SANSON AND ANOR v EBERT CONSTRUCTION LIMITED [2015] NZHC 2402
The payments made by BOSI under the Direct Agreement were advances of TPL's funds and functioned to reduce TPL's indebtedness to Ebert; those advances and the transfer of the apartment were transactions of TPL entered into within the restricted/specified period while TPL was insolvent; Ebert failed to prove the cumulative s296(3) defence (good faith and lack of reasonable grounds to suspect insolvency), so recovery under s295 is ordered.
- Citation
- [2015] NZHC 2402
- Parties
- Applicant (liquidator): Craig Alexander Sanson; Applicant (liquidator): David John Bridgman; Respondent: Ebert Construction Limited
- Court
- High Court
- Jurisdiction
- New Zealand
- Judgment Date
- 6 October 2015
- Procedural Posture
- Company Liquidation Voidable Transactions / Judgment (high Court)
- Outcome
- Application granted: transactions set aside and respondent ordered to repay sums received; leave reserved on interest and costs
- Legal Topics
- Voidable Transactions, Preferential Payments, Set Off, Direct Payment Agreements, Pari Passu Rule, Insolvency Defences
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Craig Alexander Sanson
Applicant (liquidator)
David John Bridgman
Applicant (liquidator)
Ebert Construction Limited
Respondent
Procedural Posture
Company Liquidation Voidable Transactions / Judgment (high Court)
Legal Issues
- 1 Whether payments made by financier BOSI were transactions of the company (s292)
- 2 Whether transfer of apartment occurred within specified period and is a transaction under s292
- 3 Whether TPL was insolvent at time of the transactions
Ratio Decidendi
The payments made by BOSI under the Direct Agreement were advances of TPL's funds and functioned to reduce TPL's indebtedness to Ebert; those advances and the transfer of the apartment were transactions of TPL entered into within the restricted/specified period while TPL was insolvent; Ebert failed to prove the cumulative s296(3) defence (good faith and lack of reasonable grounds to suspect insolvency), so recovery under s295 is ordered.
Court Disposition
Application granted: transactions set aside and respondent ordered to repay sums received; leave reserved on interest and costs
Orders
- Orders setting aside the Transactions: payment of $499,226.50 dated 18 November 2008, transfer of Apartment B401 and accessory unit AU40 treated as reduction of indebtedness of $540,000, and payment of $564,665.40 dated 21 November 2008
- Order that Ebert Construction Limited pay to the liquidators the sum of NZD 1,603,891.90 pursuant to s295 Companies Act 1993
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment