CAPITAL AND COAST DISTRICT HEALTH BOARD v BECA CARTER HOLLINGS & FERNER LTD [2020] NZHC 1083

CAPITAL AND COAST DISTRICT HEALTH BOARD v BECA CARTER HOLLINGS & FERNER LTD [2020] NZHC 1083

Adjournment was granted but limited to a four week postponement (trial move from 14 September 2020 to 12 October 2020) because the interests of justice required a short additional period for experts to prepare while avoiding loss of the allocated multi-week trial slot and further delay into 2021; the Court found...

Source-derived case information.

Citation
CAPITAL AND COAST DISTRICT HEALTH BOARD v BECA CARTER HOLLINGS & FERNER LTD [2020] NZHC 1083
Parties
Plaintiff: Capital and Coast District Health Board; First Defendant: Beca Carter Hollings & Ferner Ltd; Third Defendant: The Fletcher Construction Company Ltd; Fifth Defendant: R P Belbin; Sixth Defendant: Crane Enfield Metals Pty Ltd trading as Crane Copper Tube; Seventeenth Defendant: Mico New Zealand Ltd
Court
High Court
Jurisdiction
New Zealand
Judgment Date
21 May 2020
Procedural Posture
Civil Construction Defect / Negligence / Contract / Pre Trial (application for Adjournment)
Outcome
Application for adjournment granted in part; trial start moved from 14 September 2020 to 12 October 2020 (four week adjournment)
Legal Topics
Adjournment, Expert Evidence, Discovery, Trial Scheduling, COVID 19 Impact on Court Proceedings, Consumer Guarantees Act
Construction Law Negligence (professional) Contract Law Civil Procedure Adjournment Expert Evidence Discovery Trial Scheduling +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Capital and Coast District Health Board

Plaintiff

Beca Carter Hollings & Ferner Ltd

First Defendant

The Fletcher Construction Company Ltd

Third Defendant

R P Belbin

Fifth Defendant

Crane Enfield Metals Pty Ltd trading as Crane Copper Tube

Sixth Defendant

Mico New Zealand Ltd

Seventeenth Defendant

Procedural Posture

Civil Construction Defect / Negligence / Contract / Pre Trial (application for Adjournment)

  1. 1 Whether the 10 week trial should be adjourned due to late evidence and changed allegations and COVID-19 travel restrictions
  2. 2 Whether Australian-based experts' inability to travel justifies a long adjournment
  3. 3 How to balance interests of justice, court resource constraints and parties' prejudice in light of pandemic and remote hearing options

Ratio Decidendi

Adjournment was granted but limited to a four week postponement (trial move from 14 September 2020 to 12 October 2020) because the interests of justice required a short additional period for experts to prepare while avoiding loss of the allocated multi-week trial slot and further delay into 2021; the Court found remote and alternative measures available, plaintiff's lateness was regrettable but insufficient to justify a longer adjournment, and parties must use technology and cooperate to mitigate pandemic effects.

Court Disposition

Application for adjournment granted in part; trial start moved from 14 September 2020 to 12 October 2020 (four week adjournment)

Orders

  • Trial commencement moved to 12 October 2020 (ten week estimate remains)
  • First, third and seventeenth defendants to file briefs of evidence by 20 July 2020