FCL as the purchaser.[12] The agreements in respect of the Stage 1 land settled on 1 November 2016, thatis from FRTL to FPL, and from FPL to FCL.[13] FPL purchased the Stage 1 land for $4,000,000 and sold it to FCL for$5,229,000. Mr Chiu's evidence (and Mr Liu's was to similar effect) was that he didnot know or understand that Mr Chiem was beneficially interested in FPL and that heunderstood from Mr Chiem that he was acting purely as an agent for FPL. Mr Chiuwas unhappy at Mr Chiem's "mark-up" on the purchase price when he learned of thetrue position even though, as Mr Latton for Mr Chiem submits, the information wasavailable to FCL's solicitors from the Companies Office.[14] As at settlement of FCL's purchase, Mr Chiu (or, rather, the trustees of the ChiuFamily Trust) and Mr Wong were FCL's sole shareholders. The shareholding wasvaried shortly thereafter, so that the shares in FCL came to be held as follows: 50 percent by the trustees of the Chiu Family Trust ("trustees"); Mr Wong as to 25 per cent;Mr Chiem as to 20 per cent; and Mr Liu as to five per cent. These shareholdingsreflected the parties' respective contributions to the purchase price, Mr Chiem's beingmet by FPL's profit on the sale.[15] At all material times, Mr Chiu and Mr Wong were FCL's directors.[16] None of the shareholders had experience in subdivisions. Mr Chiu had, andhas, a substantial business supplying items to the defence force; Mr Wong's businessis in supplying sheet metal and he has interests in food manufacturing and restaurants;Mr Chiem has owned and operated cafés and bakeries; and Mr Liu has or had alandscaping and construction business.[17] I go on now to set out the further background information required to put thedispute in context. Fortunately, it is unnecessary to determine many of the factualdisputes that developed between the witnesses. As appears above there are twoprincipal issues. The first is whether FCL engaged Mr Chiem at $800 per week. Thesecond is whether, from 2 November 2016, Mr Chiem owed a duty of care to FCLand, if so, whether he breached it between 24 October 2017 and 5 December 2017causing the loss claimed.Resource consent[18] The resource consent for the development permitted the subdivision of theStage 1 land into 67 lots and, amongst other things, included conditions governingearthworks on the site. These required that 68,000 m3 of "clean fill" be imported tothe site, with this fill to meet particular specifications as to its composition and lack ofcontaminants. The purpose of importing the fill was to "lift" the site so that it wouldbe less susceptible to flooding or inundation.Brooklands Ltd and Deane Consultancy Ltd[19] In early-November 2016, FCL engaged an earthworks contractor, BrooklandsLtd ("Brooklands"). There is no dispute Mr Chiem introduced Brooklands to FCL.Brooklands subsequently introduced Deane Consultancy Ltd ("DCL") to providegeotechnical engineering services.[20] By the end of January 2017, and quite possibly before, FCL had engaged TerraGroup Ltd ("Terra") as "engineer to the contract". The evidence at trial was that thistitle generally signifies appointment as "project manager". FCL did not engage Terraunder a formal written contract, although Terra did supply one. Nevertheless, Terra,principally through its director Mr Mark Kearney, rendered services to FCL, for whichit was paid.[21] Mr Kearney subsequently advised FCL to terminate Brooklands' contract forseveral reasons, including that Terra was not satisfied as to Brooklands' quality controlof the earthworks. With FCL's agreement, Terra effected the termination on27 January 2017. DCL, which had worked closely with Brooklands, then withdrewfrom the project.[22] Brooklands disputed the termination, said it was owed a substantial sum, andultimately served a statutory demand on FCL. It is clear, and FCL put weight on thepoint, that Mr Chiem undertook to the other shareholders that he personally would beresponsible for resolving the dispute with Brooklands, and at his sole expense. ThisMr Chiem did, whilst keeping the other shareholders informed of progress.Brooklands withdrew its statutory demand in late-February 2017 and that appears tohave been the end of the matter.Abatement notice[23] On 2 February 2017, Auckland Council served an abatement notice on Mr Chiuin his capacity as a director of FCL. This followed an inspection of the site by theCouncil on 1 February 2017. With some exceptions, the notice required the cessationof all works on the site for what were said to be contraventions of conditions of theresource consent pertaining to earthworks and fill.[24] Not surprisingly the abatement notice was a matter of concern. On receipt ofthe notice, Mr Chiu sought advice from Mr Sam Hsu, a family friend and anexperienced project manager and developer. Mr Hsu gave evidence at trial to the effectthat he visited the site, reviewed the existing documents, and then reported to theshareholders, Mr Chiem excluded, in writing and at a meeting on 16 February 2017.Mr Hsu found that work was continuing on the site in breach of the abatement notice(this was a matter of dispute at trial, as the notice permitted the continuation of somework). Mr Hsu also considered there were deficiencies in the manner in which the sitehad been established. For instance, there were no silt or traffic management controlsin place; no "clean fill" logs were being kept; and there was no engineer "supervisionor sign off". Mr Hsu also considered there were deficiencies in the contractualdocuments and in respect of the fill that was on-site and its origin.[25] Mr Hsu recommended to the shareholders (and directors of course in the caseof Mr Chiu and Mr Wong) that work stop immediately pending engagement of asuitable group of professionals.Shareholder meeting 21 February 2017[26] All the shareholders met on 21 February 2017, including Mr Chiem. Whatpurported to be the translated, but not the original, minutes of this meeting wereincluded in the common bundle. However, when the signed original was madeavailable and translated, its contents were different in important respects to that in thebundle. It is fair to record that the differences were a surprise to counsel.[27] By way of example, the document in the bundle included two agenda items,and recorded that Mr Chiem was responsible for resolving matters with Brooklands(not in dispute) and the abatement notice. The translation of the original includes fouragenda items. The third of these evidences a general acceptance that steps had to betaken to bring the development into compliance with the resource consent and anagreement that Mr Chiem would ask "Mark" — Mark Kearney of Terra — "to takecharge" and would ask "project manager to be responsible for loan and engineering".At the time, the shareholders were looking to arrange finance to fund the ongoing workwhich would inevitably require detailed information about the project and anticipatedcosts.[28] In cross-examination, Mr Chiu accepted that the shareholders had resolved atthis meeting to engage Mr Kearney as project manager, and to ask him to take charge.This is an important point because it is part of FCL's case that Mr Chiem undertookresponsibility for resolving the abatement notice. Mr Chiem accepted in cross-examination that he did undertake to deal with the notice but I am not satisfied that isconsistent with the minutes of the meeting. There is also evidence in the commonbundle that at least one potential lender (Strata) was told to liaise with Mr Kearney toobtain information. Unfortunately, this new translation of the minutes becameavailable after Mr Liu had given evidence and, as I understood it, it was Mr Liu whodrafted the document appearing in the common bundle.Mr Blomfield[29] It appears that Mr Chiem had also engaged or purported to engage anotherearthworks contractor, Mr Daniel Blomfield, to undertake works on the site. This wasin or about January 2017. Mr Hsu discovered that Mr Blomfield was working on thesite after the abatement notice was served, although it is not clear whether he wasworking in breach of the notice or attending to permissible works. In any event, MrBlomfield was instructed to stop work on 16 February 2017, and subsequentlytrespassed from the site.Parakai Subdivision Ltd[30] After termination of Brooklands' contract, Mr Chiem incorporated ParakaiSubdivision Ltd ("Parakai"). As I understood his evidence, he did so at the request ofthe shareholders, so that there was an intermediate entity between FCL on the onehand and contractors on the other. The intention was that contractors would invoiceParakai, FCL would put Parakai in funds, and Parakai would pay the contractors' fee.[31] FCL relied on an invoice from Parakai to FCL on 21 April 2017 for $200,000for "Subdivision Management as agreed. Filling on site ...". Mr McGill, for FCL,questioned Mr Chiem on whether this invoice was in respect of fees Mr Chiem wasclaiming personally, that is for services he had rendered. I understood Mr Chiem todeny that it was. I note also that the invoice was not paid.[32] This invoice and another from Parakai were also treated as evidence thatearthworks were being conducted on-site during the period when the abatement noticewas in effect. Of course, earthworks in breach of the abatement notice should not havebeen conducted at the time. However, I am not satisfied that this adds particularly toFCL's case against Mr Chiem.ENGEO[33] In March 2017, FCL engaged ENGEO, a firm of geotechnical engineers, toundertake a retrospective review of the placement of fill on the site. Mr David Brodieof ENGEO had the day-to-day involvement. Mr Brodie was already familiar with thesite as he had provided geotechnical advice to other interested parties.[34] ENGEO found that fill imported to the site was not geotechnically suitable anddid not comply with the cleanfill requirements of the resource consent.Mr Chiu and Mr Chiem[35] By April 2017, Mr Chiu and Mr Chiem's relationship had deteriorated. OnMr Chiu's evidence this was because of the issue of the abatement notice, the disputewith Brooklands, and because he considered Mr Chiem had misled him at the time ofthe purchase. This led to an agreement, contained in a Deed of Settlement of 14 May2017, between Mr Chiu, the trustees, and Mr Chiem. There was dispute at trial abouthow the deed came to be executed but that is a matter I need not resolve. Indeed, thedeed is the subject matter of separate proceedings. Suffice to say that the deedcomprised an option A and an option B, with either one or the other to be implementedat a time of Mr Chiu's choosing. Option A, if implemented, would have seen Mr Chiuor the trustees acquiring the Stage 2 land and exiting FCL. Option B provided forMr Chiem to exit FCL. As matters developed, option B was implemented inNovember 2017. That is why Mr Chiem ceased to be involved with the developmentafter 5 December 2017.[36] It was a term of the deed that, post-execution, Mr Chiem would refrain fromcontinuing or beginning what was referred to as new work or the execution of anycontracts in relation to either the Stage 1 or Stage 2 land without first obtainingMr Chiu's written consent.[37] On the face of it, and again this may be the subject of future proceedings,Mr Chiem did not comply with this provision. Works on-site did proceed once theabatement notice was lifted and Mr Chiem did execute contracts, specifically thoseengaging professionals. What Mr Chiu knew of these matters is unclear. However,on the face of the evidence, after the deed was executed, and although he remained adirector of FCL, Mr Chiu distanced himself from FCL's affairs. This is consistent withMr Chiem's evidence that, after the deed was executed, he considered Mr Chiu hadleft the venture. In fact, in May 2017, Mr Chiem incorporated a new company, NBM2017 Construction Ltd, that he expected would come to hold the trustees' shareholdingin FCL under option A. Mr Chiem also entered into arrangements with new businesspartners, Yan Sun and Sing Pang, and their names begin to appear in emailcorrespondence from this time on.[38] Lastly on this point, I note that Mr Wong continued as a director of FCL and itis common ground that Mr Wong knew that works were continuing on-site. To theextent it is material, Mr Wong's knowledge would fall to be attributed to FCL.Lifting of abatement notice[39] After discussions and attendances with Terra and ENGEO, in April 2017 theCouncil advised that it would permit fill that had already been imported to the site toremain, provided that suitable management controls were put in place.[40] In addition, by late September 2017, the Council were satisfied that it shouldcancel the abatement notice. This meant that earthworks could resume in theforthcoming earthworks season, commencing on 1 October 2017.Airey, Coffey, Shepherd and Mr Richards[41] At about the same time, there was a change in the professionals engaged on theproject.[42] First, by mid-September 2017, Airey Consultants Ltd ("Airey") had replacedTerra. Mr Chiem executed Airey's terms of engagement on behalf of FCL. That Aireywas engaged, and the nature of the services it was to provide, is important toMr Chiem's defence to FCL's claim that he assumed responsibility for the projectmanagement of the development. Airey's terms of engagement anticipated that itwould provide many of the services usually expected of a project manager. This wasconfirmed in the evidence of Mr Hamish Anderson, an expert witness called by FCLand which I discuss below. For instance, under its terms of engagement, Airey was toliaise with the geotechnical engineer for fill monitoring and settlement controls;prepare tender documents; arrange for the lodging of health and safety and trafficmanagement plans with the Council; monitor construction works to ensure compliancewith Council standards; certify progress payments to contractors; provide siteinstructions to contractors; and numerous other tasks connected with compliance withthe conditions of the resource consent. The Airey representative with the day-to-dayinvolvement in the project was Mr Michael Lee.[43] Secondly, from 20 October 2017, Coffey Geotechnics Ltd ("Coffey") replacedENGEO as the geotechnical engineers. The person principally responsible for theassignment at Coffey was Mr Joshua Fisher.[44] Thirdly, Mr Chiem engaged Shepherd Consultants Ltd ("Shepherd") as FCL'searthworks contractor. Shepherd had previously undertaken earthworks on the site,essentially to remove "fill" that Mr Blomfield was said to have off-loaded on the site,apparently as a retaliatory measure for non-payment of invoices. Shepherd was theprincipal earthworks contractor on-site during the period in which FCL allegesMr Chiem breached the duty of care he is said to have owed.[45] No formal written agreement was entered into between FCL and Shepherd.Although Mr Lee was asked to prepare this, he did not forward a draft for executionuntil 30 November 2017, shortly before works ceased.[46] Shepherd was Mr Tom Shepherd's company, and Mr Chiem's evidence wasthat Shepherd had three or four employees on-site from the time at which earthworksresumed after 24 October 2017. I record here that Mr Chiem himself acknowledgedassisting Mr Shepherd by driving a "compactor" on two days when several ofMr Shepherd's staff were unwell. Again, FCL set considerable store by this but I donot consider it adds much to FCL's case.[47] It was another notable feature of the case that Mr Shepherd does notcommunicate by email. Accordingly, instructions to Mr Shepherd needed to berelayed either on-site or by telephone or to Mr Chiem for him to provide toMr Shepherd. Although some scepticism was expressed at trial as to the suitability ofMr Shepherd and his staff for this project, Mr Lee did approve progress payments toShepherd totalling more than $600,000.[48] Fourthly, Mr Chiem acknowledged in evidence that he had also engagedanother earthworks contractor, a Mr Richards, and that Mr Richards also undertooksome earthworks after 24 October 2017. Mr Richards did not feature to any greatextent in the contemporaneous documents or in the evidence given at trial.Events after 5 December 2017[49] As I have said, works came to a halt on 5 December 2017 because option Bhad been implemented. Subsequently, FCL engaged Mr Hsu to investigate theearthworks on-site between 24 October 2017 and 5 December 2017. At Mr Hsu'srequest, Coffey wrote a letter dated 11 May 2018 setting out its observations of whathad occurred on-site in this period and the works it recommended to remediate theexisting fill on-site. Coffey's letter in turn formed the basis for a request by FCL fortenders to undertake the works they recommended. The sum FCL claims by way ofdamages from Mr Chiem derives in part from a tender submitted for those works byYakka Contracting Ltd ("Yakka") in September 2018.Evidence[50] Each of the shareholders gave evidence as did Mr Hsu, Mr Brodie of ENGEO,Mr Lee of Airey; Mr Peter Bosselmann of Coffey; and Mr Anderson, an expert.[51] There are two points to note regarding the evidence. First, Much of the vivavoce evidence from the shareholders was translated. It was apparent throughout thatoften the shareholder concerned did not grasp what was being asked of him. Theanswers were not always apposite or pertinent to the question and, in some cases, wereunintelligible despite the best efforts of all concerned. Moreover, there were manypoints of detail which witnesses were unable to recall. Given these matters, I haveplaced considerable reliance on the contemporaneous documents in the commonbundle.[52] Secondly, a notable omission from the witness list was Mr Fisher of Coffey.By the time of trial, Mr Fisher had left Coffey. I have no doubt that Mr Fisher couldhave given relevant evidence to many of the issues in dispute. However, his absencemeant that evidence was not available, and also that he could not be cross-examined.Claim[53] Mr Chiem's claim can be dealt with relatively briefly.[54] Mr Chiem's pleading is that he was retained to manage the developmentpursuant to an oral agreement with Mr Chiu, made on behalf of FCL but prior to itsincorporation, on 15 October 2016.[55] Mr Chiem's evidence as to the nature of this agreement and how it came aboutwas different to his pleading. It was that the shareholders agreed at the outset that oneof them needed to be on-site dealing with day-to-day issues, a "client contact" orrepresentative for contractors and professional consultants that the shareholdersengaged, and then reporting back to shareholders. Mr Chiem's evidence was that heagreed to be that person, and that "we all agreed that I would be paid $800 per weekfor that role".[56] I am satisfied that Mr Chiem did have that role but I am not satisfied there wasany agreement, whether made on 15 October 2016 or any other date (in evidenceMr Chiem suggested several other possibilities), pursuant to which FCL would payhim $800 per week. Mr Chiu and Mr Liu were adamant there was no such agreement.Mr Wong's evidence was that he suggested to Mr Chiem that he could be paid $800per week to oversee the development, but no agreement to do so was reached. Rather,Mr Wong's evidence was that, in December 2016, he asked Mr Chiu to have FCL buyMr Chiem a vehicle so that Mr Chiem could visit the site. He also asked thatMr Chiem be given some cash, totalling $5,000, to cover expenses. The vehicle waspurchased in early December 2016, with funds provided by FCL. Likewise the $5,000,which was paid in two instalments in December 2016.[57] In addition to the other shareholders' denials of any agreement, there is noevidence of any contemporaneous demand by Mr Chiem for payment. This could beexpected if the agreement Mr Chiem alleges had been made.[58] On the evidence before me, Mr Chiem has not proved the agreement on whichhe relies and I dismiss his claim accordingly.Counterclaim[59] I turn now to FCL's counterclaim. This requires that FCL establish thatMr Chiem owed FCL a duty of care, that he breached that duty, and caused loss toFCL in the sum claimed. Each element of the cause of action is denied.Duty of care[60] The relevant parts of FCL's pleading as to the duty is as follows:17 Between 2 November 2016 and 5 December 2017, the plaintiffassumed the role of project manager for the development of FordyceRoad Stage 1.18 In assuming the role of project manager, the plaintiff owed thedefendant a duty of care to ensure that the development undertaken onFordyce Road Stage 1 was carried out in compliance with theResource Consent applicable to the property, and in a good andworkmanlike manner.[61] Accordingly, it is necessary for FCL first to establish Mr Chiem assumed therole of project manager between those dates and, secondly, that in doing so he owedFCL the duty of care alleged. I have construed that duty as one requiring Mr Chiemto exercise the skill and care of a reasonable, prudent project manager, providingservices with the intention that the development of the Stage 1 land would be carriedout in compliance with the resource consent, and in a good and workmanlike manner.Role of a project manager[62] Mr Anderson gave evidence of the expected role and responsibilities of areasonable and prudent project manager on a development site requiring earthworks.Mr Anderson's evidence was that the project manager's role is to oversee the planningand delivery of the specified project on time and within budget. The project managershould have appropriate qualifications, experience, and organisational,communication, and document management skills. The project manager should alsoensure suitably qualified experts are engaged. For a project of the nature at issue inthis case, Mr Anderson would have expected to see a "development feasibility model"containing revenue and cost assumptions, and a forecast of profitability; adevelopment programme and budget; and regular reporting to the principal (FCL).The project manager should be familiar with the resource consent and have theexpertise required to assemble a tender package, including a form of contractappropriate to the task at hand. The project manager is also responsible for holdingand minuting regular site meetings and maintaining appropriate records.Assumption of responsibility[63] Mr McGill referred me to the following passage in Rolls-Royce New ZealandLtd v Carter Holt Harvey Ltd in the context of FCL's claim that Mr Chiem owed it aduty of care as a result of an assumption of responsibility:1[99] Assumption of responsibility for a statement or a task does not usuallyentail a voluntary assumption of legal responsibility to a plaintiff, except incases where the defendant is found to have undertaken to exercise reasonablecare in circumstances which are analogous to, but short of, contract, and it isforeseeable that the plaintiff will rely on that undertaking. If that is the casethen, subject to any countervailing policy factors, a duty of care will arise. Inother cases, the law will deem the defendant to have assumed responsibilitywhere it is fair, just and reasonable to do so: Attorney-General v Carter, at pp168 – 169 (paras [23] – [27]). Whether it is fair, just and reasonable to deeman assumption of responsibility and then a duty of care will depend on acombination of factors, including the assumption of responsibility for the task,any vulnerability of the plaintiff, any special skill of the defendant, the needfor deterrence and promotion of professional standards, lack of alternative1 Rolls-Royce New Zealand Ltd v Carter Holt Harvey Ltd [2005] 1 NZLR 324 (CA).means of protection and so on – that is, essentially the matters discussed aboveat paras [58] – [65]. Wider policy factors will also need to be taken intoaccount.[64] As Mr McGill submits, it is necessary to review a combination of factors todetermine whether it is fair, just and reasonable to deem an assumption ofresponsibility and then a duty of care. In his closing submissions, Mr McGill submitsthe relevant combination of factors in this case is as follows.[65] First, in the course of many meetings with the shareholders, Mr Chiemacknowledged that he was responsible for the works that needed to be undertaken tolift the abatement notice. This is said to be consistent with Mr Chiem assuming theresponsibility of a project manager. Mr McGill also placed reliance on the invoicefrom Parakai to FCL referred to above.[66] Secondly, Mr McGill submits that two of the consultants working on thedevelopment, Mr Brodie from ENGEO and Mr Lee from Airey, understood thatMr Chiem had "control of the site, and was managing the development". Both gaveevidence to this effect.[67] Thirdly, Mr McGill contends that FCL was "vulnerable", in that it owed anon-delegable duty to all future purchasers of the land as to its stability and suitabilityfor residential construction.2 Mr Chiu, Mr Wong, and Mr Liu did not have theexperience to do or monitor the earthworks themselves and they relied on Mr Chiemto oversee the contractors engaged to do the works.[68] Thus Mr McGill contends that it is fair, just and reasonable to deem Mr Chiemassumed responsibility to project manage the development and impose a duty of careaccordingly.[69] Mr Latton submits that the requisite combination of factors for the impositionof a duty of care did not exist. I accept that submission. My reasons, whichincorporate most of Mr Latton's points, are these.2 Mount Albert Borough Council v Johnson [1979] 2 NZLR 234 at [179].Discussion[70] First, I am satisfied that Mr Chiem undertook to provide the service describedabove, that is to be FCL's point of contact on-site, essentially a conduit, relayinginformation and documents as required. This was Mr Chiem's evidence. Mr Wong'sevidence was consistent with this, and was to the effect that Mr Chiem was to"oversee" the development. Likewise, Mr Chiu's evidence, which was that Mr Chiemwas to be "looking after the contractors" that FCL engaged.[71] There is some evidence supporting FCL's contention that Mr Chiem assumeda larger role than this. In that respect, I refer particularly to Mr Chiem engagingShepherd and Mr Richards to do earthworks on-site, and to his execution, on FCL'sbehalf, of contractual documents with Airey and Coffey. However, there was a broadmeasure of agreement between the shareholders that Mr Chiem was not appointed asthe project manager of the development, and they did not perceive him to be such.Mr Chiem denied that he undertook or said that he would undertake such a role.Mr Wong's evidence was that the shareholders did not "agree to engage [Mr Chiem]as the project manager". Mr Chiu's evidence was to the same effect.[72] Secondly, Mr Chiem was not possessed of any special skill or expertiseequipping him to act as a project manager of a development of this kind. Mr Chiemhad no experience in the development or subdivision of land and, importantly, all ofthe shareholders knew that. Mr Liu's evidence was that he knew Mr Chiem did nothave the required skills. Mr Wong's evidence was to similar effect. On the otherhand, FCL had the services of Terra and Airey who were qualified to act as projectmanager.[73] Mr McGill relied on what he said was Mr Chiem's contemporaneousundertaking to attend to all matters required to lift the abatement notice. As I havesaid, Mr Chiem did give evidence at trial that he was responsible for this. However, Iam unable to take that evidence as anything more than an acknowledgment that he wasto be the FCL representative in this process. The abatement notice was lifted,principally through the endeavours of Terra and ENGEO, with some assistance fromAirey also. It was they who were able to satisfy the Council as to the state of the siteand to assure the Council that future earthworks would proceed in accordance with theresource consent. The contemporaneous documents do not evidence Mr Chiemundertaking any substantive role in the discussions with the Council.[74] Mr McGill also submits, correctly, that Mr Brodie and Mr Lee both gaveevidence (in chief at least) that they considered Mr Chiem to be the project managerfor the development. However, this evidence did not withstand cross-examination.[75] Although Mr Brodie's evidence-in-chief was that he received most of hisinstructions on the project from Mr Chiem, in cross-examination Mr Brodieacknowledged that most of ENGEO's communications on significant matters werewith Terra. For instance, ENGEO remitted its proposal to carry out a geotechnical andenvironmental suitability assessment of the site to Terra. ENGEO received andresponded to requests by Terra for information. ENGEO liaised with Terra and otherparties regarding silt control measures on-site. Mr Brodie acknowledged to Mr Lattonthat there were no instructions from Mr Chiem in the contemporaneouscorrespondence. Mr Brodie also accepted in cross-examination that thecorrespondence and communications at the time were those to be expected between aconsultant, such as ENGEO, and the engineer to the contract, Terra.[76] Nor did Mr Lee's evidence that he perceived Mr Chiem to be the projectmanager withstand cross-examination. On the contrary, as I have said, Airey's termsof engagement provided for Airey to undertake many services for FCL, consistentlywith those Mr Anderson said he would expect a project manager to perform. AndMr Lee did attend to many of the matters required by the Airey contract. Hecommunicated with the Council; he arranged site meetings, including with Councilrepresentatives; he liaised with the surveyors who had been engaged; he did prepare acontract for Shepherd; and he approved Shepherd's claims for progress payments,totalling more than $600,000.[77] Mr Lee and Mr Fisher did ask Mr Chiem to attend to various matters from timeto time. For instance, Mr Lee asked Mr Chiem to arrange for the manufacture of"settlement markers", these being a means to establish the extent to which fill issettling and compacting. As far as I can ascertain, this is one of the few actions Mr Leedid ask Mr Chiem to take, and Mr Chiem did as requested.[78] Mr Fisher asked Mr Chiem to provide photographs of the works beingconducted on-site, in lieu of Mr Fisher visiting the site. Mr Chiem did so. Mostimportantly of all, Mr Chiem also received instructions from Mr Fisher as to whichparts of the site were ready for fill to be placed, matters such as compacting the fill,regarding contamination testing of fill on and brought to the site, and such like.Mr McGill put it to Mr Chiem that his receipt of these instructions constitutedevidence that he, Mr Chiem, was directing or instructing works on-site. However,Mr Chiem's evidence was that he was receiving this information so that he could relayit to Mr Shepherd and his employees, and that he did so.[79] Drawing all of these threads together, the position is that all the shareholdersagree Mr Chiem was to act as FCL's client representative on-site but not as projectmanager. FCL and its shareholders knew Mr Chiem did not have the skills requiredto perform that role. On the contrary, FCL engaged properly qualified experts to workon the development. There are certainly instances of Mr Chiem going beyond his roleas a point of contact, but I am not satisfied the circumstances are such that it would befair, just and reasonable to impose the duty of care alleged.[80] In case I am wrong, I turn now to discuss whether FCL would have establisheda breach of the duty of care.Breach[81] FCL's allegation of breach of the duty of care it alleges is as follows:In breach of the duty of care, the Earthworks [defined as those between24 October 2017 and 5 December 2017] undertaken under the direction of theplaintiff were conducted to a poor standard and with a lack of quality control,in respect of the nature of the fill materials placed on the site.[82] FCL's pleading includes particulars of the breach alleged. These are thatMr Chiem allowed or directed:(a) the importation and placement of "inappropriate" fill onto the site;(b) inadequate "discing" of existing fill on the site;(c) inadequate compacting of imported fill;(d) the placement of fill without appropriate testing of an underlying failedlayer;(e) the incorporation of uncertified clay stockpiles into existing soils on theeastern side of the site;(f) works to be undertaken without the removal of vegetation;(g) the importation of fill that had not been the subject of contaminationtesting; and(h) the stockpiling of fill containing concrete and steel along the easternboundary of the site.[83] In short, FCL's contention is that, during the period pleaded, Mr Chiem allowedor directed earthworks on-site which were conducted to a poor standard, and that therewas also a lack of quality control in respect of fill placed on-site.[84] In the main, FCL's case on breach and these particulars are based on the letterfrom Mr Fisher of Coffey to Mr Hsu dated 11 May 2018, referred to in [49] above("Coffey letter"). It is this letter that FCL relies on to establish that the earthworkson-site at the time were deficient. It is in this context that Mr Fisher's evidence wouldhave been highly relevant. Also, no expert evidence was called as to geotechnicalmatters which might have allowed an independent assessment of the state of the siteas of 5 December 2017.[85] In lieu of Mr Fisher, FCL called Mr Bosselmann, Mr Fisher's supervisor atCoffey at the relevant time, as a witness. However, although he signed the Coffeyletter under a note indicating that he had reviewed and authorised it, Mr Bosselmannhad little, if any, familiarity with the project and had never visited the site. Nor hadMr Bosselmann reviewed Mr Fisher's file before he gave evidence. Mr Bosselmann'sevidence was based on his recollection of his discussions with Mr Fisher, who he saidconsulted him from time to time.[86] Before I go any further, I should say something about the evidence generallyrelating to the earthworks on-site after 24 October 2017.[87] Mr Fisher visited the site on a number of occasions. Mr Bosselmann'sevidence was that a site visit would not usually be for longer than an hour. Mr Fisheralso sent various emails to Mr Richards, Mr Lee and Mr Chiem regarding matters suchas preparation of the site, which areas were suitable or ready for filling, surveying(which Mr Lee organised), contamination testing which Coffey's environmental teamwas to undertake, and so on. As I have said, Mr Chiem's evidence was, to the extenthe was given instructions as to earthworks on-site, he relayed them to Shepherd andMr Richards.[88] On 21 November 2017, Mr Fisher emailed Mr Chiem and Mr Lee and said hewished to have a meeting at his office on 24 November 2017 to discuss:.. earthworks methodology going forward and what we need to see in orderfor us to provide completion reports.At the moment, as the engaged consultant on the job, we feel that our requestsaren't being met and therefore won't be in a position to sign anything off.[89] Mr Lee forwarded Mr Fisher's email to Mr Sun and Mr Pang the same day (see[37] above). Mr Lee also said that Mr Fisher had tried to advise Mr Chiem of Coffey'srequirements but that those requirements were not being met.[90] Mr Chiem's response to this email from Mr Fisher was to require a meeting ofall interested parties, on-site, and no later than 23 November 2017. The meeting tookplace on the 23rd.[91] The following day, Mr Fisher emailed Mr Chiem the locations of two areasthat had been inspected and cleared for filling and, amongst other things, said he wascompiling "an earthworks methodology that we wish to be implemented".[92] As it turned out, Mr Fisher did not forward the methodology to Mr Chiem until5 December 2017, some 10 days later, and the day earthworks ceased. This made themethodology of little practical use, to Mr Chiem at least. It is also difficult to reconcileMr Fisher's delay in sending the methodology, and Mr Lee's authorisation ofsubstantial progress payments to Shepherd, with a sense that the earthworks wereseriously awry. Nor am I able to detect any significant concerns in thecontemporaneous correspondence, prior to the email of 21 November 2017. I notealso that, in his covering email of 5 December 2017, Mr Fisher said that since themeeting on 23 November 2017, "we have started moving in the right direction". Themethodology itself refers to matters such as keeping appropriate separation betweenpiles of fill, and where the contractor should pile material such as vegetation andconcrete. It does not establish any breach of the duty alleged.[93] Mr McGill questioned Mr Bosselmann about the circumstances in which theCoffey letter, that is the 11 May 2018 letter, came to be written. Mr Bosselmanninitially said it was because Coffey "had to bring things to a head" as works were notbeing undertaken "in accordance with [Coffey's] prescribed methodology". However,as Mr Bosselmann subsequently acknowledged in cross-examination, this evidencecould not be correct, because earthworks on the site had ceased six months prior.Mr Bosselmann then said he thought Coffey had supplied the letter as Mr Hsu wishedto understand events and what was going to be required to get the site to a point whereearthworks could resume.[94] I turn now to consider the extent to which the allegation of breach, and theparticulars pleaded, are borne out by the evidence.Particular (a)[95] Mr Bosselmann confirmed in cross-examination that he could not identify anymatter raised in the Coffey letter to the effect that "inappropriate" fill, by which Iassume is meant fill that did not comply with the Council's cleanfill requirements, wasimported and placed on the site after 24 October 2017. The Coffey letter refers to fillfrom subdivisions in Penihana and Waikumete. The fill from these sites met theCouncil's requirements, although only just in the case of the fill imported from thePenihana site.Particular (b)[96] Mr Fisher states in his letter that on 1 and 2 November 2017:Existing fill along the eastern boundary was disced to condition it prior tore-compaction. Contractors disc's were inadequate (too lightweight) anddidn't penetrate deep enough into the fill.[97] In an email to Mr Chiem dated 2 November 2017, Mr Fisher said that thecontractor's discs were only "scratching the surface" and that "you will need to tryagain when it is dry perhaps with a heavier set of discs". Mr Chiem's unchallengedevidence on this point was that he had relayed Mr Fisher's advice to Mr Shepherd whodid or said he would hire discs of a greater depth. There is no evidence of anysubsequent advice from Mr Fisher to Mr Chiem that the discing remained or continuedto be inadequate.Particular (c)[98] There are statements in the Coffey letter to the effect that on, 13 to15 November 2017, some fill was discovered to be compacted insufficiently. Thatentry also indicates that the contractor began to "rip up" this fill, presumably tocompact it again.Particulars (d), (e) and (f)[99] There are statements in the Coffey letter bearing out these particulars. Theentry for 17 November 2017 refers to placement of fill on the eastern boundary of thesite without re-testing an underlying failed layer. The entry for 27 November 2017refers to incorporation of clay, and the entry for 28 and 29 November 2017 states thatvegetation had not been removed and was being mixed into existing fill.Particular (g)[100] The Coffey letter states that, on 1 December 2017, fill was imported to sitefrom Waikumete without prior testing for contamination. The letter also states thattesting on-site indicated that the fill met cleanfill criteria. Rather, the complaint wasthat fill had been mixed into unchecked stockpiles on-site. Accordingly, thecontamination point is not borne out by the letter, but plainly the fill should not havebeen mixed into unchecked stockpiles.Particular (h)[101] The entry in the letter for 5 December 2017 is that the majority of small moundsof fill placed along the eastern boundary of the site were unsuitable for bulk filling dueto the presence of concrete and steel. That may well be correct but the earthworksmethodology forwarded by Coffey anticipated the presence of such materials inimported fill. The important point step was to remove that material, which may wellbe what was intended by stockpiling it as the letter records had been done.[102] To conclude on this point, parts of the Coffey letter do suggest that theearthworks conducted in the relevant period were deficient in some of the respectsparticularised, but that is as far as it goes. However, that letter is the sole evidencethat those deficiencies occurred, and when, and there is no evidence that they persistedor remained as of 5 December 2017. Nor is there evidence bearing out the allegationas to a lack of quality control in respect of fill brought to site."Allowed or directed"[103] In addition, the allegation of breach is that Mr Chiem directed the earthworksand/or that he allowed or directed them. There is no evidence that Mr Chiem"directed" the earthworks, or knowingly allowed deficient work to continue.Mr Fisher was directing what needed to be done. Had Mr Chiem been acting as projectmanager, it most certainly would have been his obligation to ensure those instructionswere faithfully relayed to the contractor, and to be diligent in monitoring them. In myview, those were his obligations in any event. However, Mr Bosselmann's evidencewas that the deficiencies identified in the Coffey letter were those for which theearthworks contractor would be responsible. Indeed, the Coffey letter expressly laysthe blame for many of the issues on the contractor.[104] In cross-examination, Mr McGill pressed Mr Chiem repeatedly on whether hehad relayed Mr Fisher's instructions to the contractor and understood that they wouldcomply with them. Mr Chiem was adamant that he had relayed those instructions andhe did expect them to be complied with. Passages of Mr McGill's cross-examinationof Mr Chiem give the flavour of it:3Q. We'll move on, page 3425 please Mr Chiem. Now in the middle ofthe page there's a record of an email from you to Mr Fisher on the29th of November 2017, correct?A. That's correct.Q. And over the page on 3426, 3427, 3428, 3429 and 3430 are somephotos, just have a look at those.A. So when they start to do the excavation at the site I took the photosand sent to Mr Fisher and waiting for his reaction.Q. Thank you, you've answered my question already. So those are yourphotos and you sent them to Mr Fisher and then at the top of page3425 is Mr Fisher's response to you, on the same day, correct?A. That's correct.Q. Take a minute to read it.A. Yep, I know that one.Q. You know this one. So this is Mr Fisher telling you what to do on site,again, correct?A. So at the season, at the time, it was dry season so therefore is missionto try to compact according to the advice of Mr Fisher.Q. It's just Mr Fisher telling you what needs to happen on site though,isn't it?A. That's true so once he's seen the photos he will tell the contractor whatto do and approach how to do it.Q. And did you tell Mr Shepherd what to do when you'd seen thisinstruction?A. So I already know that Mr Shepherd understand the situation and hewent on ahead and hire the water blaster to put, soften the ground sothat he can continue to work.Q. But did you tell Mr Shepherd what Mr Fisher had instructed?A. Yes, I have sent a message.3 Notes of Evidence at 346 – 348.Q. Did you tell Mr Richards also, was he on site then?A. Yes, he aware of the procedure.THE COURT:Q. No, that wasn't the question, the question was whether you toldMr Richards?A. Yes, I have told Mr Richards because at that time the ground is veryhard and the reason....Q. Please turn to page 3451, the bottom half of the page is an email fromMr Lee to Timothy O'Grady at the Auckland Council on the 30th ofNovember 2017, copied to you, just take a minute to read thatMr Chiem, bottom half?A. Yes, I have witnessed this email, I have seen this email.Q. Do you want to take a minute just to read it?A. So I don't know about the issue with this, but whatever I received, aproblem, I will forward it to the geotech engineer and Mr Lee.Because I have no expertise in the technical issues and I will forwardall the technical stuff to them.Q. This is an email from Mr Lee to the council giving them an update onwhat's happening on the site, isn't it?A. That's correct.Q. And you can see in the fourth bullet point where Mr Lee says to thecouncil: "We have advised Bon to shape up the north-eastern cornerof the site to ensure that flows will discharge back towards the SRP."So Mr Lee has given you an instruction to do that work, correct?A. So I have instructed Tom Shepherd's staff to come and correct thepoint, settlement as mentioned in the fourth point.Q. And Mr Lee didn't tell Mr Shepherd to do that work did he?A. So only the professional can act to do carry those work and at the endMr Lee will come and inspect the result of the work done.Q. And the next sentence says: "We have also advised Bon to widen theSRP which can be completed to provide more storage, et cetera." Soagain, Mr Lee telling you what needs to be done, correct?A. It's the usual practice Mr Lee will tell, it's the normal practice thatMr Lee will tell me the instruction and I will pass on the instructionto Mr Shepherd and otherwise his staff as well.Conclusion on breach[105] To conclude, had the duty of care FCL alleges been established, I would nothave found that Mr Chiem had breached it.[106] On the evidence before me, it is not possible to conclude that the earthworkson-site between 24 October 2017 and 5 December 2017 were conducted in a deficientmanner or, if they were, that those deficiencies were not remedied. There is also noevidence that would lead me to conclude that Mr Chiem directed or allowed them.[107] For the sake of completeness, I should mention Mr Anderson's on this topic,such as it was. It appeared from Mr Anderson's evidence that he was not sufficientlyfamiliar with the many relevant communications post-August 2017. Mr Anderson wasthus unable to offer an informed opinion on what might have been expected of areasonable and prudent project manager throughout and whether Mr Chiem had actedconsistently with this standard.Damages[108] Having reached these conclusions, it is unnecessary for me to consider the nextcontroversial topic which is the damages claimed, and the extent to which these toowere proved.[109] Briefly, FCL's evidence as to its damages claim was given by Mr Hsu. Hisevidence was that the damages claimed comprise two main components.[110] The first component comprises 50 per cent of the costs estimated by Yakka forpreliminary and general items, essentially to do with re-establishment of the site, andthe costs of supplying, importing and receiving 25,000 m3 of fill. The total claim forthis first component is $1,751,223.76, with the cost of the fill estimated to be$1,566,750.[111] The second component of the claim totals $1,040,509.32. This is Yakka'sestimate in respect of the cost of the earthworks said to be required to remediate thesite. This sum includes more than $620,000 for the uplifting and disposal of unsuitablematerial, more than $200,000 for discing and associated works, and approximately$150,000 for excavating material.[112] In case it assists the parties, I would not have declined an award of damagessolely because the claim is based on estimates. My principal reservation regarding theclaim was that I could not be sure from Mr Hsu's evidence that the sum claimed wasconfined to the costs attributable to restoring the site to its 24 October 2017 state, andpossibly such associated earthworks as were required in the course of that restoration.My impression of Mr Hsu's evidence was that the damages claimed included acomponent of betterment for which Mr Chiem could not be liable.Result[113] I dismiss the plaintiff's claim against the defendant. The agreement on whichthe claim is based is not proved on the evidence before me.[114] I dismiss the defendant's counterclaim against the plaintiff. The duty of carealleged is not proved. If I am wrong in that, FCL has not proved a breach of that duty.Costs[115] In the absence of agreement, the parties may make submissions on costs.Post-script[116] In July 2022, Mr Latton advised that he considered documents that Mr Chiuhad recently discovered in the related proceeding to which I have referred wererelevant to the issues of credibility, and particularly Mr Chiu's. That memorandumled to the provision of other memoranda, and the documents themselves. For theavoidance of doubt, I record that this judgment is based on the evidence presented attrial and I have taken no account of subsequently received material.Peters J