CUSTOM STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD [2018] NZCA 36

CUSTOM STREET HOTEL LTD v PLUS CONSTRUCTION NZ LTD [2018] NZCA 36

Formal suspension by the engineer is not a precondition to a contractor's right to terminate under NZS 3910:2003 cl 14.3.3; the right to suspend and the right to terminate are triggered once the 10-working-day remedy period has expired and suspension is available. Clauses 14.2.3 and 14.2.4 require completion of the...

Source-derived case information.

Citation
[2018] NZCA 36
Parties
Appellant: Custom Street Hotel Limited; First Respondent: Plus Construction NZ Limited; Second Respondent: Plus Construction Co Limited
Court
Court of Appeal
Jurisdiction
New Zealand
Judgment Date
7 March 2018
Procedural Posture
Commercial Appeal From Arbitration (court of Appeal) / Court of Appeal Judgment (appeal Dismissed)
Outcome
Appeal dismissed
Legal Topics
Termination, Default Notices, Suspension, Performance Bond Certification, Interpretation of NZS 3910:2003, Remedies, Costs
Contract Law Construction Law Arbitration Law Security for Performance (performance Bond) Termination Default Notices Suspension Performance Bond Certification +3 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Custom Street Hotel Limited

Appellant

Plus Construction NZ Limited

First Respondent

Plus Construction Co Limited

Second Respondent

Procedural Posture

Commercial Appeal From Arbitration (court of Appeal) / Court of Appeal Judgment (appeal Dismissed)

  1. 1 Whether the contractor's breach must be repudiatory to disentitle it from terminating
  2. 2 Whether formal suspension by the engineer is a precondition to termination under cl 14.3.3 or the CRA
  3. 3 Whether the principal can recover additional cost of completion prior to completion under cls 14.2.4 and 14.2.5

Ratio Decidendi

Formal suspension by the engineer is not a precondition to a contractor's right to terminate under NZS 3910:2003 cl 14.3.3; the right to suspend and the right to terminate are triggered once the 10-working-day remedy period has expired and suspension is available. Clauses 14.2.3 and 14.2.4 require completion of the works before the engineer's cost certification and any wash-up payment for additional cost of completion can be made. The arbitrator's factual findings that Plus had not repudiated and validly terminated must be respected on appeal.

Court Disposition

Appeal dismissed

Orders

  • Appeal dismissed
  • Appellant must pay respondents one set of costs for a standard appeal on a band A basis and usual disbursements