H INFRASTRUCTURE LIMITED (IN RECEIVERSHIP AND IN LIQUIDATION) v WORLEY NEW ZEALAND LIMITED [2022] NZHC 1316

H INFRASTRUCTURE LIMITED (IN RECEIVERSHIP AND IN LIQUIDATION) v WORLEY NEW ZEALAND LIMITED [2022] NZHC 1316

Worley breached its express warranties in cl 3.3 and schedule 2 by providing a tender design that did not 'suit' the URD and lacked sufficient detail to allow HIL to identify and price costs and risks; clause 20.5 did not bar recovery of the base value of direct losses caused by that breach; HIL proved specified...

Source-derived case information.

Citation
[2022] NZHC 1316
Parties
Plaintiff: H Infrastructure Limited (in receivership and in liquidation); Defendant: Worley New Zealand Limited
Court
High Court
Jurisdiction
New Zealand
Judgment Date
3 June 2022
Procedural Posture
Breach of Contract (warranty in Pre Bid Consultancy Agreement) / Final Judgment (trial)
Outcome
Judgment for plaintiff in part: plaintiff awarded damages for proved direct losses; claim for overheads dismissed; defendant entitled to set-off; interest and costs reserved for further submissions.
Legal Topics
Breach of Warranty, Damages, Contract Interpretation, Exclusion Clauses, Indemnity, Contributory Negligence, Professional Services Liability
Contract Law Construction Law Commercial Law Breach of Warranty Damages Contract Interpretation Exclusion Clauses Indemnity +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

H Infrastructure Limited (in receivership and in liquidation)

Plaintiff

Worley New Zealand Limited

Defendant

Procedural Posture

Breach of Contract (warranty in Pre Bid Consultancy Agreement) / Final Judgment (trial)

  1. 1 Whether Worley breached warranties in cl 3.3 of the PBCA by providing a tender design that did not suit the URD
  2. 2 Whether clause 20.5 of the PBCA excluded recovery of HIL's claimed losses
  3. 3 Quantum and causation of claimed items of loss and recoverability of overheads

Ratio Decidendi

Worley breached its express warranties in cl 3.3 and schedule 2 by providing a tender design that did not 'suit' the URD and lacked sufficient detail to allow HIL to identify and price costs and risks; clause 20.5 did not bar recovery of the base value of direct losses caused by that breach; HIL proved specified items of loss in part but failed to prove claimed overheads and contributory negligence was not established.

Court Disposition

Judgment for plaintiff in part: plaintiff awarded damages for proved direct losses; claim for overheads dismissed; defendant entitled to set-off; interest and costs reserved for further submissions.

Orders

  • Worley New Zealand Limited breached the PBCA warranties and H Infrastructure Limited is awarded damages for proved direct losses in the sum of NZD 777851.78.
  • H Infrastructure Limited's claim for on-site and off-site overheads is dismissed for lack of proof.